Green River Lake Shopped Shop building Roof Replacement
Closed Solicitation Posted
- Solicitation number
- W912QR24Q0044
- Agency
-
ENDIST Louisville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Campbellsville, Kentucky 42718, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Louisville is seeking proposals for the roof replacement of the Green River Lake Maintenance Building. The scope of work includes the removal and disposal of the existing asphalt roof and felt underlayment, inspection and reporting on the condition of the roof sheathing and fascia boards, and the installation of a new metal roof system with gutters, downspouts, and splash blocks. The contract will be awarded based on the lowest total price to the government, and options are included for the replacement of damaged sheathing and fascia boards beyond predetermined quantities. The solicitation is due on April 16, 2024.
This procurement is set aside 100% for Small Business under NAICS code 236220. The maintenance building measures approximately 7,700 square feet and has a 520 linear foot perimeter. The contractor will be required to complete the work within 90 calendar days of the Notice to Proceed. Two amendments have been issued to the solicitation, with the most recent extending the due date and modifying the metal roofing panel specifications.
Notice text
3 versions
Update #3 · Latest ·
**** Ammendment 0002 issued ******
Solicitation W912QR24Q0044 is hereby modified as follows:
The Solicitation Due date has been extended from 12 April 2024 to 16 April 2024.
A revised Scope of work is attached to this amendment replacing the original.
The metal gauge that has changed from 29 gauge to 24 gauge.
All other terms and conditions remain unchanged
**** Ammendment 0002 Issued *****
**** Ammendment 0001 issued ******
Solicitation W912QR24Q0044 is hereby modified as follow s:
The Solicitation Due date has been extended from 09 April 2024 to 12 April 2024.
All other terms and confitions remain unchanged
**** Ammendment 0001 Issued *****
The Scope of work includes removal and disposal of the existing asphalt roof and felt underlayment down to the roof sheathing, the maintenance building measures approximately 7,700 sq ft and 520 lineal feet perimeter. Within 3 days of roof removal contractor to conduct an inspection of the roof sheathing and fascia boards. Contractor to generate a report of the total square footage of sheathing & lineal feet of fascia boards to be replaced and provide report to the TPOC & Lake Manager, during this inspection the TPOC & Project staff will be allowed to verify the unsuitable sheathing / fascia to be replaced. Options 001 & 002 will be awarded according to the contractor’s square foot / lineal foot unit price on the price breakout schedule. Contractor to remove existing roof penetrations (exhaust vents) and repair / replace roof sheathing. Install new underlayment, metal roofing panels, ridge cap vent, seamless gutters, downspouts, and splash blocks according to the specifications located herein.
Update #2 ·
**** Ammendment 0001 issued ******
Solicitation W912QR24Q0044 is hereby modified as follow s:
The Solicitation Due date has been extended from 09 April 2024 to 12 April 2024.
All other terms and confitions remain unchanged
**** Ammendment 0001 Issued *****
The Scope of work includes removal and disposal of the existing asphalt roof and felt underlayment down to the roof sheathing, the maintenance building measures approximately 7,700 sq ft and 520 lineal feet perimeter. Within 3 days of roof removal contractor to conduct an inspection of the roof sheathing and fascia boards. Contractor to generate a report of the total square footage of sheathing & lineal feet of fascia boards to be replaced and provide report to the TPOC & Lake Manager, during this inspection the TPOC & Project staff will be allowed to verify the unsuitable sheathing / fascia to be replaced. Options 001 & 002 will be awarded according to the contractor’s square foot / lineal foot unit price on the price breakout schedule. Contractor to remove existing roof penetrations (exhaust vents) and repair / replace roof sheathing. Install new underlayment, metal roofing panels, ridge cap vent, seamless gutters, downspouts, and splash blocks according to the specifications located herein.
Update #1 ·
The Scope of work includes removal and disposal of the existing asphalt roof and felt underlayment down to the roof sheathing, the maintenance building measures approximately 7,700 sq ft and 520 lineal feet perimeter. Within 3 days of roof removal contractor to conduct an inspection of the roof sheathing and fascia boards. Contractor to generate a report of the total square footage of sheathing & lineal feet of fascia boards to be replaced and provide report to the TPOC & Lake Manager, during this inspection the TPOC & Project staff will be allowed to verify the unsuitable sheathing / fascia to be replaced. Options 001 & 002 will be awarded according to the contractor’s square foot / lineal foot unit price on the price breakout schedule. Contractor to remove existing roof penetrations (exhaust vents) and repair / replace roof sheathing. Install new underlayment, metal roofing panels, ridge cap vent, seamless gutters, downspouts, and splash blocks according to the specifications located herein.
Files
| File | Type | Posted |
|---|---|---|
| W912QR24Q0044 Amendment 0002.pdf | ||
| W912QR24Q0044 Ammendment 0001.pdf | ||
| W912QR24Q0044.pdf |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| NY montezuma NWR main shop roof | — | Total Small Business | |
| Design-Bid-Build - Rough River Lake Axtel Wastewater Treatment Plant (WWTP) | ENDIST Louisville | No set-aside | |
| Roof Repair | Animal and Plant Health Inspection Service | Total Small Business | |
| Design/Build Maintenance and Repair Army Reserve (MRAR), Area Maintenance Support Activity (AMSA) 21, JBMDL, NJ | ENDIST Louisville | Total Small Business | |
| Fenn Ranger Station roofing replacement | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity