RECOVERY--Y--PROJECT NUMBER 074740, Santa Maria Levees, CA Santa Maria South Levee Improvements, Reach 3 (Suey Crossing Bridge to Bradley Canyon Confluence) California

Award Notice Posted

Solicitation number
W912PL-10-B-0002
Agency
Awarded
to Wood Bros., Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912PL-10-C-0019 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Wood Bros., Inc. W912PL-10-C-0019, Santa Maria Levees, CA

Project Number 074740, Santa Maria Levees, Reach 3 extends about 3.13 miles from Suey Crossing Bridge to Bradley Canyon Confluence. Improvements consist of an 8-ft wide and about 30 ft deep compacted soil cement section along the levee riverward side slope and 50 to 62 ft. deep and 1,700 ft. long steel sheet pile along the levee at the upstream end of the soil cement levee portion. Construction of the compacted soil cememt levee requires excavation of the existing ground to the approximate depth of 15 ft. to 20 ft. below the existing grade. Construction of 50-60 ft. deep steel sheet pile does not require excavation of the existing levee. Also included in the improvements are removal, disposal and installation of the levee signs, fences, and gates, along with resurfacing of road, extending of reinforced pipe culvert and stone work which consists of removal of existing 22 rock groins, and salvage and disposal of the removed material at a designated site. Location is Santa Maria, CA.

Update #2 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): None

The project consists of improvements of the existing south levee within the Santa Maria levee system. The south levee improvement project includes reaches 1 & 2 that were awarded for construction in early October 2009, and reach 3 which is being considered for this contract. Reach 3 extends about 3.13 miles from Suey Crossing Bridge to Bradley Canyon Confluence. The improvements consist of construction of an 8-ft. wide and about 30-ft. deep compacted soil cement section along the levee riverward side slope and 50 to 62 ft. deep and 1,700 ft. long steel sheet pile along the levee at the upstream end of the soil cement levee portion. Construction of the compacted soil cement levee requires excavation of the existing ground to the approximate depth of 15ft. to 20ft. below the existing grade. Construction of 50-60ft. deep steel sheet pile does not require excavation of the existing levee. Improvements also call for removal, salvage and disposal of existing rock groins. Removal, disposal and installation of the levee signs, fences and gates are also needed for levee improvement. Resurfacing the existing 14 wide ABC levee road with the new 4 thick ABC is necessary for operation and maintenance. There are two existing single-cell (5X2) Reinforced Concrete Box (RCB) culverts, one 36 and one 48 Diameter Reinforced Concrete Pipe (RCP) that need to be extended, modified and included with the new outlet structures. Stone work consists of removal of existing 22 rock groins, salvage and disposal of the removed material at a designated site.

The estimated cost of this project is $10,000,000 - $25,000,000.00.

NOTE: This procurement is issued under full and open competition without exclusion of sources. When applicable, FAR 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns will be applied to this action.

ALL OFFERORS/BIDDERS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: The solicitation will be available on-line on or about 18 December 2009. Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments for this Invitation for Bids will be posted on the Federal Business Opportunity Web Site: www.fbo.gov. Viewing/downloading documents from the site will require prior registration in Central Contractor Registration Web Site: www.ccr.gov. Please note that ALL firms wishing to access the solicitation, both prospective prime contractors and subcontractors, must be CCR-registered, have a MPIN, and either a DUNS number or CAGE code.

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,000,000.00. If the offeror/bidder is a large business, the firm will be required to submit a sub-contracting plan. The plan shall be prepared in accordance with FAR 52.219-9. Failure to submit an acceptable sub-contracting plan may make the bidder ineligible for award of the contact. To be acceptable, the plan must adequately address the six required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of appendix DD, Part 2, AFARS 19.705. The Los Angeles District subcontracting goals are specific percentages of the contractors total planned subcontract amount. The goals are as follows: 70% with small business; 6.2% with small disadvantaged business; 7.0% with woman owned small business; .9% with service disabled veteran owned small business; 3.0% with veteran-owned small business and 9.8% with hub zone small business. All interested contractors are reminded that the successful contractor will be expected to place subcontracts to the maximum practicable extent with small and disadvantaged firms in accordance with the provisions of Public Law 95-507.

IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO CHECK WWW.FBO.GOV FREQUENTLY FOR ANY AMENDMENTS OR CHANGES TO THE SOLICITATION. NO OTHER ANNOUNCEMENT OF CHANGES WILL BE MADE.

THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY LOSS OF INTERNET CONNECTIVITY OR FOR AN OFFERORS INABILITY TO ACCESS THE DOCUMENTS POSTED AT THE REFERENCED WEBSITE.

NO CDs OR HARD COPIES WILL BE MADE AVAILABLE.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov.

Update #1 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): None

The project consists of improvements of the existing south levee within the Santa Maria levee system. The south levee improvement project includes reaches 1 & 2 that were awarded for construction in early October 2009, and reach 3 which is being considered for this contract. Reach 3 extends about 3.13 miles from Suey Crossing Bridge to Bradley Canyon Confluence. The improvements consist of construction of an 8-ft. wide and about 30-ft. deep compacted soil cement section along the levee riverward side slope and 50 to 62 ft. deep and 1,700 ft. long steel sheet pile along the levee at the upstream end of the soil cement levee portion. Construction of the compacted soil cement levee requires excavation of the existing ground to the approximate depth of 15ft. to 20ft. below the existing grade. Construction of 50-60ft. deep steel sheet pile does not require excavation of the existing levee. Improvements also call for removal, salvage and disposal of existing rock groins. Removal, disposal and installation of the levee signs, fences and gates are also needed for levee improvement. Resurfacing the existing 14 wide ABC levee road with the new 4 thick ABC is necessary for operation and maintenance. There are two existing single-cell (5X2) Reinforced Concrete Box (RCB) culverts, one 36 and one 48 Diameter Reinforced Concrete Pipe (RCP) that need to be extended, modified and included with the new outlet structures. Stone work consists of removal of existing 22 rock groins, salvage and disposal of the removed material at a designated site.

The estimated cost of this project is $10,000,000 - $25,000,000.00.

NOTE: This procurement is issued under full and open competition without exclusion of sources. When applicable, FAR 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns will be applied to this action.

ALL OFFERORS/BIDDERS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: The solicitation will be available on-line on or about 18 December 2009. Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments for this Invitation for Bids will be posted on the Federal Business Opportunity Web Site: www.fbo.gov. Viewing/downloading documents from the site will require prior registration in Central Contractor Registration Web Site: www.ccr.gov. Please note that ALL firms wishing to access the solicitation, both prospective prime contractors and subcontractors, must be CCR-registered, have a MPIN, and either a DUNS number or CAGE code.

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,000,000.00. If the offeror/bidder is a large business, the firm will be required to submit a sub-contracting plan. The plan shall be prepared in accordance with FAR 52.219-9. Failure to submit an acceptable sub-contracting plan may make the bidder ineligible for award of the contact. To be acceptable, the plan must adequately address the six required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of appendix DD, Part 2, AFARS 19.705. The Los Angeles District subcontracting goals are specific percentages of the contractors total planned subcontract amount. The goals are as follows: 70% with small business; 6.2% with small disadvantaged business; 7.0% with woman owned small business; .9% with service disabled veteran owned small business; 3.0% with veteran-owned small business and 9.8% with hub zone small business. All interested contractors are reminded that the successful contractor will be expected to place subcontracts to the maximum practicable extent with small and disadvantaged firms in accordance with the provisions of Public Law 95-507.

IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO CHECK WWW.FBO.GOV FREQUENTLY FOR ANY AMENDMENTS OR CHANGES TO THE SOLICITATION. NO OTHER ANNOUNCEMENT OF CHANGES WILL BE MADE.

THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY LOSS OF INTERNET CONNECTIVITY OR FOR AN OFFERORS INABILITY TO ACCESS THE DOCUMENTS POSTED AT THE REFERENCED WEBSITE.

NO CDs OR HARD COPIES WILL BE MADE AVAILABLE.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov.

Files

File Type Posted
FEB 16 W912PL-10-B-0002.pdf PDF
Plans_Am5.zip ZIP file
Am5.pdf PDF
Am4.pdf PDF
Am3.pdf PDF
AM03Plans.zip ZIP file
Am2.pdf PDF
Am01.pdf PDF
W912PL10B0002_Plan4.zip ZIP file
W912PL10B0002_Plan3.zip ZIP file
W912PL10B0002_Plan2.zip ZIP file
W912PL10B0002_Plan5.zip ZIP file
W912PL10B0002_spec.pdf PDF
W912PL10B0002_Plan1.zip ZIP file
Show all 14

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors