Sources Sought Notice for Sole Source Market Research for the PN096278 FY26MCA Electrical Switching Station-North project at Watervliet Arsenal (WVA), New York.

Closed Pre-Solicitation Posted

Solicitation number
W912DS26S0033
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

PSC
Not on record
Place of performance
Watervliet, New York 12189, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Army Corps of Engineers New York District is preparing to solicit a construction contract for electrical switching station infrastructure at Watervliet Arsenal, New York, with responses to this sources sought notice due June 12, 2026. The Corps intends to sole-source specific branded components unless equivalent alternatives are identified through this market research.

The project will construct a generator connection terminal and associated electrical infrastructure to provide backup power during extended Main Substation outages. Scope includes electric manholes, duct bank, grounding cable, fencing, switchgear, transfer switches, cables, generator procurement and installation, splices and connections, plus supporting facilities (paving, walks, curbs, gutters, utilities testing and commissioning). The switching station will feed 4 megawatts into the existing WVA distribution network while establishing capacity for 8 megawatts of power generation needed to fully power the arsenal during emergency loss of primary power. Work includes all necessary utility interconnections for fuel supply to the generation facility, connection of the switching station to the existing electrical distribution network, and installation of automatic-start controls for power generation and distribution switching.

This sources sought notice serves to notify potential bidders of the Government's intent to sole-source identified brand-name components, to identify sources capable of providing equivalents, and to solicit one-step negotiated procurement on the overall construction contract. Award is planned for fiscal year 2026.

Notice text

The New York District plans to solicit and award a construction contract for subject project in FY26. The scope of the project is:

To construct a generator connection terminal to provide backup power to the Arsenal in the event of a long-term power outage from the facility’s Main Substation. The primary scope includes electric manholes, duct bank, grounding cable, fencing, switchgear, transfer switches, cables, generator procurement and installation, splices and connections. Supporting facilities include paving, walks, curbs, gutters, and utilities testing and commissioning.

This project will construct a switching station capable of feeding 4MW of power into the existing WVA distribution network and constructing a facility capable of 8MW of power generation needed to power the WVA during an emergency loss of power. The facilities will increase the existing switching station capacity from 4MW to the full 8MW needed for powering the installation fully while also providing the means of that power generation. The project also includes the construction of all necessary utility interconnections to bring fuel to the power generation facility and to connect the switching station to the existing electrical distribution network. The installation of controls for the auto start of this power generation and distribution switch are also included in this project.

1. This notification serves three (3) purposes:

a. To notify potential bidders of the Government’s intent to solicit a brand name(s) only component for this project.

b. To identify potential sources that can provide an equivalent to the brand name only item(s).

c. Notification of the Army’s intent to solicit brand name components as described below.

2. The items described below, under summary of requirements, are embedded in the construction project. The contract will be issued as a one-step negotiated procurement. Only the components described below will be sole sourced, if no other sources are identified that can provide an equivalent system. In the event no equivalent sources are found, the brand name only justification will be issued pursuant to FAR Part 6.302-1, Only One Responsible Source. A subsequent market survey will not be published in support of a Justification and Approval for sole sourcing. Supplies of the brand name component will be provided directly to the Contractor(s) and not to the Government.

3. Summary of Requirements:

a. Mechanical Controls System

The requirement is to sole-source a requirement for brand-name Johnson Controls Inc. (JCI) Metasys components, programming, and engineering modifications to support the installation of the sitewide electrical switching project. The purpose of this acquisition is to integrate new control equipment into the existing-to-remain Building Automation System (BAS) infrastructure. Currently, WVA relies heavily on proprietary JCI Metasys controllers and software to monitor and control facility systems. Utilizing OEM-compatible JCI Metasys equipment is technically necessary to ensure full compatibility with the existing base-wide Metasys server and associated field devices, while following the guidelines outlined in Unified Facilities Guide Specifications (UFGS) 25 10 10. Proprietary control system appliances are required to achieve synchronization of telemetry signals with the remainder of the facility, leveraging the existing Metasys network as the primary communications backbone for remote monitoring and electrical switching commands.

After careful review of the necessary project scope, the Government has determined that maintaining compatibility with the existing software infrastructure used for building servicing is essential. Therefore, the decision has been made to continue using the JCI Metasys product line for these new controls. This choice is driven by the strict requirement to ensure seamless integration and operation within the current system without impairing its existing cybersecurity posture or reliability. The Utility Monitoring and Control System (UMCS) modifications must be delivered as a complete, networked architecture that provides real-time, point-to-point telemetry reporting to the local supervisory engines, which in turn report directly to the central Metasys front-end server. Because the existing facility infrastructure is standardized on this platform, utilizing proprietary JCI components is the only way to ensure the uninterrupted, reliable control necessary for this critical mission-support infrastructure

4. Any vendor that wishes to provide an alternate source to the brand names above that is compatible with the above must provide a response with data supporting the claim within 15 business days of this announcement to New York District Corps of Engineering, Contracting Division.

This is a market survey and notification of intent only. This is not a request to respond to a solicitation. This requirement will be solicited at a future date.

Similar open opportunities

Opportunity Agency Set-aside Responses due
106 CE electrical loop repair 150 Old Riverhead Rd Westhampton Beach, NY 11978 11978 · NAICS 238210 New York National Guard No set-aside
LLA Navigation Lock Switchgear Pomeroy, Washington 99347, United States · NAICS 238210 ENDIST Walla Walla Total Small Business
US Army assessment of Thermal Power Station Operations Aberdeen Proving Ground, Maryland 21005, United States · NAICS 611430 ACC Aberdeen Proving Ground No set-aside
U. S. Army Contracting Command – Watervliet Arsenal (ACC-WVA) Organic Industrial Base (OIB) Modernization Commercial Solutions Opening (CSO) Watervliet, New York 12189, United States ACC Warren No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors