Expression of Interest/Request for Information for Onsite Concrete Testing Services in Support of Construction of Saltstone Disposal Unit Seven (SDU-7)
Closed Pre-Solicitation Posted
- Solicitation number
- SRR-SCM-2018-00065
- Agency
-
Savannah River National Laboratory
Office of Science, Department of Energy
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 541380 Testing Laboratories and Services
- PSC
- Not on record
- Place of performance
- Savannah River Site Procurement Services Savannah River Remediation LLC Aiken, South Carolina 29808, United States
Notice details come from SAM.gov. Updated .
Notice text
PURPOSE
The purpose of this inquiry is to determine your interest and qualifications as a possible Offeror for onsite concrete testing services in support of construction for the SDU-7 concrete tank project. In addition, this inquiry also provides an opportunity for SRR to ask pertinent questions of potential subcontractors.
GENERAL DESCRIPTION OF SERVICE:
It is anticipated that construction will begin at Savannah River Site in late August 2018 on a 32-million-gallon concrete tank to serve as a low level radioactive solid waste disposal unit. Currently, SRR personnel will be performing various QA/QC functions; however, this EOI requests information from potential subcontractors who would perform various onsite/offsite testing functions in lieu of SRR personnel.
Attached to this EOI is the draft specification for the construction of the tank as well as draft design drawings for the construction of the tank. At the present time, a procurement specification has not been written for the scope associated with this EOI; however, the required services can be found in more detail in sections 1400, 1450, 3300 and 1810 of the attached SDU-7 Tank procurement specification.
Tank information pertinent to this EOI is as follows:
• Tank diameter is 375 feet
• 208 support columns 2 foot in diameter
• 25 walls, 43 ft. tall
• Roof slabs 7 sections, Main slab is 2-foot-thick and will require 14 placements.
• Field cures required
• 8 shrinkage tests required, reference C-C2-Z-00017
• Approximately 102 concrete placements.
EOI/RFI DISCLAIMER
SRR will use the information obtained in your response to this EOI/RFI to determine your firm's
ability and interest in performing this service. THIS EOI/RFI IS FOR INFORMATIONAL
PURPOSES ONLY. THE ATTACHED SCOPE OF WORK AND DESIGN DOCUMENTS ARE
CONSIDERED FOR THIS REQUEST TO BE IN DRAFT FORM.
EXPENSES RELATED TO EOI/RFI FOR INFORMATION SUBMISSIONS
This EOI/RFI does not commit SRR to issue a future solicitation for these services or to award a
subcontract, nor to pay any costs incurred in the development and submission of any response.
EOI/RFI SUBMITTAL INSTRUCTIONS
The response should demonstrate your overall qualifications and proven capabilities in supplying
the equipment and services required to perform the services described in Attachment #1 SDU-7
Procurement Specification. The information specified below is requested.
1. Organization and Experience
Demonstrate that your firm has sufficient resources and experience, or if you propose to perform
the potential subcontract by use of a partnering agreement with another firm, or with the use of
sub-tier subcontractors/suppliers.
2. Service Capability (Equipment, Personnel, and Facilities) and Scope Performance
Provide documentation to indicate that your firm has the capability, equipment, personnel
resources, and facilities necessary to perform the work scope.
3. Quality Assurance Program
Demonstrate your firm's QA Program. Testing lab shall be qualified in accordance with ASTM
E329 including field technicians.
REQUIREMENTS
Potential Offerors need to be aware of SRR Subcontract Requirements as follows:
1. Any subcontract awarded as a result of this EOI will be subject to the Service Contract Act
unless the subcontractor can certify exemption.
2. Environmental Safety and Health Evaluation Worksheet for the past three calendar years
will be required with OSHA 300 logs to support. SRR requires an Experience Modification
Rate (EMR) of 1.0 or less and a Total Recordable Case (TRC) rate of 4.3 or less.
3. Potential Federal Budget constraints will be presented within the RFP.
4. Representations and Certifications will be required and will be part of the RFP.
5. Small Business Subcontracting Plans will be required of Large Business Offerors.
6. North American Industry Classification System (NAICS): 541380
SUBCONTRACT TYPE
It is anticipated that if the requirement referenced in this EOI develops into a future procurement
action, the award will be a fixed-price subcontract. Following a formal RFP and Pre-Proposal
meeting at SRR, a single subcontract is planned; however, SRR reserves the right to make multiple
awards. Award will be made to the Offeror(s) whose proposal(s) best conforms to any resultant
RFP and is determined by SRR to be the most advantageous. SRR will evaluate the proposals
based on a low price/technically acceptable approach.
An award is anticipated in 4th quarter 2018.
SUBMISSION OF RESPONSES
If you do not plan to submit a response, a brief email indicating your lack of interest and reasons
would be appreciated. Offerors can review typical subcontract documents at:
SRRemediation.com, then to Business Opportunities, then to Documents and Forms
EOI responses will be received by SRR via email at the below address until June 15, 2018
COB. If you have any questions, please do not hesitate to contact me at 803-952-8103 or via email
at jonathan.younts@srs.gov.
Files
| File | Type | Posted |
|---|---|---|
| C-SPP-Z-00015_SDU7_Spec._Rev._J1.pdf | ||
| All_Drawings_SDU-7_Tank.pdf | ||
| EOI_-_SDU-7_Onsite_Concrete_Testing.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity