Fabricate Fish Weir Passage - Foster Dam Oregon
Award Notice Posted
- Solicitation number
- W9127N-17-R-0057
- Agency
-
ENDIST Portland
US Army Corps of Engineers, Department of Defense
- Awarded
- to Transco Industries, Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- W9127N17C0037 Federal contract award
- NAICS code
- 332312 Fabricated Structural Metal Manufacturing
- PSC
- Not on record
- Place of performance
- http://www.nwp.usace.army.mil/Locations/Willamette-Valley/Foster/ Foster Dam, Oregon 97345, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
**********************IMPORTANT NOTE***********************
THE SOLICITATION NUMBER IS CHANGED TO READ W9127N17B0018
****
The purpose of this project is to improve downstream fish passage at Foster dam with a new Fish Weir. The features of work include an improved weir that operates with flows of 300 cfs to 860 cfs, three (3) new stoplogs, and the demolition of an existing fish crane. The fish weir will be installed in existing spillway stoplog slots and will pass water onto the spillway through an approximate opening of 14ft x 9ft. The weir can be constructed offsite. The weight of the new weir is limited by the lifting capacity of the deployment truck-crane on the bridge overhead; the weir is designed to weigh less than 22,000lbs. The new stoplogs will be deployed below the fish weir to set it at elevations required to pass desired flowrates during low and high pool.
Update #1 ·
The purpose of this project is to improve downstream fish passage at Foster dam with a new Fish Weir. The features of work include an improved weir that operates with flows of 300 cfs to 860 cfs, three (3) new stoplogs, and the demolition of an existing fish crane. The fish weir will be installed in existing spillway stoplog slots and will pass water onto the spillway through an approximate opening of 14ft x 9ft. The weir can be constructed offsite. The weight of the new weir is limited by the lifting capacity of the deployment truck-crane on the bridge overhead; the weir is designed to weigh less than 22,000lbs. The new stoplogs will be deployed below the fish weir to set it at elevations required to pass desired flowrates during low and high pool.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| US Moorings Dock Replacement | Award Notice | |
| This notice | Award Notice | |
| Fish Weir, Fish Passage at Foster Dam, Oregon | Pre-Solicitation |
On GovTribe