About this opportunity

This pre-solicitation notice seeks capability statements from contractors interested in constructing a substation to provide power to container handling cranes at the Military Ocean Terminal Concord facility in California. The Department of the Army Corps of Engineers Engineering District Sacramento intends to issue a solicitation in April 2022 for a firm-fixed price construction contract with a period of performance of 365 calendar days. Interested parties must submit responses by January 24, 2022 to the point of contact provided, with responses limited to 10 pages and including details on the offeror's experience, size, socioeconomic status, and bonding capacity.

The NAICS code is 237130 for power and communication line structure construction, with a size standard of $39.5 million. There is no set-aside designated at this time, though the agency will consider setting aside the procurement for small businesses in socioeconomic categories such as 8(a), HUBZone, woman-owned, veteran-owned, or service-disabled veteran-owned. The estimated value of the construction is between $5-10 million. Respondents will provide details of relevant past projects valued over $5 million as well as their self-performance percentage on comparable work.

Notice text

This Sources Sought Notice is for Market Research ONLY to determine the availability, capability, and interest of small business firms for a potential small business category type set-aside.   

NO AWARD will be made from this Sources Sought Notice.   

NO SOLICITATION, SPECIFICATIONS, OR DRAWINGS ARE AVAILABLE AT THIS TIME as this is solely for Market Research. Please do not request such documentation.  Requests for any of this information will go unanswered.   

If the conditions at FAR 19.502-2(b) are met the contracting officer is required to set the acquisition aside for small business concerns. If set-aside, FAR 52.219-14, requires that for general construction the small business contractor will self-perform at least 15% of the cost of the contract, not including the cost of materials. Accordingly, interested contractors having the skill, capabilities, workload capacity and ability to obtain bonding necessary to complete the described project (either through self-performance and/or the managing of subcontractors) are invited to provide their capability statements to the point of contact listed below.  All responses will be used to determine the appropriate acquisition strategy for a potential acquisition.   

The purpose of this notice is to obtain a snapshot of current market capabilities and gain knowledge of potential small business sources to include small business in the following socioeconomic categories: Certified HUB Zone; Woman-Owned Small Business (WOSB) and Serviced-Disabled Veteran-Owned Small Business (SDVOSB); Veteran Owned Small Business (VOSB) and 8(a) small business concerns to perform MOTCO Wharf 2 Generator Site Work.  Other than small businesses are encouraged to express interest and submit capability statements as well.    

Contractors’ capabilities will be reviewed solely for the purpose of determining an appropriate acquisition strategy to include whether this prospective action is appropriate to be set-aside for the small business community or should proceed as an unrestricted full and open acquisition.   Other than small businesses are encouraged to respond to this NOTICE to provide a greater context of current market capabilities. However, per the Federal Acquisition Regulations, preference will be given to the small business categories as listed above. In determining the acquisition strategy, the Government must ensure there is adequate competition among the potential pool of available contractors.  

The Government estimates issuing a solicitation in April 2022. 

The Government intends to award a Firm-Fixed Price contract and the period of performance is 365 calendar days.

In accordance with FAR 36.204(g) the estimated magnitude of construction is expected to be between $5,000,000 and $10,000,000

The NAICS Code is 237130 – Power and Communication Line and Related Structures Construction. The size standard is $39,500,000.  Product Service Code is 6120 Transformers: Distribution and Power Station.

GENERAL SCOPE: 

The scope of the Wharf 2 Substation Project is to construct a substation to provide power to two (2) containerized cargo handling gantry cranes, including a 3750 KVA isolation transformer, 300 KVA step down transformer, grounding, switchgear, circuit breakers, control, low and medium voltage circuits, and ground fault monitoring. Supporting facilities include fencing, bollards, light poles, area receptacles, lightning protection, and grounding grid with bonding to adjacent prominent metal objects and air terminal down-conductors, equipment housekeeping pads, substation concrete pad, and concrete-encased conduit and insulated cables.

CAPABILITY STATEMENT 

The following requests are designed to inform the US Army Corps of Engineers, Sacramento District, of current construction contractor market capabilities. Please provide your response to the following.  The submission is limited to 10 pages. 

1) Offeror's name, DUNS#, address, point of contact, phone number, and e-mail address. 

2) Offeror's experience and capability to complete (either through self-performance in excess of 15% or the managing of one or more subcontracts as a Prime) contracts of this magnitude and complexity and comparable work performed within the past 6 years. Describe the Prime’s self-performed effort, brief description of the project, customer name, timeliness of performance, customer satisfaction, and dollar value of the project - provide at least 3 examples.  

3) Offeror's socioeconomic type and business size (Certified HUB Zone; Woman-Owned Small Business (WOSB) and Serviced-Disabled Veteran-Owned Small Business (SDVOSB); Veteran Owned Small Business (VOSB) and 8(a) small business concerns). 

4) Offeror's Bonding Capability in the form of a letter from Surety. 

The Capabilities Statement will not be considered an offer (proposal) or a bid for any future Request for Proposal or Invitation for Bid that may result from this notice. Moreover, it will not restrict the Government to an ultimate acquisition approach.   

This notice is for information and planning purposes only.  The respondents will not be notified of the results of any review conducted of the capability statements received.  

Please notify this office in writing via email by 24 January 2022 at 3:00 p.m. PST. Submit response and information through email to: Mary.M.Noonan@usace.army.mil. Please include the Sources Sought No. W9123822S0015 in the subject line.   

Notice history

Notice Type Posted
Military Ocean Terminal Concord (MOTCO) Wharf 2 Substation Award Award Notice
Military Ocean Terminal Concord (MOTCO) Wharf 2 Substation Latest solicitation Solicitation
USACE SPK DBB Construction - Military Ocean Terminal Concord (MOTCO) Wharf 2 Substation – Concord, California Pre-Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
CSSC Utility Feed Transformer Replacement 790 East Old Romeo Road, Lockport, IL 60441 60441 · NAICS 237130 ENDIST Chicago No set-aside
Kautz road substation construcion, UIP subproject 2- KRS Batavia, Illinois 60510, United States · NAICS 237130 Fermi National Accelerator Laboratory No set-aside