Window Replacement at USCG Station Ft. Pierce

Closed Solicitation Posted

Solicitation number
30310PR240000003
Agency
Coast Guard Department of Homeland Security
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
R499 Support- Professional: Other
Place of performance
Fort Pierce, Florida 34949, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This combined synopsis and solicitation requests fixed price proposals to remove existing windows and install new windows at the United States Coast Guard Station in Fort Pierce, Florida. The Coast Guard seeks a contractor to remove seven windows from three buildings and install new single hung and mullion windows per the specifications provided. Proposals are due by April 1, 2024 and will be evaluated based on past performance and price to award the contract to the best value offeror by April 10, 2024. A pre-bid site visit will be held on March 21 and questions are due by March 25.

This is a total small business set-aside with a NAICS code of 236220 for commercial and institutional building construction. The place of performance is 900 Seaway Drive in Fort Pierce, Florida, with all work to be completed by the contractor between March and October 2024 utilizing labor, materials, and equipment provided at their own expense. The contractor must comply with construction wage rates, safety, and other requirements and be registered in SAM under the applicable NAICS codes to be considered for the award.

Notice text

This combined synopsis/solicitation for services prepared in accordance with the format in subpart 12.6 of the Federal Acquisition Regulation (FAR) as supplemented with additional information included in this notice. This synopsis/solicitation is being advertised as Small Business Set-Aside only. This announcement constitutes the only solicitation; no separate written solicitation will be issued.

The solicitation number is 30310PR240000003

Applicable North American Industry Classification Standard (NAICS) codes are:  236220

Commercial And Institutional Building Construction

This requirement is for a fixed price contract.  The contract will be awarded using simplified acquisition procedures in accordance with FAR part 13 and part 15
 

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, Best Value.
 

When submitting your proposals, request a price breakdown of the following:

  1. Cost of labor and supervision
  2. Cost of materials and equipment needed to perform the work.

Prospective contractors shall also provide along with your proposal past performance documents which will be used to determine expertise to perform such work.

Contract will be awarded to the vendor who can perform the work outlined in the provided SOW in the time frame needed by unit.  Past Performance and Cost factors will also be used when selecting the award.

Anticipated award date: 10 business days after close of solicitation, OOA 10 April 2024

Quotes are to be received no later than close of business (2 p.m.) on 01 April 2024. Quotes can be email to:  Mehdi.Bouayad@uscg.mil

Quotations sent via the US Postal Service or hand delivered should be sent to:

Commanding Officer
USCG Base Miami Beach (P&C)
Attn: Mehdi Bouayad

909 SE 1st Ave, Room 512

Miami, FL 33131.

Telephone requests of quotes, will not be accepted, a formal notice of changes (if applicable) will be issued in Beta.Sam.Gov (SAM.gov | Workspace)

***** SITE VISIT****

Thursday Mar 21 2024 AT 10:00am AT PROJECT SITE (USCG Station Ft. Pierce)

POC: MKC Alexander Kull

Email: Alexander.R.Kull@uscg.mil

Phone: 217-273-1543

 XI. SCOPE OF WORK: United States Coast Guard Station Fort Pierce requires replacement to the unit Communications room, CO office, and XPO Office Windows.

Contractor shall provide all labor, materials, and equipment necessary to complete the following unless noted below:

In the performance of this contract, the contractor shall install the equipment to meet the below specifications at USCG Station Fort Pierce, FL.

Equipment:

  1.  7700 Series Single Hung 44 x 59 ½ in all designated locations
  2. Vertical Mull - 1 X 4 X 59 1/2 V White, With Clips where required

       

LABOR:

       1. Furnish all labor, materials and equipment necessary to complete the removal of existing windows and/or doors and the installation of listed windows and/or doors.

       2. Remove existing windows and/or doors from property.

LOCATION OF PROJECT:

USCG STATION FT. PIERCE

900 SEAWAY DRIVE

Fort Pierce, FL 34949

Q&A’s:  Questions concerning the work requested must be sent to Mehdi.Bouayad@uscg.mil by COB Monday 25 March 2024.  These Q&A’s will be answered and posted to this solicitation as an amendment prior to close of solicitation.

STORM PROTECTION

Should warnings of extreme weather (such as storm surge, wind of gale force) be issued, the

Contractor shall take every practicable precaution to minimize danger to personnel, the work

and adjacent property. Precautions shall include, but not be limited to, closing all openings,

removing all loose materials, tools and equipment from exposed locations, and removing or

securing fencing, scaffolding and other temporary work.

DELIVERY AND STORAGE

Equipment and materials shall be carefully handled, properly stored, and adequately protected

to prevent damage before and during installation, in accordance with the manufacturer's

recommendations. Damaged or defective items shall be replaced. Location of storage and

staging area shall be designated by the POC. The contractor will be responsible for security of

all materials and equipment.

RECEIPT OF MATERIALS

Shipment of equipment, materials, and supplies shall be addressed to the Contractor - not the

Government. The Contractor must be on hand to accept shipments; the Government will not

accept shipments.

CLEANUP

The Contractor shall keep the work area, including storage areas, free from accumulations of

waste materials on a daily basis and comply with all federal, state and local regulations

pertaining to the storage, transport and disposal of wastes. The Contractor shall not use Coast

Guard waste disposal facilities including garbage cans, trash piles or dumpsters.

SECURITY

Working Personnel List.

The Contractor shall provide the COR Chief Alexander Kull with a list of names of all personnel who will be working

on the site. The Contractor may submit a revised list at any time during the project. Only

personnel on the approved listing will be allowed on the site.

Personnel Identification.

All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either

the individual’s driver’s license, or a company issued ID. The identification must be laminated,

and show facial picture of the individual. Individuals without proper ID will be escorted off

the Coast Guard premises.

QUALITY

Quality of Contractor Furnished Material. Materials supplied by the Contractor shall be of a

quality conforming to applicable Federal specifications and lead and asbestos free.

WARRANTIES

All warranties and/or guarantees, either implied or expressed, for individual equipment shall

be endorsed to the Government.

FINAL INSPECTION AND ACCEPTANCE

When the work is complete and ready for final inspection, submit a written request to schedule

final inspection to the Government. Prior to such requests, all submittals must be complete and

approved. Such requests shall allow a minimum of two (2) days notice prior to final inspection

date.

SAFETY

General

The Contractor is wholly responsible for work site safety. The Contractor shall implement a

safety program that protects the lives and health of personnel in the service area, prevents

damage to property and avoids work interruptions. The Contractor shall provide appropriate

safety measures including but not limited to barricades, signs and signal lights as well as

complying with the requirements of all applicable Federal, State and Local safety laws, rules

and regulations.

Compliance

The Contractor is specifically required to comply with the requirements of the U. S. Army

Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version

available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety

plan shall become part of the contract requirements. Note: This review/acceptance does not in

any way relinquish the Contractor from responsibility for work site safety nor the obligation

to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other State or

Local safety law, rule or regulation applicable to the contract work. The Coast Guard will

cooperate fully with the Department of Labor (Occupational Safety and Health Administration)

in their enforcement of OSHA regulations.

 Safety Plan

The Contractor shall submit a written safety plan within seven (7) calendar days following

contract award. At a minimum, this plan shall describe the Contractor's general safety program

and identify specific safety provisions for hazards incidental to the contract work such as

elevated working surfaces, working over water, working from floating work platforms,

overhead crane operations or similar conditions of the work. This Safety Plan shall be approved

prior to commencing any work on site.

APPLICABLE FAR CLAUSES

FAR 52.213-4: 52.213-4 Terms and Conditions-Simplified Acquisitions (Other Than Commercial Items).

ATTACHED BY REFERENCE

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS

52.236-2 DIFFERING SITE CONDITIONS (APRIL 1984)

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APRIL 1984)

52.236-27 SITE VISIT (CONSTRUCTION) {FEB 1995)

Work hours: Monday through Friday, 0730 – 1800 (7:30 am – 6 pm) No weekends or Holidays authorized.

See attached applicable FAR Clauses by reference.

Offerors may obtain full text version of these clauses electronically at: www.arnet.gov/far

The following Homeland Security Acquisition Regulations (HSAR) are incorporated as addenda to this solicitation: HSAR 3052.209-70 Prohibition on Contracts with Corporate Expatriates (Jun 2006); Contracting Officers Technical Representative (Dec 2003) (COTR) HSAR 3052.237-72. Copies of HSAR clauses may be obtained electronically at http://www.dhs.gov.

Request Company’s Tax ID information and UEI number.

Vendors providing an offer must be registered in SAM (System for Award Management) prior to close of this solicitation. https://www.sam.gov/portal/public/SAM/. The vendors SAM registration must be in an “ACTIVE” status prior to award.

Vendors must ensure that the above listed NAICS codes are listed on their SAM registration to perform this type of service.

Attachments

Files attached to this notice, newest first
File Type Posted
SF_30- Amendment to Solicitation 001.pdf PDF
Questions and Answers.pdf PDF
20240129_SOW Comms window replacement.pdf PDF
Synopsis Solicitation 1.pdf PDF
20240129_SOW Comms window replacement.docx DOCX document

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity