W912QR22R0020-0006.pdf

PDF 2 MB Posted

Attached to
Solicitation for Grissom Air Reserve Base Runways Project
Solicitation number
W912QR22R0020
Issued by

About this file

This document is an amendment to a solicitation for runway repair work at Grissom Air Reserve Base in Indiana. The solicitation seeks bids for milling and overlay of approximately 3,290,000 square feet of pavement and full depth replacement of approximately 471,000 square feet. Scope of work includes repairing sections of Taxiway C and Taxiway G by removing pavement at full depth and replacing with Portland cement concrete. The full length of Runway 12,501 feet will be repaired using mill and overlay or full depth concrete methods. Shoulders along the entire runway length will also be repaired by milling and overlay. Overruns at each end of the runway will be repaired by milling and overlay. Airfield lighting circuits including approach lighting, threshold lighting, feeder cables, and signage will also be repaired or replaced. The amendment extends the response deadline from February 28 to March 4, 2022. It removes FAR clauses related to project labor agreements. The solicitation is issued by the Department of the Army Corps of Engineers Louisville District.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912QR22R0020-0006

W912QR22R0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMDT 0006 SUMMARY OF CHANGES

Solicitation: W912QR22R0020 Project: Repair Airfield Lighting Circuits / Repair Taxiway G / Repair Overruns / Repair Runway and

Shoulders / Repair Taxiway C Location: Grissom Air Reserve Base, Indiana

General Information:

1. The due date and time for submission of proposals has been extended to 1:00 PM (Eastern) on 04 March

2022.

SECTION 00 70 00 – Conditions of the Contract

1. The following FAR Clauses have been DELETED:

a. FAR 52.222-33 ALT II – Notice of Requirement for Project Labor Agreement

b. FAR 52.222-34 ALT 1 – Project Labor Agreement

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 28-Feb-2022 01:00 PM to 04-Mar-2022 01:00 PM.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been deleted:

52.222-33 Alt II Notice of Requirement for Project Labor Agreement (MAy 2010) Alternate I

MAY 2010

52.222-34 Alt I Project Labor Agreement (May 2010) Alternate I MAY 2010

(End of Summary of Changes)

W912QR22R0020-0006

SF30
SUMMARY OF CHANGES