About this opportunity
The U.S. Coast Guard is seeking electrical inspection and maintenance services for electrical systems at Floating Pier One, Base Ketchikan, with a specific focus on shore tie terminals and associated electrical lines at Berth 5. The procurement requires contractors to inspect all shore tie terminals for damage, corrosion, and moisture intrusion; perform repairs and sealing to prevent future moisture intrusion; test terminals for proper operation; inspect and clean electrical lines running from the FRC Floating Pier Isolation Transfer to shore tie terminals; and conduct Megger insulation resistance testing to identify potential failures. Contractors must be appropriately licensed for marine electrical work and comply with applicable electrical codes and safety standards. The contract will be awarded to the lowest priced technically acceptable contractor based on firm, fixed-price bids submitted on an FOB Destination basis that includes all shipping costs. The proposal deadline is March 13, 2026, at 3:00 PM Alaska Time, with inquiries directed to Senior Field Contracting Officer Deno Stamos at deno.a.stamos@uscg.mil.
This solicitation includes no set-aside designations and does not identify any incumbent contractors. The material quote estimate for shore tie terminal box repairs is capped at $5,000, with all quotes required to be submitted on a firm, fixed-price basis. The contractor must complete shore tie terminal inspection and maintenance within two weeks of contract award, complete electrical line inspection and grooming within three weeks of award, and submit the final written report with photographic evidence and Megger test results documentation within one month from the start of performance. Work will be performed at Floating Pier One, Base Ketchikan, Alaska 99901, with all deliverables submitted to USCG Ketchikan and payment to be made electronically within 30 net days upon submission of invoices and the completed DD-250 Material Inspection and Receiving Report to the USCG Finance Center using Invoice Routing Code SILC PCB-2.
Notice text
3 versions
Update #3 · Latest ·
EXTENDED PROPOSAL DUE DATE OUT TO 13 MARCH 2026 AT 3:00 PM ALASKA TIME
SEE ATTACHED SPECS/SCOPE OF WORK----
Scope of Work: Electrical Inspection and Maintenance – Floating Pier One, Base Ketchikan
1. Objective:
Provide inspection, maintenance, and repair services for electrical systems associated with Floating Pier One, Base Ketchikan, with a focus on shore tie terminals and associated electrical lines.
2. Location:
Floating Pier One, Base Ketchikan. Berth 5
3. Tasks:
A. Shore Tie Terminal Maintenance
- Inspect all shore tie terminals where vessels connect to shore power.
- Identify and document any damage, corrosion, moisture intrusion, or other deficiencies.
- Repair any identified issues to restore full functionality.
- Dry and seal all shore tie terminals to prevent future moisture intrusion.
- Test terminals for proper operation after repairs and sealing.
B. Electrical Line Inspection and Grooming
- Inspect the electrical line running from the FRC Floating Pier Isolation Transfer to the shore tie terminals.
- Clean and groom all accessible portions of the line, removing debris, corrosion, and contaminants.
- Conduct a thorough inspection for physical damage, wear, or potential failure points.
- Perform Megger (insulation resistance) testing on the electrical lines to identify any insulation breakdowns or other potential issues.
- Document all findings and provide recommendations for further action if required.
4. Deliverables:
- Written inspection report detailing findings, repairs performed, and recommendations for future maintenance.
- Documentation of Megger test results and any corrective actions taken.
- Photographic evidence of before and after conditions for all work performed.
5. Period of Performance:
- Shore Tie Terminal inspection and maintenance shall be completed within two (2) weeks from award of contract.
- Electrical line inspection, grooming, and cleaning shall be completed within three (3) weeks from award of contract.
- Final written report of findings and actions written(typed) and documented shall be submitted within one (1) month from the start of the period of performance.
6. Safety and Compliance:
- All work must comply with applicable electrical codes, safety standards, and Base Ketchikan requirements.
- All personnel must be appropriately licensed and qualified for marine electrical work.
Quote/Estimate: Quote or Estimate shall include materials going up to 5,000K for any repairs in the shore tie terminal box on the floating pier, but not to exceed.
Question: Could you quantify the shore tie terminals and cable lengths from Isolation Transfer to each Terminal to refine labor/testing time.
answer to a contractors question 1.
Good Afternoon Contracting Team,
The Shore tie Terminals is one box that has two plugs for shore ties. Approximate size is 4’x4’x2’ Not exact size of the box, but approximate.
Approximate distance of the cable/ conduit run is 550’ plus or mins 20 feet.
Area of Concern: On map, it is South Float One (Berth 5 and Berth 10).
Base Ketchikan POC: LT Robert Marx and CWO Russell Dever.
***contact Senior Field Contracting Officer (SFCO ) DENO STAMOS AT deno.a.stamos@uscg.mil if a site walk is required .
THIS IS A COMBINED SYNOPSIS SOLICIATION. RECEIPT OF BIDS VIA EMAIL IS DUE NO LATER THAN 26 FEBRUARY 2026 AT 3:00 PM ALASKA TIME ZONE,
NAICS CODE: 238210
FSC CODE:J059
Update #2 ·
SEE ATTACHED SPECS/SCOPE OF WORK----
Scope of Work: Electrical Inspection and Maintenance – Floating Pier One, Base Ketchikan
1. Objective:
Provide inspection, maintenance, and repair services for electrical systems associated with Floating Pier One, Base Ketchikan, with a focus on shore tie terminals and associated electrical lines.
2. Location:
Floating Pier One, Base Ketchikan. Berth 5
3. Tasks:
A. Shore Tie Terminal Maintenance
- Inspect all shore tie terminals where vessels connect to shore power.
- Identify and document any damage, corrosion, moisture intrusion, or other deficiencies.
- Repair any identified issues to restore full functionality.
- Dry and seal all shore tie terminals to prevent future moisture intrusion.
- Test terminals for proper operation after repairs and sealing.
B. Electrical Line Inspection and Grooming
- Inspect the electrical line running from the FRC Floating Pier Isolation Transfer to the shore tie terminals.
- Clean and groom all accessible portions of the line, removing debris, corrosion, and contaminants.
- Conduct a thorough inspection for physical damage, wear, or potential failure points.
- Perform Megger (insulation resistance) testing on the electrical lines to identify any insulation breakdowns or other potential issues.
- Document all findings and provide recommendations for further action if required.
4. Deliverables:
- Written inspection report detailing findings, repairs performed, and recommendations for future maintenance.
- Documentation of Megger test results and any corrective actions taken.
- Photographic evidence of before and after conditions for all work performed.
5. Period of Performance:
- Shore Tie Terminal inspection and maintenance shall be completed within two (2) weeks from award of contract.
- Electrical line inspection, grooming, and cleaning shall be completed within three (3) weeks from award of contract.
- Final written report of findings and actions written(typed) and documented shall be submitted within one (1) month from the start of the period of performance.
6. Safety and Compliance:
- All work must comply with applicable electrical codes, safety standards, and Base Ketchikan requirements.
- All personnel must be appropriately licensed and qualified for marine electrical work.
Quote/Estimate: Quote or Estimate shall include materials going up to 5,000K for any repairs in the shore tie terminal box on the floating pier, but not to exceed.
Question: Could you quantify the shore tie terminals and cable lengths from Isolation Transfer to each Terminal to refine labor/testing time.
answer to a contractors question 1.
Good Afternoon Contracting Team,
The Shore tie Terminals is one box that has two plugs for shore ties. Approximate size is 4’x4’x2’ Not exact size of the box, but approximate.
Approximate distance of the cable/ conduit run is 550’ plus or mins 20 feet.
Area of Concern: On map, it is South Float One (Berth 5 and Berth 10).
Base Ketchikan POC: LT Robert Marx and CWO Russell Dever.
***contact Senior Field Contracting Officer (SFCO ) DENO STAMOS AT deno.a.stamos@uscg.mil if a site walk is required .
THIS IS A COMBINED SYNOPSIS SOLICIATION. RECEIPT OF BIDS VIA EMAIL IS DUE NO LATER THAN 26 FEBRUARY 2026 AT 3:00 PM ALASKA TIME ZONE,
NAICS CODE: 238210
FSC CODE:J059
Update #1 ·
SEE ATTACHED SPECS/SCOPE OF WORK----
Scope of Work: Electrical Inspection and Maintenance – Floating Pier One, Base Ketchikan
1. Objective:
Provide inspection, maintenance, and repair services for electrical systems associated with Floating Pier One, Base Ketchikan, with a focus on shore tie terminals and associated electrical lines.
2. Location:
Floating Pier One, Base Ketchikan. Berth 5
3. Tasks:
A. Shore Tie Terminal Maintenance
- Inspect all shore tie terminals where vessels connect to shore power.
- Identify and document any damage, corrosion, moisture intrusion, or other deficiencies.
- Repair any identified issues to restore full functionality.
- Dry and seal all shore tie terminals to prevent future moisture intrusion.
- Test terminals for proper operation after repairs and sealing.
B. Electrical Line Inspection and Grooming
- Inspect the electrical line running from the FRC Floating Pier Isolation Transfer to the shore tie terminals.
- Clean and groom all accessible portions of the line, removing debris, corrosion, and contaminants.
- Conduct a thorough inspection for physical damage, wear, or potential failure points.
- Perform Megger (insulation resistance) testing on the electrical lines to identify any insulation breakdowns or other potential issues.
- Document all findings and provide recommendations for further action if required.
4. Deliverables:
- Written inspection report detailing findings, repairs performed, and recommendations for future maintenance.
- Documentation of Megger test results and any corrective actions taken.
- Photographic evidence of before and after conditions for all work performed.
5. Period of Performance:
- Shore Tie Terminal inspection and maintenance shall be completed within two (2) weeks from award of contract.
- Electrical line inspection, grooming, and cleaning shall be completed within three (3) weeks from award of contract.
- Final written report of findings and actions written(typed) and documented shall be submitted within one (1) month from the start of the period of performance.
6. Safety and Compliance:
- All work must comply with applicable electrical codes, safety standards, and Base Ketchikan requirements.
- All personnel must be appropriately licensed and qualified for marine electrical work.
Quote/Estimate: Quote or Estimate shall include materials going up to 5,000K for any repairs in the shore tie terminal box on the floating pier, but not to exceed.
Area of Concern: On map, it is South Float One (Berth 5 and Berth 10).
Base Ketchikan POC: LT Robert Marx and CWO Russell Dever.
***contact Senior Field Contracting Officer (SFCO ) DENO STAMOS AT deno.a.stamos@uscg.mil if a site walk is required .
THIS IS A COMBINED SYNOPSIS SOLICIATION. RECEIPT OF BIDS VIA EMAIL IS DUE NO LATER THAN 26 FEBRUARY 2026 AT 3:00 PM ALASKA TIME ZONE,
NAICS CODE: 238210
FSC CODE:J059
Files
| File | Type | Posted |
|---|---|---|
| Scope of Work_Berth 5.docx | DOCX document | |
| MASTER RFP Q FOR POSTING NEW RQMTS.docx | DOCX document |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity