Interior Space Renovation
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 70Z027-26-R-00007
- Agency
-
Coast Guard
Department of Homeland Security
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- New Jersey 08234, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Coast Guard Air Station Atlantic City seeks removal and replacement of drywall, insulation, flooring, carpet, cove base, and interior finishes in specified areas, with sealed offers due May 19, 2026 at 3:00 PM Eastern Time. This is a 100% small business set-aside under NAICS 236220 (Commercial and Institutional Building Construction), with a $45 million annual size standard.
Place of performance is Egg Harbor Township, New Jersey. The contractor must commence work within 30 calendar days of receiving notice to proceed and complete all work within 120 calendar days. The Base Bid encompasses drywall removal and installation (minimum 5/8-inch thick, Class A fire-rated), interior paint with low-VOC requirements, carpet tile (modular 12" × 48"), ceramic tile in Room 235, luxury vinyl tile in the Command Suite and three adjoining offices, PVC ceiling tiles (Class A fire-rated), pipe and duct insulation, and kitchenette cabinetry replacement. Optional Bid Item #1 includes epoxy flooring (four-coat, 100% solids system with double broadcast flake) in five designated areas totaling approximately 2,725 square feet. All materials must be free from lead, chlorine compounds, mercury, cadmium, PDBEs, phthalates, and PFOAs. The contractor must provide Safety Data Sheets and Technical Data Sheets for all products, obtain required permits and licenses, and provide a one-year warranty on all workmanship. The government will supply ceiling tiles.
This is a Firm-Fixed Price contract. Performance and payment bonds are required within 15 calendar days after award. Written questions are due by noon on May 15, 2026. Evaluation uses a lowest-price-technically-acceptable approach with technical capability and price factors. Site visits are strongly encouraged and can be arranged with James Smith at (609) 677-2197 or James.H.Smith@uscg.mil with at least three business days' notice. All visitors must provide valid Real ID or Passport, full name, date of birth, and last four digits of Social Security Number. The contracting officer is Sergio Cosby at Sergio.A.Cosby@uscg.mil.
Notice text
6 versions
Update #6 · Latest ·
SF-1442 has been updated to reflect the correct Solicitation number as posted in SAM.gov as well as the updated deadline.
Due to incorrect Wage Determinations list being previously posted, the correct Davis-Bacon Wage Determinations lists for Atlantic County has been cited in the attachments section. In order for all interested vendors to make adjustments, the solicitation closing date has been moved to Tuesday May 19th at 3:00pm.
Q&A:
12MAY2026 - Responses
- Ceramic Tile states repair cracked, loose, or delaminated tiles but also states tiles replacement. Which is correct? Answer: Replace
- Please confirm we are only extending the existing tile floor throughout the balance of the room? Answer: Correct. Extending ceramic tile in Rm 235.
- Luxury Vinyl Tile states, repair cracked, loose or delaminated tiles. Please confirm that this should be a full removal and replacement of the LVT? Answer: Remove and replace LVT floor in Command Suite and the 3 adjoining offices.
- The only room noted for new ceiling tiles is Rm. 243, is this correct? Answer: Yes, this is correct.
- At the site visit it was noted that the facility will supply all ceiling tile, is this correct? Answer: We will provide the ceiling tiles.
- What permits are anticipated for this project? Answer: No permits are expected.
- What is the specification required for the new kitchen cabinets? Answer: Replace in kind
- The scope provides a 60-day period of performance which is not sufficient for material lead times and work performance, is the government willing to consider extending the POP to 120 or 180 days? Answer: Yes, POP has been extended to 120 days.
Prior Responses:
Q: Where can I find the bid docs required, I went on the site and all I see if a solicitation form? Answer: Submit the SF-1442 with pricing filled into Block 17 along with any company specific package prepared for proposal submission to the federal government.
- Can the Government extend the period of performance to 120 days to allow sufficient time for the delivery of kitchen cabinets? Answer: Yes. SOW & SF-1442 have been amended to reflect the changes in the POP. Due date for solicitations has been extended to 15 May 2026 to permit adjustments for interested vendors.
- Will the contractor be permitted to use the on-site restroom facilities, or is the contractor required to provide a portable restroom? Answer: No. Contractors shall supply portable restrooms.
- On which floor of the building will the work be performed, and is an elevator available for the contractor's use? Answer: work will be performed on the first and second floors, no elevator is available.
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Update #5 ·
Due to incorrect Wage Determinations list being previously posted, the correct Davis-Bacon Wage Determinations lists for Atlantic County has been cited in the attachments section. In order for all interested vendors to make adjustments, the solicitation closing date has been moved to Tuesday May 19th at 3:00pm.
Q&A:
12MAY2026 - Responses
- Ceramic Tile states repair cracked, loose, or delaminated tiles but also states tiles replacement. Which is correct? Answer: Replace
- Please confirm we are only extending the existing tile floor throughout the balance of the room? Answer: Correct. Extending ceramic tile in Rm 235.
- Luxury Vinyl Tile states, repair cracked, loose or delaminated tiles. Please confirm that this should be a full removal and replacement of the LVT? Answer: Remove and replace LVT floor in Command Suite and the 3 adjoining offices.
- The only room noted for new ceiling tiles is Rm. 243, is this correct? Answer: Yes, this is correct.
- At the site visit it was noted that the facility will supply all ceiling tile, is this correct? Answer: We will provide the ceiling tiles.
- What permits are anticipated for this project? Answer: No permits are expected.
- What is the specification required for the new kitchen cabinets? Answer: Replace in kind
- The scope provides a 60-day period of performance which is not sufficient for material lead times and work performance, is the government willing to consider extending the POP to 120 or 180 days? Answer: Yes, POP has been extended to 120 days.
Prior Responses:
Q: Where can I find the bid docs required, I went on the site and all I see if a solicitation form? Answer: Submit the SF-1442 with pricing filled into Block 17 along with any company specific package prepared for proposal submission to the federal government.
- Can the Government extend the period of performance to 120 days to allow sufficient time for the delivery of kitchen cabinets? Answer: Yes. SOW & SF-1442 have been amended to reflect the changes in the POP. Due date for solicitations has been extended to 15 May 2026 to permit adjustments for interested vendors.
- Will the contractor be permitted to use the on-site restroom facilities, or is the contractor required to provide a portable restroom? Answer: No. Contractors shall supply portable restrooms.
- On which floor of the building will the work be performed, and is an elevator available for the contractor's use? Answer: work will be performed on the first and second floors, no elevator is available.
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Update #4 ·
Q&A:
12MAY2026 - Responses
- Ceramic Tile states repair cracked, loose, or delaminated tiles but also states tiles replacement. Which is correct? Answer: Replace
- Please confirm we are only extending the existing tile floor throughout the balance of the room? Answer: Correct. Extending ceramic tile in Rm 235.
- Luxury Vinyl Tile states, repair cracked, loose or delaminated tiles. Please confirm that this should be a full removal and replacement of the LVT? Answer: Remove and replace LVT floor in Command Suite and the 3 adjoining offices.
- The only room noted for new ceiling tiles is Rm. 243, is this correct? Answer: Yes, this is correct.
- At the site visit it was noted that the facility will supply all ceiling tile, is this correct? Answer: We will provide the ceiling tiles.
- What permits are anticipated for this project? Answer: No permits are expected.
- What is the specification required for the new kitchen cabinets? Answer: Replace in kind
- The scope provides a 60-day period of performance which is not sufficient for material lead times and work performance, is the government willing to consider extending the POP to 120 or 180 days? Answer: Yes, POP has been extended to 120 days.
Prior Responses:
Q: Where can I find the bid docs required, I went on the site and all I see if a solicitation form? Answer: Submit the SF-1442 with pricing filled into Block 17 along with any company specific package prepared for proposal submission to the federal government.
- Can the Government extend the period of performance to 120 days to allow sufficient time for the delivery of kitchen cabinets? Answer: Yes. SOW & SF-1442 have been amended to reflect the changes in the POP. Due date for solicitations has been extended to 15 May 2026 to permit adjustments for interested vendors.
- Will the contractor be permitted to use the on-site restroom facilities, or is the contractor required to provide a portable restroom? Answer: No. Contractors shall supply portable restrooms.
- On which floor of the building will the work be performed, and is an elevator available for the contractor's use? Answer: work will be performed on the first and second floors, no elevator is available.
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Update #3 ·
Q&A:
Q: Where can I find the bid docs required, I went on the site and all I see if a solicitation form? Answer: Submit the SF-1442 with pricing filled into Block 17 along with any company specific package prepared for proposal submission to the federal government.
- Can the Government extend the period of performance to 120 days to allow sufficient time for the delivery of kitchen cabinets? Answer: Yes. SOW & SF-1442 have been amended to reflect the changes in the POP. Due date for solicitations has been extended to 15 May 2026 to permit adjustments for interested vendors.
- Will the contractor be permitted to use the on-site restroom facilities, or is the contractor required to provide a portable restroom? Answer: No. Contractors shall supply portable restrooms.
- On which floor of the building will the work be performed, and is an elevator available for the contractor's use? Answer: work will be performed on the first and second floors, no elevator is available.
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Update #2 ·
Q&A:
- Can the Government extend the period of performance to 120 days to allow sufficient time for the delivery of kitchen cabinets? Answer: Yes. SOW & SF-1442 have been amended to reflect the changes in the POP. Due date for solicitations has been extended to 15 May 2026 to permit adjustments for interested vendors.
- Will the contractor be permitted to use the on-site restroom facilities, or is the contractor required to provide a portable restroom? Answer: No. Contractors shall supply portable restrooms.
- On which floor of the building will the work be performed, and is an elevator available for the contractor's use? Answer: work will be performed on the first and second floors, no elevator is available.
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Update #1 ·
This solicitation is for the completion of removing and replacing drywall, insulation, flooring, carpet, cove base in specified areas as described in the Statement of Work. Please review all attachments for description of work to include drawings.
Files
| File | Type | Posted |
|---|---|---|
| Standard Form 1442 - Interior Finish.pdf | ||
| Construction Wage Determinations_AtlanticCounty_NJ.txt | TXT text file | |
| Standard Form 1442 - Interior Finish.pdf | ||
| SCOPE OF WORK_Revised.pdf | ||
| SCOPE OF WORK_Revised.pdf | ||
| Construction RFQ Clause Template.pdf | ||
| A109.pdf | ||
| Construction RFQ Clause Template.docx | DOCX document | |
| Standard Form 1442 - Interior Finish.pdf | ||
| A108.pdf | ||
| Wage Determinations_Atlantic County_NJ.txt | TXT text file |
Show all 11
Notice history
| Notice | Type | Posted |
|---|---|---|
| Interior Space Renovation | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| USCG ISA Tenant Improvement Construction Project | — | No set-aside | |
| United states coast guard ketchikan alaska new carpet installation | — | No set-aside | |
| RTOIL Office rehab | Naval Air Warfare Center | No set-aside | |
| GAOA Remove and Replace Roofing on Island Park Admin Site Housing Units | Forest Service | Total Small Business | |
| Building 262 Renovation, FLETC Glynco, Georgia | Federal Law Enforcement Training Center | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity