About this opportunity
This solicitation from the Department of the Air Force Air Combat Command seeks to fully replace a damaged floating dock at Grassy Pond in Lake Park, Georgia. The selected contractor must demolish the existing dock and install a new galvanized steel T-shaped floating dock measuring 10 feet by 60 feet with an 80-foot walkway and 10-foot entry ramp secured by pilings. The contractor will be evaluated based on meeting specifications for materials, handrails, pilings, permits, demolition, construction, transportation, and providing a one-year warranty. Questions are due by February 13, 2024 and proposals are due February 21, 2024.
This opportunity is set aside for small businesses only and has a place of performance of 5360 Grassy Pond Rd, Lake Park, GA 31636. The replacement dock must be installed by the contractor within a standard timeline and include eight 6-foot galvanized steel pilings. Estimated values are unavailable, but the contractor must provide all necessary equipment, tools, materials and labor to fully demolish and replace the damaged floating dock to the specifications provided.
Notice text
3 versions
Update #3 · Latest ·
***UPDATE 2- Q&A posted***
Grassy Pond currently has a floating dock on Lott's Pond that is damaged due to Hurricane Idalia and needs to be replaced. The dock is fully detached from the shore and has no pilings keeping it in place.
All sizing of equipment must be similar or equal
23d FSS requires the full replacement of a floating dock on Lott's Pond.
• 1 T-shaped Dock Floating Dock
- All of the framework and handrails will be galvanized steel, a composite deck, and a poly float.
Handrails = 1-1/4" Sch 40 Pipe (1-5/8" OD) with a .140" Wall Thickness Made of Galvanized Steel
Handrails to Encompass Entire Floating Dock Including Entry Way
- 80' Walkway with 10' entry ramp = 90'
Entry Ramp to be secured to the shore with 2 EA 3" Sch 40 Pilings embedded 6' into the ground and include non-slip
- "T" is 10' x 60' (6 EA 5' x 20' sections oriented in a 2 x 3 grid)
- Pilings = 8 EA (3" Sch 40 Galvanized Steel)
6' Minimum Embedded + Depth of the Water + 3' Out of Water
Pilings are to be Hollow in the Middle
Round out Sharp Edges
Drive in the Pilings
- Custom Galvanized Steel Slide Brackets for Pilings = 8 EA
• Must Include:
- All required equipment, tools, materials, including but not limited to aquatic vehicles, storage for materials, forklifts, cranes,
- Fees to obtain any relative permits (i.e. Dig permits)
- All required demolition including concrete/curbing/poles/rods
- Removal of all waste/previously used materials including but not limited to removal of the current floating dock at Lott's Pond
- All required construction to include but not limited to pilings/footers and assembly of the floating dock
- All required transportation/travel
Standard 1-year warranty to be provided by Contractor.
Deliver to 5360 Grassy Pond Rd , Lake Park, GA 31636
Update #2 ·
***UPDATE- If you plan on attending the site visit on Feb 7th at 12 pm. Please send me an email to RSVP***
Grassy Pond currently has a floating dock on Lott's Pond that is damaged due to Hurricane Idalia and needs to be replaced. The dock is fully detached from the shore and has no pilings keeping it in place.
All sizing of equipment must be similar or equal
23d FSS requires the full replacement of a floating dock on Lott's Pond.
• 1 T-shaped Dock Floating Dock
- All of the framework and handrails will be galvanized steel, a composite deck, and a poly float.
Handrails = 1-1/4" Sch 40 Pipe (1-5/8" OD) with a .140" Wall Thickness Made of Galvanized Steel
Handrails to Encompass Entire Floating Dock Including Entry Way
- 80' Walkway with 10' entry ramp = 90'
Entry Ramp to be secured to the shore with 2 EA 3" Sch 40 Pilings embedded 6' into the ground and include non-slip
- "T" is 10' x 60' (6 EA 5' x 20' sections oriented in a 2 x 3 grid)
- Pilings = 8 EA (3" Sch 40 Galvanized Steel)
6' Minimum Embedded + Depth of the Water + 3' Out of Water
Pilings are to be Hollow in the Middle
Round out Sharp Edges
Drive in the Pilings
- Custom Galvanized Steel Slide Brackets for Pilings = 8 EA
• Must Include:
- All required equipment, tools, materials, including but not limited to aquatic vehicles, storage for materials, forklifts, cranes,
- Fees to obtain any relative permits (i.e. Dig permits)
- All required demolition including concrete/curbing/poles/rods
- Removal of all waste/previously used materials including but not limited to removal of the current floating dock at Lott's Pond
- All required construction to include but not limited to pilings/footers and assembly of the floating dock
- All required transportation/travel
Standard 1-year warranty to be provided by Contractor.
Deliver to 5360 Grassy Pond Rd , Lake Park, GA 31636
Update #1 ·
Grassy Pond currently has a floating dock on Lott's Pond that is damaged due to Hurricane Idalia and needs to be replaced. The dock is fully detached from the shore and has no pilings keeping it in place.
All sizing of equipment must be similar or equal
23d FSS requires the full replacement of a floating dock on Lott's Pond.
• 1 T-shaped Dock Floating Dock
- All of the framework and handrails will be galvanized steel, a composite deck, and a poly float.
Handrails = 1-1/4" Sch 40 Pipe (1-5/8" OD) with a .140" Wall Thickness Made of Galvanized Steel
Handrails to Encompass Entire Floating Dock Including Entry Way
- 80' Walkway with 10' entry ramp = 90'
Entry Ramp to be secured to the shore with 2 EA 3" Sch 40 Pilings embedded 6' into the ground and include non-slip
- "T" is 10' x 60' (6 EA 5' x 20' sections oriented in a 2 x 3 grid)
- Pilings = 8 EA (3" Sch 40 Galvanized Steel)
6' Minimum Embedded + Depth of the Water + 3' Out of Water
Pilings are to be Hollow in the Middle
Round out Sharp Edges
Drive in the Pilings
- Custom Galvanized Steel Slide Brackets for Pilings = 8 EA
• Must Include:
- All required equipment, tools, materials, including but not limited to aquatic vehicles, storage for materials, forklifts, cranes,
- Fees to obtain any relative permits (i.e. Dig permits)
- All required demolition including concrete/curbing/poles/rods
- Removal of all waste/previously used materials including but not limited to removal of the current floating dock at Lott's Pond
- All required construction to include but not limited to pilings/footers and assembly of the floating dock
- All required transportation/travel
Standard 1-year warranty to be provided by Contractor.
Deliver to 5360 Grassy Pond Rd , Lake Park, GA 31636
Files
| File | Type | Posted |
|---|---|---|
| Grassy Pond Dock QA.docx | DOCX document | |
| Combo-Synopsis.pdf | ||
| Combo-Synopsis.pdf | ||
| 1- Statement of Work Grassy Pond Dock.pdf | ||
| 3-Grassy Pond Map.pdf | ||
| 2-Dock Photos.pdf |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Guatemala - Tactical Dock | US Embassy Guatemala City | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity