US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Newark, New Jersey, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, New York District, intends to solicit proposals for maintenance dredging of portions of the Newark Bay Federal Navigation Project in New Jersey. Approximately 600,000 cubic yards of sediment will be removed from the Main and Port Newark Channels to depths of -40 to -50 feet MLLW using a mechanical dredge with an environmental bucket. Dredged material must meet all federal, state, and local placement criteria and will be transported to a contractor-provided upland site. Bidders must demonstrate an integrated production rate of 2,500 cubic yards per day to minimize channel closure time. Plans and specifications will be available in April 2022 with bids due in May 2022 and contract award anticipated for July 2022.
There is no set-aside designation for this procurement. The primary NAICS code is 237990 and PSC code is D203 for dredging services. The work is estimated to cost between $25-100 million and take place between August 2022 through March 2023. Liquidated damages of $2,648 per day will be assessed for delays in completion of dredging, transportation, dewatering, and placement of all material by the required end date.
Notice text
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the Newark Bay, New Jersey, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 600,000 cubic yards (CY) of selected critical shoals from the Main and Port Newark Channels of Newark Bay. Dredging in these channels would be required to depths of -40 feet and -50 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt and clay.
Due to restrictions found in the New Jersey Department of Environmental Protection Water Quality Certificate, the proposed work can only be performed by utilizing a mechanical dredge with a closed clamshell environmental bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government.
The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements.
Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed, and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact.
Plans and specifications for the subject project are expected to be available in April 2022, with bid opening in May 2022. It is the intention of the government to award in July 2022 and the proposed work is anticipated to take place between August 2022 and March 2023. The work is estimated to cost between $25,000,000 and $100,000,000.
Liquidated damages of $2,648.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete.
This is an unrestricted Procurement.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Maintenance Dredging of Newark Bay, New Jersey, Federal Navigation Project | Award Notice | |
| Maintenance Dredging of Newark Bay, New Jersey, Federal Navigation Project | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity