RECOVERY ACT: Dam Repair/Reconstruct - Province Pond/Broken Bridge on the White Mountain National Forest

Award Notice Posted

Solicitation number
AG-4419-S-10-0067
Agency
Awarded
to Drew Corporation
Set-aside
No set-aside

Opportunity facts

Contract number
AG-4419-C-10-0177 Federal IDV award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Place of performance
Carroll County New Hampshire, and Oxford County, Maine, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

This amendment is issued to correct the pre-bid meeting time and location to read:

Date: December 9, 2009 Time: 10:00am EST



Participants will meet at:

Junction of Crocker Pond Road NFSR #18 and Sunken Pond Road NFSR #62, Broken Bridge, ME



From HWY 2, Bethel, ME; South on Route 5 approx. 4 miles, right onto Patte Brook Road approx. 3 miles, left onto Forest Road #18 approx. 1.1 miles, left to Forest Road #62 approx. 0.25 miles, New Access Road to Right (old skid trail).



For Further information Contact Jacob Ormes, 71 White Mountain Drive, Campton, NH 03223

Office: (603) 536-6253, Cell: (603) 726-0783



The response date has been extended to 23 December 2009, 1500 EST.

Update #4 ·

This amendment is issued to correct the pre-bid meeting time and location to read:

Date: December 9, 2009 Time: 10:00am EST



Participants will meet at:

Junction of Crocker Pond Road NFSR #18 and Sunken Pond Road NFSR #62, Broken Bridge, ME



From HWY 2, Bethel, ME; South on Route 5 approx. 4 miles, right onto Patte Brook Road approx. 3 miles, left onto Forest Road #18 approx. 1.1 miles, left to Forest Road #62 approx. 0.25 miles, New Access Road to Right (old skid trail).



For Further information Contact Jacob Ormes, 719 N. Main St, Laconia, NH 03246, 603-528-8741



The response date has been extended to 23 December 2009, 1500 EST.

Update #3 ·

This amendment is to add the applicable clauses.

Update #2 ·

This amendment is to add the solicitation, plans, specifications, and drawings.



This procurement will not be set aside for any particular business group.



Update #1 ·

RECOVERY ACT: This work is located on the Saco/Androscoggin Ranger Districts in Carrol/Oxford Counties in New Hampshire/Maine respectively. It includes reconstruction of two earthen dams provence Pond in NH and Broken Bridge in ME. Work consists of, but is not limited to, permit administration, clearing/grubbing, excavation/embankment, conctete, and incidental construction. Province Pond has limited vehicle access, concrete is to be flown in by helicopter with longline bucket.

Files

Show all 14

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors