Repair Fire Protection pipeline at Hario Shima Ordnance for CFA Sasebo, Japan - Track-1

Award Notice Posted

Not the latest version. See the latest pre-solicitation from .

Solicitation number
N4008418B6502
Agency
Awarded
to American Engineering Corporation
Set-aside
No set-aside

Opportunity facts

Contract number
N4008418C6503 Federal contract award
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Award notice for Repair Fire Protection Pipeline at Hario Shima Ordnance for CFA Sasebo, Japan â€" Track-1 (eP #1561498). Awarded Vendors: American Engineering Corporation (DUNS 690619705)
7-8-13 Oyama
Ginowan, Japan. Contract Award Dollar Amount: 5888455.27. Contract Award Date: 2018-07-29.

Update #2 ·

This project will replace an aged and deteriorated underground fire protection pipeline at Harioshima Ordnance. The ductile iron (DIP) saltwater distribution piping will be replaced with High Density Polyethylene (HDPE) pipe and installed underground. Associated hydrants, valves and fittings will also be replaced, and pavement restored.
The work is planned to be carried out in two tracks via two separate contract awards, one awarded in United States Fiscal Year (FY) 2018 and one awarded in United States FY 2019. The first track (Phases 1 through 3) is currently planned to be solicited around June 2018 and award by September 2018. The second track (Phases 4 through 8) is currently planned to be solicited around January 2018 and award by March of 2019.
Area of each phase is shown in Attachment (1): HO Saltwater Fire Suppression Line.
FY2018 (Track 1) â€" 2,542 Linear Meters and 20 hydrants, magnitude of construction IAW FAR 36.204 is between $5,000,000 to $10,000,000.
FY2019 (Track 2) â€" 6,674 Linear Meters and 42 hydrants, magnitude of construction IAW FAR 36.204 is between $10,000,000 and $25,000,000.
.

Update #1 ·

This project will replace an aged and deteriorated underground fire protection pipeline at Harioshima Ordnance. The ductile iron (DIP) saltwater distribution piping will be replaced with High Density Polyethylene (HDPE) pipe and installed underground. Associated hydrants, valves and fittings will also be replaced, and pavement restored.



The work is planned to be carried out in two tracks via two separate contract awards, one awarded in United States Fiscal Year (FY) 2018 and one awarded in United States FY 2019. The first track (Phases 1 through 3) is currently planned to be solicited around June 2018 and award by September 2018. The second track (Phases 4 through 8) is currently planned to be solicited around January 2018 and award by March of 2019.

Area of each phase is shown in Attachment (1): HO Saltwater Fire Suppression Line.



FY2018 (Track 1) – 2,542 Linear Meters and 20 hydrants, magnitude of construction IAW FAR 36.204 is between $5,000,000 to $10,000,000.



FY2019 (Track 2) – 6,674 Linear Meters and 42 hydrants, magnitude of construction IAW FAR 36.204 is between $10,000,000 and $25,000,000.



Files

Notice history

Notice Type Posted
Repair Fire Protection Pipeline at Hario Shima Ordnance, Track-1 Latest pre-solicitation Pre-Solicitation
This notice Award Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors