Design-Build, Joint Simulation Environment (JSE) Facility, Edwards AFB, CA

Closed Pre-Solicitation Posted

Solicitation number
W912PL20R0003
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Edwards AFB 222 N. Rosamond Blvd Edwards Afb Ca 93524 USA

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Engineering District Los Angeles is seeking design-build services for the construction of a two-story, 72,140 square foot Joint Simulation Environment facility at Edwards Air Force Base in California. The solicitation requires the facility be constructed in accordance with DoD standards for permanent facilities and antiterrorism requirements. Proposals will be evaluated on past performance, technical approach, project management plan, schedule, and small business participation. The submission deadline is April 22, 2020.

There is no set-aside designation for this procurement. The estimated value is between $25-100 million and the total contract performance period is 720 calendar days. Subcontracting plans are mandatory for large business contracts over $1.5 million. The NAICS code is 237910 for site preparation contractors and the PSC code covers construction of buildings. Firms should monitor the www.fbo.gov website for solicitation documents and any amendments, as no hard copies will be distributed.

Notice text

6 versions

Update #6 · Latest ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on beta.sam.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check beta.sam.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

Update #5 ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

The solicitation will be available on or about December 5, 2019.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on beta.sam.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check www.fbo.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

Update #4 ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

The solicitation will be available on or about mid to late December 2019.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on www.fbo.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check www.fbo.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

Update #3 ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

The solicitation will be available on or about late November 2019.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on www.fbo.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check www.fbo.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

 

Update #2 ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

The solicitation will be available on or about mid/late October 2019.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on www.fbo.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check www.fbo.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

 

Update #1 ·

Design and Construction of a two story 72,140 square foot Joint Simulation Environment (JSE) facility at Edwards AFB, CA. The new facility will be Type IIB. Materials and finishes will take cues from the adjacent buildings and comply with the Edwards AFB Installation Facility Standards (IFS). Work will include reinforced concrete foundation and slab floor, structural steel frame, split-face masonry unit walls, standing seam metal roof, sensitive compartmentalized information facilities (SCIF), special access program facilities (SAPF), fire detection and protection systems, utilities, emergency generator, communication support, pavements, site improvements including covered walkways, existing facility demolition, and all other necessary support. Facilities will be designed as permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism/force protection requirements per UFC 4-010-01.

In accordance with Defense Federal Acquisition Regulations sub-part 236.204(ii), the estimated magnitude of this project is: Between $25,000,000 and $100,000,000. The total contract performance period is 720 calendar days.

The acquisition will be conducted under a competitively negotiated source selection process. The acquisition strategy is Best Value "Tradeoff" This process permits tradeoffs among cost or price and non-cost factors and allows the Government to accept other than the lowest priced proposal. Both a technical proposal and a price proposal will be required. Non-cost factors (evaluation factors) may consist of the following: Past Performance Experience of the Prime Construction Contractor and the Lead Design Firm on projects similar in nature; Technical Approach; Project Management Plan; Schedule; and Small Business Participation Plan. The aforementioned evaluation factors may not be all inclusive.

Plans and specifications will not be provided in hard paper copy. The solicitation and all amendments will be posted on www.fbo.gov

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,500,000.00. If the offeror is a large business, the firm will be required to submit a sub-contracting plan as part of its proposal package.

It is the responsibility of the contractor to check www.fbo.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror's inability to access the documents posted at the referenced website. No CDs or hard copies will be made available.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov

All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, negotiation and/or final award process.

 

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
F-35 Composite Repair and Training Facility / F-35 Maintenance Facility, Hill Air Force Base, Utah Hill Air Force Base, Utah, United States · NAICS 236210 ENDIST Sacramento No set-aside
Solicitation: Construct Combat Rescue Helicopter Flight Simulator Facility at Moffett ANGB Moffett Angb, Santa Clara County, California Moffett Field, California 94035, United States · NAICS 236220 California National Guard Total Small Business
Enhanced Use Leasing Project Edwards Air Force Base Edwards, California 93523, United States · NAICS 53 Air Force Installation Contracting Agency No set-aside
MACH1_AOI_Military Working Dog Facility_ Vandenberg Space Force_LOE 1 and LOE 2 Lompoc, California 93437, United States · NAICS 236220 Air Force Installation Contracting Agency No set-aside
PKA Relocatable Facility FE Warren AFB, Wyoming 82005, United States · NAICS 332311 Global Strike Command Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors