- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Glenwood, New Mexico 88039, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is for the NM FLAP 159(1) Catwalk Access Road project. The Department of Transportation Federal Highway Administration seeks to replace 5 miles of roadway surfacing and improve erosion protection along the road within the Gila National Forest in Catron County, New Mexico. Major work items include embankment construction, riprap placement, gabion construction, concrete and asphalt paving, reconstruction of low water crossings, and aggregate and culvert placement. The anticipated advertisement date is June 2023 with an award date of July 2023 and construction is slated to occur between August 2023 and November 2024.
There is no set-aside designated for this project. Estimated values range from $5-10 million. Key work items include 6,000 cubic yards of embankment construction, 2,300 cubic yards of riprap, 700 cubic yards of gabions, 15,000 tons of roadway aggregate, 8,000 tons of asphalt, and 700 linear feet of culvert pipe. The proposed schedule has advertisement in June 2023, award in July 2023, and construction from August 2023 through November 2024.
Notice text
THIS IS NOT AN INVITIATION FOR BID, PLANS AND SPECIFICATIONS ARE NOT AVAILBLE
PROJECT NUMBER: NM FLAP 159(1)
PROJECT NAME: Catwalk Access Road
PROJECT DESCRIPTION:
The NM FLAP 159(1) project is located in Catron County, NM within the Gila National Forest. This project will replace the surfacing and improve erosion protection along 5.0 miles of roadway.
SCOPE OF THE WORK:
The major work elements include embankment construction, riprap placement, gabion construction, concrete paving, reconstruction of low water crossings, aggregate placement, culvert construction, and asphalt placement.
PRINCIPAL WORK ITEMS:
- Embankment Construction CUYD 6,000
- Riprap CUYD 2,300
- Gabions CUYD 700
- Roadway Aggregate TONS 15,000
- Asphalt TONS 8,000
- Culvert Pipe LNFT 700
ANTICIPATED SCHEDULE:
The anticipated advertisement date is June 2023 with an award date of July 2023. Physical construction activities at the site are anticipated to occur between August 2023 and November 2024.
ESTIMATED COST RANGE:
The proposed project is estimated at a cost of between $5,000,000 and $10,000,000.
Notice history
| Notice | Type | Posted |
|---|---|---|
| NM FLAP 159(1) Catwalk Access Road | Award Notice | |
| NM FLAP 159(1) Catwalk Access Road | Solicitation | |
| NM FLAP 159(1) Catwalk Access Road | Pre-Solicitation | |
| NM FLAP 159(1) Catwalk Access Road | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity