DESCRIPTION OF WORK
The major items of work to be performed under the base bid include, but are not limited to the
following:

a. Installation of a geosynthetic liner system on part of the upstream slope and crest of Jadwin
Dam.  The liner system consists of geomembrane, geotextile, geogrid, and coarse aggregates. 
Excavation and placement of existing riprap and installation of new riprap is also required.

b. Installation of new piezometers.

c. Modifications to existing piezometers, settlement pipes, and horizontal pipes.
d. Removal of an existing USGS shed and modifications to the USGS pipe.

Files

Show all 12

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
W912BU21B0012 - Jadwin Dam Modification Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors