RECOVERY-Culvert Replacement - Forest Road 2160 MP 2. 4

Award Notice Posted

Solicitation number
AG-0489-S-09-0061
Agency
Awarded
Set-aside
No set-aside

Opportunity facts

PSC
Not on record
Place of performance
Olympic National Forest 1835 Blacklake Blvd SW Olympia, Washington 98512, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Please note correction to page 97 in the solicitation to FAR clause 52.228-1 Bid Guarantee.



Bid Bond is required at 20% of bid price not 100% of bid price. No other changes to this solicitation

Update #5 ·

The current proposal due date is hereby extended until 11 March 2010 at 4:00pm Pacific time. New specs and designs will be posted for potential vendors to bid on within two weeks. The government reserves the right to extend the due date in the future if needed.

Update #4 ·

The Government is planning on providing Amended specifications on or around Feburary 8, 2010 for this project. The Bid Due date will be extended to a future date after the amended specifications are issued.



Please check back on this site for updated specification and a revised due date.





The current proposal due date is hereby suspended until further notice.



Update #3 ·

The Government is planning on providing Amended specifications on or around Feburary 8, 2010 for this project. The Bid Due date will be extended to a future date after the amended specifications are issued.



Please check back on this site for updated specification and a revised due date.





The current proposal due date is hereby suspended until further notice.



Update #2 ·

THIS IS AN AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 (ARRA) PROCUREMENT.



The U.S. Forest Service, EROC-NW servicing Region 6 has a requirement to replace a culvert with a larger open bottom pipe arch (18 feet span, 9 feet rise, 95 feet long) in accordance with plans and specifications. Work includes traffic control, testing of soil erosion, pollution control; clearing and grubbing, removal of existing culver, excavation and haul of existing fill material; placement and compaction of structural backfill, constructing a stream simulation rock stream channel, placing riprap, placing, shaping an compacting aggregate surfacing; seeding and mulching. Work includes furnishing all materials, excavation, backfill and disposal of excess materials.



The contractor shall provide all management and project administration services, quality control, logistical support, equipment, materials and supplies required to complete the project on time and within schedule in compliance with drawings and specifications. The contractor shall also provide as necessary, flagmen and traffic controls to protect the project and public. Award will be made in sufficient time for planning and preparation to complete work by either August 3, 2010 or September 3, 2010 as directed by the Contracting Officer.



A negotiated, firm fixed price contract is comtemplated requiring a submission of both a technical and a price proposal. Award will be made to the offeror whose proposal offers the best value to the Government. The estimated construction range of magnitude for this project is between $250,000 and $500,000.



The solicitation is expected to be released on or around January 7 2010.



Bids are Due Feb 10, 2010 NLT 1600 HRS PST



This is a full and open competition

Update #1 ·

THIS IS AN AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 (ARRA) PROCUREMENT.



The U.S. Forest Service, EROC-NW servicing Region 6 has a requirement to replace a culvert with a larger open bottom pipe arch (18 feet span, 9 feet rise, 95 feet long) in accordance with plans and specifications. Work includes traffic control, testing of soil erosion, pollution control; clearing and grubbing, removal of existing culver, excavation and haul of existing fill material; placement and compaction of structural backfill, constructing a stream simulation rock stream channel, placing riprap, placing, shaping an compacting aggregate surfacing; seeding and mulching. Work includes furnishing all materials, excavation, backfill and disposal of excess materials.



The contractor shall provide all management and project administration services, quality control, logistical support, equipment, materials and supplies required to complete the project on time and within schedule in compliance with drawings and specifications. The contractor shall also provide as necessary, flagmen and traffic controls to protect the project and public. Award will be made in sufficient time for planning and preparation to complete work by either August 3, 2010 or September 3, 2010 as directed by the Contracting Officer.



A negotiated, firm fixed price contract is comtemplated requiring a submission of both a technical and a price proposal. Award will be made to the offeror whose proposal offers the best value to the Government. The estimated construction range of magnitude for this project is between $250,000 and $500,000.



The solicitation is expected to be released on or around January 7 2010.

Files

File Type Posted
MOU-Jan25_signed.pdf PDF
Amendment 2.pdf PDF
Solicitation R3.docx DOCX document
Solicitation R2.docx DOCX document
Adjusted Schedule of Items.doc DOC document
Revised Drawings FS Rd 2160.pdf PDF
Adjusted Work Descrip.doc DOC document
Past Perf.docx DOCX document
Sol Amend 1.pdf PDF
Solicitation R1.doc DOC document
licitation R1.docx DOCX document
Rd 2160 Drawings20090813_115615.pdf PDF
Solicitation.doc DOC document
Fire Plan.doc DOC document
WA1_dvb.htm HTM file
Show all 15

Notice history