NV/AZ FTBR US93(2), Hoover Dam Access Road
Award Notice Posted
- Solicitation number
- 6982AF18B000007
- Agency
-
Federal Highway Administration
Department of Transportation
- Awarded
- to Eagle Peak Rock & Paving, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- 6982AF18C000013 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Hoover Dam Boulder City, Nevada 89005, United States
Notice details come from SAM.gov. Updated .
Notice text
NV/AZ FTBR OLD US93(2), Hoover Dam Access Road
The Central Federal Lands Highway Division (CFLHD) of the Federal Highway Administration (FHWA), in cooperation with the Bureau of Reclamation (BOR) is proposing to rehabilitate the Hoover Dam Access Road and associated parking lots through the NV/AZ FTBR OLD US93(2), Hoover Dam Access Road project. The Hoover Dam Access Road project is located at the Hoover Dam, approximately 33.5 miles east of Las Vegas, NV. The project does cross the dam, with work in both Nevada and Arizona.
The project focuses on a pavement preservation approach to the existing roadway and parking lots, consisting of primarily surface treatments, ranging from a crack sealing and pavement patching to micro-surfacing, thin bonded overlays and pavement milling and asphalt overlays.
SIGNIFICANT QUANTITIES (Schedule B):
Schedule A:
•· 40301-0100, Asphalt Concrete Pavement, Type 1, 1,600 TON
•· 41801-2000, Asphalt Concrete Pavement Patch, Type 2, 2,100 SQYD
•· 42901-0000, Ultra-Thin Bonded Wearing Course, 2,500 TON
•· 63402-0300, Pavement Markings, Type B, Solid and Broken, 35.5 MILE
Option X:
•· 40901-2000, Micro Surfacing, Type 2, 38,850 SQYD
•· 63402-0300, Pavement Markings, Type B, Solid, 13.0 MILE
Option Y:
•· 30402-5300, Full Depth Reclamation, Method 2, 6-Inch Depth, 6,500 SQYD
•· 40301-0100, Asphalt Concrete Pavement, Type 1, 1,000 TON
MISCELLANEOUS: The contractor will be required:
•· To provide the Bureau of Reclamation a minimum of 3 days notice for all equipment and fuel being delivered to the project site. No equipment will be allowed to mobilize to the site and no fuel deliveries will be allowed without advance notification.
•· Pay differing Davis-Bacon wage rates for Arizona and Nevada. The contractor will need to track the work in each state to insure the proper Davis-Bacon wages are paid where the work is performed.
•· Provide a historical monitor for all construction operations within 3' of the historical rock wall located at Hoover Dam project site for Schedule A and Option X.
•· Perform all asphalt milling, asphalt patch repairs, and asphalt concrete pavement placement during the night for Schedule A.
•· Maintain traffic and traffic control to keep the traveling public safe during all construction operations.
It is anticipated that the project will be advertised in December, 2017 with a Notice to Proceed issued in February, 2018.