Recovery-Design Build Lightning Protection Upgrade for 13 Fire Lookout sites, Malheur NF

Award Notice Posted

Solicitation number
AG-0489-S-10-0166
Agency
Awarded
to Power Pro, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-0489-C-10-0368 Federal contract award
NAICS code
541310 Architectural Services
PSC
Not on record
Place of performance
Malheur NF (Various Fire Lookout sites) John Day, Oregon 97055, United States

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Total offers received:  Three (3)

Update #3 ·

Recovery-Design Build - Lightning protection upgrade for 13 Fire Lookouts in Malheur National Forest. This project is funded under the provisions of the American Recovery and Reinvestment Act of 2009 (ARRA). This contract will procure the design and construction of lighting upgrades for 13 remote Fire Lookouts stations in the Malheur National Forest. Each site will require a site investigation, engineering reports, design deliverables, construction cost estimates and construction.



The Government anticipates a two-phase award process for this project. The first phase will consists of a down selection of no more than 5 technically acceptable proposals that have acceptable past performance, sound technical solution and reasonable cost estimate. The second phase will consist of evaluating contractor's technical proposals and price to determine who provides the best value to the Government.



This Solicitation is expected to be released on or around 2/8/2010



The Government range for this project is estimated to be between $250,000 and $500,000.



This procurement is full and open competition under the small business competitive demonstration program.





This project is subject to the American Recovery and Reinvestment Act reporting requirements.



Update #2 ·

Recovery-Design Build - Lightning protection upgrade for 13 Fire Lookouts in Malheur National Forest. This project is funded under the provisions of the American Recovery and Reinvestment Act of 2009 (ARRA). This contract will procure the design and construction of lighting upgrades for 13 remote Fire Lookouts stations in the Malheur National Forest. Each site will require a site investigation, engineering reports, design deliverables, construction cost estimates and construction.



The Government anticipates a two-phase award process for this project. The first phase will consists of a down selection of no more than 5 technically acceptable proposals that have acceptable past performance, sound technical solution and reasonable cost estimate. The second phase will consist of evaluating contractor's technical proposals and price to determine who provides the best value to the Government.



This Solicitation is expected to be released on or around 2/8/2010



The Government range for this project is estimated to be between $250,000 and $500,000.



This project is a 100% Small Business set aside.



This project is subject to the American Recovery and Reinvestment Act reporting requirements.



Update #1 ·

Recovery-Design Build - Lighting protection upgrade for 13 Fire Lookouts in Malheur National Forest. This project is funded under the provisions of the American Recovery and Reinvestment Act of 2009 (ARRA). This contract will procure the design and construction of lighting upgrades for 13 remote Fire Lookouts stations in the Malheur National Forest. Each site will require a site investigation, engineering reports, design deliverables, construction cost estimates and construction.



The Government anticipates a two-phase award process for this project. The first phase will consists of a down selection of no more than 5 technically acceptable proposals that have acceptable past performance, sound technical solution and reasonable cost estimate. The second phase will consist of evaluating contractor's technical proposals and price to determine who provides the best value to the Government.



This Solicitation is expected to be released on or around 2/8/2010



The Government range for this project is estimated to be between $250,000 and $500,000.



This project is a 100% Small Business set aside.



This project is subject to the American Recovery and Reinvestment Act reporting requirements.



Files

File Type Posted
AG-0489-S-10-0166 Upgrade Lighting Protection.pdf PDF
Site Maps.pdf PDF
specs.pdf PDF
WD OR080051.pdf PDF
Experience_Questionnaire.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors