Solicitation for Grissom Air Reserve Base Runways Project
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912QR22R0020
- Agency
-
ENDIST Louisville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Grissom ARB, Indiana, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals for runway and taxiway repairs at Grissom Air Reserve Base in Indiana. Work includes milling and overlay of approximately 3.29 million square feet of pavement and replacing approximately 471,000 square feet at full depth. Additional repairs listed are sections of Taxiways C and G, the 12,501 foot main Runway 12, shoulders, overruns, and airfield lighting circuits. Proposals must meet specifications provided and will be evaluated based on technical qualifications, past performance, and price/cost. The response deadline is March 4, 2022.
The solicitation has no set-aside designation. The primary NAICS code is 237990 and PSC code is D304. The incumbent is the Department of the Army Corps of Engineers Louisville District. The estimated value is between $5-10 million to be completed by late 2022. Repairs are to improve 3.76 million square feet of pavement surfaces across runways and taxiways at Grissom Air Reserve Base in Grissom, Indiana.
Notice text
3 versions
Update #3 · Latest ·
****AMDT 0007 is hereby posted.****
AMDT 0003 04 February 2022 - The link for this solicitation oppotunrity in the Procurement Integrated Enterprise Enviornment (PIEE) is: https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912QR22R0020
This project is a renovation of approximate total mill and overlay is 3,290,000 square feet and approximate total full depth replacement is 471,000 square feet of PCC. The proposed project includes: Repair throats at Taxiway C to full depth. Conduct a repair of the north and south Taxiway C throats by removing all layers of pavement at full depth to subgrade and replace with Portland cement concrete (PCC). Repair Taxiway G sections. Remove the asphalt over Portland cement concrete (APC) at full depth to subgrade and replace with Portland cement concrete. Repair full length of Runway 12,501ft using mill and overlay and full depth PCC methods as designed. Variable Mill of surface and overlay with asphalt concrete (AC). Repair 1,200LF to full depth with PCC. Repair shoulders for the entire length of the runway (12,501ft) by variable milling of surface and overlaying with asphalt concrete. Repair the asphalt concrete paved overruns at the 23 and 05 ends of the runway by milling the surface and overlaying with asphalt concrete. Repair by replacement of airfield lighting circuits the (1) complete approach system for runway 05 (2) the threshold light bar at the end of runway 23 (3) feeder cables from home runs at both 23 and 05 ends (4) Taxiway G edge lighting (5) airfield guidance sign system.
Update #2 ·
AMDT 0003 04 February 2022 - The link for this solicitation oppotunrity in the Procurement Integrated Enterprise Enviornment (PIEE) is: https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912QR22R0020
This project is a renovation of approximate total mill and overlay is 3,290,000 square feet and approximate total full depth replacement is 471,000 square feet of PCC. The proposed project includes: Repair throats at Taxiway C to full depth. Conduct a repair of the north and south Taxiway C throats by removing all layers of pavement at full depth to subgrade and replace with Portland cement concrete (PCC). Repair Taxiway G sections. Remove the asphalt over Portland cement concrete (APC) at full depth to subgrade and replace with Portland cement concrete. Repair full length of Runway 12,501ft using mill and overlay and full depth PCC methods as designed. Variable Mill of surface and overlay with asphalt concrete (AC). Repair 1,200LF to full depth with PCC. Repair shoulders for the entire length of the runway (12,501ft) by variable milling of surface and overlaying with asphalt concrete. Repair the asphalt concrete paved overruns at the 23 and 05 ends of the runway by milling the surface and overlaying with asphalt concrete. Repair by replacement of airfield lighting circuits the (1) complete approach system for runway 05 (2) the threshold light bar at the end of runway 23 (3) feeder cables from home runs at both 23 and 05 ends (4) Taxiway G edge lighting (5) airfield guidance sign system.
Update #1 ·
This project is a renovation of approximate total mill and overlay is 3,290,000 square feet and approximate total full depth replacement is 471,000 square feet of PCC. The proposed project includes: Repair throats at Taxiway C to full depth. Conduct a repair of the north and south Taxiway C throats by removing all layers of pavement at full depth to subgrade and replace with Portland cement concrete (PCC). Repair Taxiway G sections. Remove the asphalt over Portland cement concrete (APC) at full depth to subgrade and replace with Portland cement concrete. Repair full length of Runway 12,501ft using mill and overlay and full depth PCC methods as designed. Variable Mill of surface and overlay with asphalt concrete (AC). Repair 1,200LF to full depth with PCC. Repair shoulders for the entire length of the runway (12,501ft) by variable milling of surface and overlaying with asphalt concrete. Repair the asphalt concrete paved overruns at the 23 and 05 ends of the runway by milling the surface and overlaying with asphalt concrete. Repair by replacement of airfield lighting circuits the (1) complete approach system for runway 05 (2) the threshold light bar at the end of runway 23 (3) feeder cables from home runs at both 23 and 05 ends (4) Taxiway G edge lighting (5) airfield guidance sign system.
Files
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| Contract Award Synopsis - Grissom Air Reserve Base Runways Project | Award Notice | |
| This notice | Solicitation | |
| Pre-Solicitation Synopsis for Grissom Air Reserve Base Runways Project | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Mechanized Material Handling Storage Aid System at Grissom ARB, Indiana | AFLCMC Wright Patterson AFB | Total Small Business |