Stonewall Jackson Lake Dam Replace Pylon Building Roofs
Closed Solicitation Posted
- Solicitation number
- W911WN19Q0189
- Agency
-
ENDIST Pittsburgh
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 238160 Roofing Contractors
- Place of performance
- Stonewall Jackson Lake Dam 1012 Skin Creek Road Weston Wv 26452 USA
Notice details come from SAM.gov. Updated .
Notice text
4 versions
Update #4 · Latest ·
Quotation due date has been extended until Tuesday August 20, 2019.
Awardable Options have been added to the RFQ, and as such CLINs have been revised.
Update #3 ·
An amendment will be forthcoming to revise this RFQ, and to extend the due date for this project, please refrain from submitting any quotes until this Amendment is posted.
If you have any questions, please feel free to contact the Contract Specialist listed for this project.
Update #2 ·
Amendment 0001 extends the quotation due date to Thursday August 15, 2019.
Update #1 ·
This is a Request for Quote (RFQ) issued in accordance with FAR Parts 13 and 36. The U.S. Army Corps of Engineers, Pittsburgh District has a requirement for Roofing Replacement at the Stonewall Jackson Lake Dam Pylong Building located at 1012 Skin Creek Rd. Weston, WV 26452-7435. The site of work may be reached from state and local roads and streets.
The work includes the removal of existing roofing systems on three roof levels down to the concrete decks and the placement of new tapered insulation and modified bitumen built up roofing system on these roofs at the pylon building on the dam. The general description of the work is to furnish all equipment, labor, layout of work, supervision and materials necessary to complete the work as shown and as specified. Typical detail of the new roof is indicated on the attached “TYPICAL NEW MODIFIED BITUMEN ROOF DETAIL”.
The existing roofs on the pylon building at the dam consist of two lower level roofs that function as observation decks and one upper level penthouse roof.
Details of the building construction are shown on the attached reference drawings, however, the penthouse roofing has been replaced at one time with a spray-applied system over foam insulation. No further information on the penthouse roof is available. The work shall include removal and disposal of all roofing materials over the all three roofs down to the existing concrete decks, including all flashing, roof drains, flashing around penthouse roof scuttle, and installation of new tapered insulation, flashing, roof drains, and all other work to furnish all equipment, labor, layout of work, supervision and materials necessary to complete the work as shown and as specified.
The Contractor shall be responsible for transport of materials to the site and to prevent demolished materials from entering the lake. All material provided in the performance of this contract shall be unused and meet the requirements of the specifications.
The Contractor shall verify dimensions and clearances in the field before beginning work.
Files
| File | Type | Posted |
|---|---|---|
| Amendment_0003_(9-25-19).pdf | ||
| Amendment_0002(8-14-19).pdf | ||
| Amendment_0001.pdf | ||
| RFQ_W911WN19Q0189.pdf | ||
| Technical_Specifications_and_Contract-Reference_Drawings.pdf |