UT FLAP 2500(1) Taylor Mountain Road
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF21B000017
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- Not on record
- Place of performance
- Vernal, Utah 84078, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is for the rehabilitation and reconstruction of approximately 6.67 miles of Taylor Mountain Road located in Uintah County, Utah. The Department of Transportation Federal Highway Administration seeks to rehabilitate 4.95 miles and reconstruct 1.71 miles of the roadway to improve safety and correct roadway geometry through widening, alignment changes, and drainage improvements. Major work elements include cut and embankment slopes, embankment stabilization, aggregate base course, asphalt paving, clearing vegetation, shoulder stabilization, drainage structures including large and deep pipes and concrete headwalls, as well as pavement markings and signage updates. There are no stated evaluation criteria or important dates in the pre-solicitation notice.
There is no set-aside designated for this procurement. Significant quantities of work include 41 acres of clearing and grubbing, 18,000 cubic yards of embankment construction, 19,000 tons of aggregate base, 5 miles of full depth reclamation, and asphalt concrete paving. The notice provides no information on potential incumbents, budget ranges, NAICS or PSC codes. Key details include the quantities listed as well as the 6.67 mile length of roadway rehabilitation and reconstruction.
Notice text
2 versions
Update #2 · Latest ·
PROJECT DESCRIPTION: The UT FLAP 2500(1), Taylor Mountain Road project is located approximately 6 miles north of Vernal, UT in northeastern Utah. The project begins at the intersection of 2500 W and 3500 N and continues north for 6.67 miles to just past the Ashley National Forest (USFS) boundary. The existing roadway provides access to businesses, private residences, and the Ashley National Forest. The route is categorized as a rural minor collector in rolling terrain and is maintained by Uintah County. This project consists of the rehabilitation, restoration, and resurfacing (3R) of approximately 4.95 miles and reconstruction (4R) of
approximately 1.71 miles of road. Major work elements include widening the roadway to a consistent width and vertical and horizontal alignment changes to correct roadway geometry and improve safety. Construction will generally include cut slopes (bedrock and soil), embankment, deep patch embankment stabilization, aggregate base course, and paving. Improvements include clearing roadside vegetation, stabilization of shoulders, drainage improvements (including large pipes, deep pipes, and concrete headwalls), pavement markings, and updating signing. Select parking/pullouts and access road intersections will also be rehabilitated or reconstructed.
SIGNIFICANT QUANTITIES (Schedule A):
20101-0000 Clearing and Grubbing: 41 ACRE
20420-0000 Embankment Construction: 18,000 CUYD
30101-0000 Aggregate Base: 19,000 TON
30401-5300 Full Depth Reclamation: 5.0 MILE
40101-0600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL: 16,000 TON
MISCELLANEOUS:
Due to weather restrictions, on-site construction typically cannot occur until March.
It is anticipated this project will be advertised in October 2021 with construction between March 2022 and October 2022.
Estimated total cost is $6,000,000 to $8,000,000.
Update #1 ·
THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
PROJECT DESCRIPTION: The UT FLAP 2500(1), Taylor Mountain Road project is located approximately 6 miles north of Vernal, UT in northeastern Utah. The project begins at the intersection of 2500 W and 3500 N and continues north for 6.67 miles to just past the Ashley National Forest (USFS) boundary. The existing roadway provides access to businesses, private residences, and the Ashley National Forest. The route is categorized as a rural minor collector in rolling terrain and is maintained by Uintah County. This project consists of the rehabilitation, restoration, and resurfacing (3R) of approximately 4.95 miles and reconstruction (4R) of
approximately 1.71 miles of road. Major work elements include widening the roadway to a consistent width and vertical and horizontal alignment changes to correct roadway geometry and improve safety. Construction will generally include cut slopes (bedrock and soil), embankment, deep patch embankment stabilization, aggregate base course, and paving. Improvements include clearing roadside vegetation, stabilization of shoulders, drainage improvements (including large pipes, deep pipes, and concrete headwalls), pavement markings, and updating signing. Select parking/pullouts and access road intersections will also be rehabilitated or reconstructed.
SIGNIFICANT QUANTITIES (Schedule A):
20101-0000 Clearing and Grubbing: 41 ACRE
20420-0000 Embankment Construction: 18,000 CUYD
30101-0000 Aggregate Base: 19,000 TON
30401-5300 Full Depth Reclamation: 5.0 MILE
40101-0600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL: 16,000 TON
MISCELLANEOUS:
Due to weather restrictions, on-site construction typically cannot occur until March.
It is anticipated this project will be advertised in October 2021 with construction between March 2022 and October 2022.
Estimated total cost is $6,000,000 to $8,000,000.
Notice history
| Notice | Type | Posted |
|---|---|---|
| UT FLAP 2500(1) Taylor Mountain Road | Award Notice | |
| UT FLAP 2500(1) Taylor Mountain Road | Solicitation | |
| This notice | Pre-Solicitation | |
| UT FLAP 2500(1) Taylor Mountain Road | Pre-Solicitation | |
| UT FLAP 2500(1) Taylor Mountain Road | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity