Repair Floor Coating B#2348, Suwon AB (MATOC ONLY)

Award Notice Posted

Solicitation number
W90VN618R0017
Agency
Awarded
to Gun-Hae Construction Co.ltd
Set-aside
No set-aside

Opportunity facts

Contract number
W91QVN-18-D-0059-W90VN618F0086 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Place of performance
Suwon, Korea, South

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

PRINCIPAL FEATURES: This project includes, but shall not be limited to the following principal features:

0001. PHASE PLAN


1. The renovation of this building will be phased to support minimal mission messing requirements. Phase 1 (refer to drawing # 3) will be released for renovation first. Steps shall be taken to prevent dirt/debris/noise from construction activities for remaining area. After Phase 1 is finished, Phase 2 will be released for renovation.


0002. ARCHITECTURAL WORK


A. REMOVAL WORK / INTERIOR FINISH
1. Repair any damaged concrete floor and provide new conc sealer.
2. Repair any damaged concrete floor joint.
3. Provide non-slip broom finish.
4. Repaint existing parking line.

Update #1 ·

PRINCIPAL FEATURES: This project includes, but shall not be limited to the following principal features:

0001. PHASE PLAN


1. The renovation of this building will be phased to support minimal mission messing requirements. Phase 1 (refer to drawing # 3) will be released for renovation first. Steps shall be taken to prevent dirt/debris/noise from construction activities for remaining area. After Phase 1 is finished, Phase 2 will be released for renovation.


0002. ARCHITECTURAL WORK


A. REMOVAL WORK / INTERIOR FINISH
1. Repair any damaged concrete floor and provide new conc sealer.
2. Repair any damaged concrete floor joint.
3. Provide non-slip broom finish.
4. Repaint existing parking line.
2. Install new GCWT wall finish with metal lath, latex mortar and grout as shown on the drawings.
3. Install new wall base finish with rubber cove base as shown on the drawings.
4. Repaint and apply latex, oil, alkyd, epoxy paint as shown on interior finish schedule.


D. MISCELLANEOUS WORK
1. Install new toilet accessories including toilet & urinal partitions, mirror glass, towel bar, shower curtains w/rods, soap dishes, toilet tissue dispensers, paper towel dispenser/waste receptacles, grab bars, soap dispensers, mop racks, shower benches and etc as shown on attached drawings.
2. Apply sealant or seal for doors and windows.

Files

File Type Posted
SF30.pdf PDF
Drawings.pdf PDF
W90VN618R0017.pdf PDF
Suwon_Air_Base_EAL.xls XLS spreadsheet