Fire alarm replacement, tmfjb, wash DC
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- AOCACB24R0043
- Agency
-
Architect of the Capitol
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Washington, District of Columbia 20002, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Architect of the Capitol is seeking capabilities statements from firms interested in replacing the fire alarm system at the Thurgood Marshall Federal Judicial Building in Washington D.C. The project objectives are to replace aging equipment with a modern, addressable system compliant with current codes and standards. The solicitation is anticipated to utilize best value tradeoff evaluation criteria, assessing experience, technical approach, past performance, and price. Responses to the pre-solicitation notice are due February 27, 2024.
There is no set-aside designation. The anticipated NAICS code is 236220 and work is estimated to begin in spring 2025, taking 18-24 months to complete. The total project cost is estimated between $22-28 million, including base work and options to upgrade smoke detection. The existing system contains approximately 1,100 fire alarm components across ten floors and basement levels. Replacement is to proceed in 12 phases to maintain functionality throughout construction.
Notice text
SOURCES SOUGHT AOCACB24R0043 – FIRE ALARM REPLACEMENT, TMFJB, WASH DC
The Architect of the Capitol (AOC) is issuing a Sources Sought Announcement a FIRE ALARM REPLACEMENT project at Thurgood Marshall Federal Judicial Building (TMFJB) in Washington, DC. This announcement is to determine the interest, availability, and capability of firms to perform the work described below. The NAICS code for this procurement is 236220. The RFP/Solicitation is scheduled to be issued in JULY 2024. The construction is expected to start in the Spring of 2025 and last 18-24 months. The estimated construction cost is estimated between $22,000,000 and $28, 000.000 (this includes Base and Options)
SOLICITATION
The solicitation is expected to include the following:
Base CLIN 001 – Full Fire Alarm Replacement
Option CLIN 002 – Smoke Detection Upgrade – all work will be completed in Base period of performance. The Government has 30 days after contract NTP to award the Option.
Anticipated Best Value/Tradeoff (Lowest Price Technically Acceptable) evaluation criteria are as follows:
Factor 1 – Prime Personnel
Factor 2 – Prime Experience
Factor 3 – Subcontractor Experience
Factor 4 – Technical Approach/Schedule
Factor 5 - Past Performance
Factor 6 – Price (not rated)
OBJECTIVES
Introduction:
The Thurgood Marshall Federal Judiciary Building (TMFJB) Fire Alarm (FA) Replacement Study & Design project objective is to replace the existing Simplex 4100 fire alarm system with a new modern addressable fire alarm system.
The project must achieve the following:
- Provide a more maintainable, reliable, fully functional addressable fire alarm system.
- Design shall be in accordance with IBC 2015, NFPA 72-2016, 2018 AOC Design Standards, AOC A/E Design Manual.
- Replace existing fire alarms control equipment and fire alarm equipment.
- Provide interior finish work such as gypsum wall bord, ceiling panels and painting walls.
- Demolish existing fire alarm equipment.
- New system shall incorporate and maintain the controls of the smoke management and smoke removal systems.
- New system shall allow for modular expansion.
- Prioritize parallel fire alarm infrastructure to maintain continuity of operation while system is being replaced to limit outages.
- Achieve the project goals without harmful impact to the architecturally significant spaces and materials identified in the Building’s Preservation Guide. Design impacts to all spaces and materials to be reversible to the greatest possible extent.
- Quantity of Existing Fire Alarm System Components:
Project Summary Statement:
Fire Alarm Replacement Study & Design, AOC Project No. SC22005R, will provide a design to replace the existing fire alarm control equipment (head-end) and devices in kind to achieve a fully functional addressable fire alarm system utilizing the latest model equipment and technology. The Study outlined in this document shall dictate if the existing fire alarm backbone and field circuits can be retained, repaired, or added to.
Executive Summary:
This project was commissioned by AOC to address ongoing concerns of the existing TMFJB fire alarm systems. The existing system breakdowns, false alarms, and repairs are increasing as the equipment ages, and replacement parts are difficult to obtain. Without timely replacement, there is potential for further deterioration to the system and an increased risk of failure.
The existing building includes three stories below grade and seven stories above grade and utilizes Type IIA construction with a total area of approximately 1,100,000 sf. The TMFJB is provided with a complete automatic sprinkler system. A voice evacuation fire alarm system with speaker/strobe notification is provided for the building. Partial coverage automatic smoke detection is provided in select locations for elevator recall and within air duct systems as well as limited locations in the office suites.
Field surveys of the fire alarm and smoke control systems were performed to observe the existing systems and identify existing deficiencies, areas of non-compliance, or where industry best practices could reduce the fire and life safety risk of the facility. Based upon the options outlined in the POR, the Architect of the Capitol has selected the option for a full replacement of the existing fire alarm system, with an alternate for smoke detection throughout the building.
The Contractor shall provide all supervision, plant, labor, materials, tools, and equipment, to carry out all work and operations as necessary. All work shall be completed in accordance with all federal, state, District and local laws and regulations.
Project Overview: Phasing:
• Phase 1A: FCC
• Phase 1B: Mezzanine, Network Raceways, and Remote-Control Unit Cabinets
• Phase 2: Upper/Lower Garage
• Phase 3: Concourse Level
• Phase 4: Ground Floor
• Phase 5: Level 2
• Phase 6: Level 3
• Phase 7: Level 4
• Phase 8: Level 5
• Phase 9: Level 6
• Phase 10: Level 7 and Penthouse
• Phase 11: Transition Smoke Control
• Phase 12: Demolition of all Existing Head End Equipment
Phase 1A:
- Consolidate, remove smoke removal equipment
- Install FACU cabinet
- Install FACU battery, amplifier & NAC cabinets
- Install interconnecting raceways
- Rough-in inspection
- Pull cable
- Test fiber & cable
- Cable install inspection
- Install control equipment
- Program Mezzanine & Garage levels
Phase 1B:
- Install data & DAL riser’s raceways
- Install remote NAC, amplifier & FAC cabinets
- Install raceway
- Rough-in inspection
- Pull riser fiber
- Pull Mezzanine wire & cable
- Test fiber
- Test cable
- Cable install inspection
- Install field devices
- Contractor performs pretest & checkout of system programming
- Owner acceptance test
- Decommission and tag-out existing
Phase 2 through 10:
-
- Install raceway
- Rough-in Inspection
- Pull riser fiber
- Pull upper & lower garage wire & cable
- Test fiber
- Test all cable
- Cable install inspection
- Install field devices
- Contractor performs pretest & checkout of system programming
- Owner acceptance test
- Decommission & tag-out existing system devices
Phase 11:
- Transition Smoke control
Phase 12:
- Demolition of all existing head-end equipment.
INTERESTED PARTIES
Interested firms should submit a capabilities package to include their qualifications and experience with performing projects of similar size, nature and complexity. Please indicate what qualifications, certifications, or past experience uniquely qualifies the offeror's firm to perform the above-described work. Please include at least two specific examples of the firm's experience performing the work requirements stated above. The projects must have been performed within the last ten years. Please indicate the team subcontractors that will be used to support the offeror's effort and include their prior experience and qualifications, if subcontractors are planned to be used.
Responses are limited to 10 pages. Responses are due FEBRUARY 27, 2024. Responses should be addressed to Susan Dunnagan and emailed to susan.dunnagan@aoc.gov . The Government will not pay for any material provided in response to this market survey nor return the data provided. This is not a request to be placed on a solicitation mailing list nor is it a Request for Proposal (RFP) or an announcement of a solicitation. The results of this survey will be considered to be in effect for a period of one year from the date of this notice.
Please do not contact any other AOC personnel regarding this Source Sought notification.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Thurgood Marshall Federal Judiciary Building Fire Alarm Replacement | Award Notice | |
| Thurgood Marshall Federal Judiciary Building Fire Alarm Replacement | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| SACN Replace Fire Alarms and Intrusions Systems | — | Total Small Business |