About this opportunity

The U.S. Army Corps of Engineers Louisville District intends to issue a Request for Proposal to construct a new 300-member Army Reserve Center in Newark, Delaware. The solicitation will provide for the construction of a 43,000 square foot combined Army Reserve Center and Branch Maintenance Activity building, as well as an optional 3,000 square foot storage facility. Supporting requirements include site work, security features, and sustainable design elements. Proposals will be evaluated based on technical qualifications, past performance, and price. The deadline for proposal submissions is January 16, 2020.

There is no set-aside designation for this procurement. The project involves construction under NAICS code 236220 and PSC code C211. The contract duration is estimated at 670 calendar days with an anticipated award value above $7 million. Supporting facilities include paved areas, fencing, utilities, and vehicle wash facilities to serve the 300-member Army Reserve Center.

Notice text

3 versions

Update #3 · Latest ·

Construction of a new Army Reserve Center located at Newark, DE.

Update #2 ·

THIS PROJECT IS NOW BEING SOLICITED. PLEASE SEE ATTACHED DOCUMENTS.

The U.S. Army Corps of Engineers (USACE) Louisville District is issuing Request for Proposal (RFP) W912QR20R0001 to Construct a 300 member Army Reserve Center (ARC) on the existing Newark, DE Armed Forces Reserve Center (AFRC) property. Primary facilities include construction of an ARC building, collocated Branch Maintenance Activity (BMA), and organizational storage building. ARC building and BMA will be combined and approximately 43,000 SF. The optional storage building will be approximately 3,000 SF. Buildings will be of permanent construction with reinforced concrete foundations; concrete floor slabs; reinforced concrete or masonry walls; low-slope or sloped roof; Heating, Ventilation and Air Conditioning (HVAC); and plumbing, mechanical, security and electrical systems. Supporting facilities include land clearing, paving, concrete aprons, vehicle wash rack/platform(s), fencing, general site improvements and utility connections. Accessibility for the disabled will be provided. Antiterrorism/Force Protection (AT/FP) and physical security measures will be incorporated into the design including maximum standoff distances from roads, parking areas and vehicle unloading areas. Sustainability/Energy measures will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance. Air Conditioning (Estimated 138 Tons).

This acquisition will be an unrestricted procurements

The magnitude of this construction project is anticipated to be between $10,000,000 and $25,000,000, in accordance with DFARS 236.204

The project contains options such as: concrete or asphalt circulation areas, unheated storage building, and collateral equipment.

SOLICITATION WEBSITE: The official solicitation, when posted, will be available free of charge by electronic posting only and may be found at Federal Business Opportunities website, http://www.fbo.gov. Paper copies of the solicitation will not be issued. Telephone and Fax requests for this solicitation will not be honored. Project files are Portable Document Format (PDF) files and can be viewed, navigated, or printed using Adobe Acrobat Reader. To download the solicitation for this project, contractors are required to register at the Federal Business Opportunities website at http://www.fbo.gov. Amendments, if/when issued, will be posted to the above referenced website for electronic downloading. This will be the only method of distributing amendments prior to closing; therefore, it is the Offerors responsibility to check the website periodically for any amendments to the solicitation.

Offerors shall have and shall maintain an active registration in the following database:

System for Award Management (SAM): Offerors shall have and shall maintain an active registration in the SAM
database at http://www.sam.gov to be eligible for a Government contract award. If the Offeror is a Joint Venture (JV), the JV entity shall have valid SAM registration in the SAM database representing the JV as one business/firm/entity. If at the time of award an Offeror is not actively and successfully registered in the SAM database, the Government reserves the right to award to the next prospective Offeror.

POINT-OF-CONTACT: The point-of-contact for this procurement is Contract Specialist Josh Gitchel, at Joshua.gitchel@usace.army.mil.

The Contract Duration is estimated at 670 calendar days.

Update #1 ·

The U.S. Army Corps of Engineers (USACE) Louisville District intends to issue a Request for Proposal (RFP) W912QR20R0001 to Construct a 300 member Army Reserve Center (ARC) on the existing Newark, DE Armed Forces Reserve Center (AFRC) property. Primary facilities include construction of an ARC building, collocated Branch Maintenance Activity (BMA), and organizational storage building. ARC building and BMA will be combined and approximately 43,000 SF. The optional storage building will be approximately 3,000 SF. Buildings will be of permanent construction with reinforced concrete foundations; concrete floor slabs; reinforced concrete or masonry walls; low-slope or sloped roof; Heating, Ventilation and Air Conditioning (HVAC); and plumbing, mechanical, security and electrical systems. Supporting facilities include land clearing, paving, concrete aprons, vehicle wash rack/platform(s), fencing, general site improvements and utility connections. Accessibility for the disabled will be provided. Antiterrorism/Force Protection (AT/FP) and physical security measures will be incorporated into the design including maximum standoff distances from roads, parking areas and vehicle unloading areas. Sustainability/Energy measures will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance. Air Conditioning (Estimated 138 Tons).

The project contains options such as: concrete or asphalt circulation areas, unheated storage building, and collateral equipment.

The Contract Duration is estimated at 670 calendar days.

Files

File Type Posted
W912QR20R0001Plans-0003.pdf PDF
W912QR20R0001Specs-0003.pdf PDF
Interested Vendor List.pdf PDF
W912QR20R0001-0002.pdf PDF
W912QR20R0001Plans-0001.pdf PDF
W912QR20R0001Specs-0001.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
Design/Build Maintenance and Repair Army Reserve (MRAR), Area Maintenance Support Activity (AMSA) 21, JBMDL, NJ Joint Base MDL, New Jersey, United States · NAICS 236220 ENDIST Louisville Total Small Business
INDUSTRY DAY - Richmond Army Reserve Center - MILCON Richmond, Virginia, United States · NAICS 236220 ENDIST Louisville No set-aside
Delaware Avenue Revetment, Cape May, NJ 08204 · NAICS 237990 ENDIST Philadelphia No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors