Amendment 0002 - Extends due date to 8/20/2019, adds awardable options, revises CLINs, and revises language contained in RFQ.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0003_(9-25-19).pdf | ||
| Amendment_0001.pdf | ||
| RFQ_W911WN19Q0189.pdf | ||
| Technical_Specifications_and_Contract-Reference_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W81ET491190189
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RE: W911WN19Q0189 (Stonew all Jackson Lake Pylon Building Roofing Replacment)
The purpose of this amendment is to:
1. Extend the quotation due date to August 20, 2019.
2. Revise the CLINs, as detailed in the Summary of Changes.
3. Add section 00 73 00-4 Aw ardable Options to this RFQ.
4. Revise language in Clause 52.211-10.
5. All other terms and conditions remain unchanged and in full force and effect.
1. CONTRACT ID CODE PAGE OF PAGES
1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911WN19Q0189
X 9B. DATED (SEE ITEM 11)
30-Jul-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Aug-2019
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CELRP-RC-P
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2203
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W911WN
FACILITY CODECODE
carole.householder@usace.army.milEMAIL:412-395-7274TEL:
CAROLE M HOUSEHOLDER / CONTRACTING OFFICER
W911WN19Q0189
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 15-Aug-2019 05:00 PM to 20-Aug-
2019 05:00 PM.
The CLINs have been revised and the new price schedule should reflect as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
REIMBURSEMENT FOR PAYMENT BOND PREMIUM
FFP
This line item is ONLY to be used if the quoter proposed Payment Protection via a construction bond. IAW FAR 52.228-13, Alternative Payment Protection, clause of the contract, this CLIN only applies if the offer or bid is between $35,000 and $150,000 and if the offeror elects to provide a payment bond in lieu of an Irrevocable Letter of Credit. See Special Contract Requirements for additional information concerning reimbursement for bond premium. If applicable, funding for this CLIN will be secured prior to award.
FOB: Destination
PURCHASE REQUEST NUMBER: W81ET491190189
NET AMT
0002 1 Job Demo and Replacement of Penthouse Roof
FFP
PURCHASE REQUEST NUMBER: W81ET491190189
1001 1 Job
OPTION REIMBURSEMENT FOR PAYMENT BOND PREMIUM
FFP
OPTION 1.This line item is ONLY to be used if the quoter proposed Payment Protection via a construction bond. IAW FAR 52.228-13, Alternative Payment Protection, clause of the contract, this CLIN only applies if the offer or bid for Option 1 is between $35,000 and $150,000 and if the offeror elects to provide a payment bond in lieu of an Irrevocable Letter of Credit. See Special Contract Requirements for additional information concerning reimbursement for bond premium. If applicable, funding for this CLIN will be secured prior to exercising Option 1.
1002 1 Job OPTION Demo and Replacement of Lower
FFP
Observation Deck Roof on Pylon Building, East Side
2001 1 Job
OPTION REIMBURSEMENT FOR PAYMENT BOND PREMIUM
FFP
OPTION 2. This line item is ONLY to be used if the quoter proposed Payment Protection via a construction bond. IAW FAR 52.228-13, Alternative Payment Protection, clause of the contract, this CLIN only applies if the offer or bid for Option 2 is between $35,000 and $150,000 and if the offeror elects to provide a payment bond in lieu of an Irrevocable Letter of Credit. See Special Contract Requirements for additional information concerning reimbursement for bond premium. If applicable, funding for this CLIN will be secured prior to award.
2002 1 Job OPTION Demo and Replacment of Lower
FFP
Observation Deck Roof on Pylon Building, West Side
The following have been modified:
TOTALS
TOTAL BASE CONTRACT (ITEMS 0001 THROUGH 0002) $
TOTAL AWARDABLE OPTION 1 (ITEMS 1001 THROUGH 1002) $
TOTAL AWARDABLE OPTION 2 (ITEMS 2001 THROUGH 2002) $
TOTAL (ITEMS 0001 THROUGH 2002) $
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the base contract notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days after receipt of the Notice to Proceed. If Awardable Option 1 is exercised, the contract period of performance shall be 75 days from the Base Contract Notice to Proceed. If Awardable Option 2 is exercised, the contract period of performance shall be 90 days from the Base Contract Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
ADDENDUM TO SECTION 00 73 00
00 73 00-1 COPYING, DISSEMINATION OR DISTRIBUTION OF INFORMATION.
Those who disseminate information contained in the solicitations and/or drawings must ensure that the recipients have a legitimate need for the information and maintain a record of each recipient. Legitimate need means recognized business entities seeking to do business, or having business, with the Government as prime contractors, subcontractors or suppliers. You shall maintain a record of the following information on each recipient: Business name and address, DUNS Number and IRS Tax ID Number, and name and telephone number of person receiving the information.
00 73 00-2 SUBMISSION OFCONTRACT DOCUMENTATION
Provide contract documentation in an electronic format to the greatest extent practicable.
Contract documentation to be submitted electronically includes, but is not limited to, the following:
□ Submittals, including ENG4025 transmittal form
□ MeetingMinutes
□ Construction Photographs
□ Correspondence
□ Requestsfor Information
□ PayrollDocuments
□ Statementand Acknowledgement Forms(SF 1413)
□ Request for Additional Classification (SF 1444)
□ ProgressPayment Requestsand SupportingDocumentation
□ Contract Modification Documentation, including SF 30, Contractor’s Offer, Cost/Pricing Audit Report, and Certificate of Current Cost or Pricing Data
□ ContractorQualityControl Reports(withattachments)
□ Accident Reports
□ Schedulesand Schedule Updates
□ Closeout Documentation, includingReleaseof Claims
Electronic files must be of sufficient qualitythat all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed bythe Contracting Officer. Wheneverpossible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarkedto allow efficient navigation of the file.
When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic documents fewer than 10MB to an email address as directed bythe Contracting Officer. Electronic documents over 10MB shall be provided on a CD/DVD, or through an electronic file sharing system that will require coordination with the Contracting Officer for access guidance.
The Contractor shall be prepared to provide up to five (5) additional paper hard copies of any contract document at the discretion of the Contracting Officer, at no additional cost to the Government. In addition to the electronic file format described above, the following list of documents shall be provided in their original format because law or other regulations require signed originals be kept in accordancewith FAR 4.805 -- Storage, Handling, and Disposal of Contract Files:
□ AdvancePayment Bond
□ Bid Bond including Annual Bid Bond
□ PerformanceBondincludingAnnual Performance Bond
□ Payment Bond
□ Patent InfringementBond
□ Anyperformancesecurityinstruments
□ Certificateof Insurance
□ Novation/ChangeofNameAgreement
□ AssignmentofClaims
□ Anydocument containinga raised seal. Examplesinclude
• Notarizeddocuments o ArchitectureDrawings
□ PaperPayroll Documents
□ Physical signatureson contracts andmodifications
• SF 1442
• SF 30
00 73 00-3 WORK UNDER OTHER CONTRACTS
Attention is directed to the fact that other Contractors may be employed by the Government or by local interests at or in the vicinityof the work covered by these specifications. All Contractors shall have equal rights to the use of all roads and grounds so far as practicable and this Contractor shall cooperate with other Contractors so that the work may be performed with the maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern.
00 73 00-4 AWARDABLE OPTIONS
Only the basic contract items, Items Nos. 0001 thru 0002, will be awarded initially. Awardable Option Items 1 and 2 may be exercised upon availability and receipt of funds. Awardable Option Items within each of these groupings will be awarded as a group. The Not-to-Exceed amount for Items 1001 and 2001 should reflect bond costs for all awardable option items within each respective group. The determination to award these awardable option items will be made no later than the following dates:
Awardable Option 1, Items 1001 and 1002 – 30 September 2019 Awardable Option 2, Items 2001 and 2002 – 30 September 2019
00 73 00-5 SAFETY AND HEALTH REQUIREMENTS MANUAL
A copy of the current US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 and its changes are available at http://www.usace.army.mil/CESO/pages/home.aspx.
The contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
00 73 00-6 WAGE RATES
The attached schedule of wage rates, Department of Labor General Decision No. WV20190013 (06/14/2019) contains rates applicable to all work under this contract.