CO FTBR Crystal Dam (1), East Portal Access Road
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF21SS0001
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Montrose CO 81401 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is seeking information from contractors interested in bidding on a project to reconstruct and resurface approximately 5.3 miles of the East Portal Access Road located in Montrose County, Colorado. The road provides access to the Bureau of Reclamation's Crystal Dam and Power Plant facilities. The scope of work includes pulverizing and overlaying 5 miles of pavement, reconstructing 0.3 miles, installing rockfall protection measures, cleaning ditches and culverts, and full depth reclamation and paving. Contractors must demonstrate experience with asphalt paving, rock excavation, rock removal, and rockfall protection. The Department of Transportation Federal Highway Administration will evaluate contractors based on statements of intent to bid, certifications, bonding capacity, and prior relevant project experience. Responses are due by November 13, 2020.
There is no set-aside designated for this project. Major work items include roadway excavation, rock bolting, rock doweling, aggregate base, full depth reclamation, and asphalt paving. Significant quantities include 14,500 cubic yards of excavation and 3,500 tons of aggregate base. The NAICS code is 237110 and PSC code is D304. No incumbent is listed. The pre-solicitation notice does not provide an estimated award value or budget range for the road reconstruction and resurfacing work.
Notice text
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
THIS NOTICE IS BEING ISSUED TO DETERMINE IF THERE IS SUFFICIENT INTEREST FROM QUALIFIED PRIME CONTRACTORS who are Small Businesses, HUBZone small businesses, Woman owned small business concerns, 8(a) small businesses, or Service disabled veteran-owned small businesses and who intend to submit a bid for this solicitation to allow for a set-aside in one of these programs MUST submit the following by e-mail to CFLAcquisitions@dot.gov or by telefax to 720-963-3360 (Attn: Jorey Deml) for receipt by close of business (2 p.m. local Denver time) on November 13, 2020:
(1) A positive statement of your intention to submit a bid for this solicitation as a Prime Contractor;
(2) A copy of the letter from SBA stating date of HUBZone small business certification or acceptance to the 8(a) small business program. In the case of a Service Disabled Veteran Owned Small Business Concern, you must provide proof of eligibility (DD form 214 or a letter of adjudication from the Veterans Administration). This information must be provided in order to determine eligibility – DO NOT SEND COPIES OF YOUR SAM PROFILE;
(3) Letter from bonding agent stating your firm’s capability to bond for a single project of $5.5 million , and your firm’s aggregate bonding capacity; and
(4) Provide a list of road construction projects of equal or greater value in which you performed (as the prime contractor) roadway construction work that included asphalt paving, rock excavation (blasting), rock removal (scaling) and rockfall protection. State whether your firm was the prime contract or subcontractor on the project. DO NOT SEND INFORMATION ON PROJECTS THAT DO NOT INCLUDE THE ABOVE WORK. THE PRIME CONTRACTOR MUST DEMONSTRATE PRIOR EXPERIENCE WITH THE ACITIVITIES LISTED IN THIS PARAGRAPH.
The size of a small business firm includes all parents, subsidiaries, affiliates, etc. Refer to the Code of Federal Regulations 13 CFR 121.103 for information on how the SBA determines affiliation and 13 CFR 121.108 regarding the penalties for misrepresentation of size status. All firms should be certified in the All firms should be certified in the System for Award Management (SAM) located at https://www.sam.gov/
A Qualified HUBZone SBC receiving a HUBZone contract for general construction must spend at least 50% of the cost of the contract incurred for personnel on its own employees or employees of other qualified HUBZone SBCs. This requirement may be met by expending at least 50% of the cost of the contract incurred for personnel on its employees or it may subcontract at least 35% of the cost of the contract performance incurred for personnel to one or more qualified HUBZone SBCs. A qualified HUBZone SBC prime contractor may not, however, subcontract more than 50% of the cost of the contract incurred for personnel to non-qualified HUBZone SBCs.
PROJECT DETAILS: CO FTBR Crystal Dam(1) East Portal Access Road
The East Portal Access Road is located in Montrose County, Colorado. The road begins at the intersection with State Highway 347 at the entrance station to the Black Canyon National Park about 6 miles north of US-50. The road continues for 6.85 miles to the northeast where it terminates at the gate to the Crystal Dam facilities road. The Bureau of Reclamation (BOR) maintains the road for access to its Crystal Dam and Power Plant and to the recreational facilities along the Gunnison River. The 21-foot wide road was originally constructed in 1973 and has had no major maintenance projects other than a chipseal done in 2015. The roadway pavement is generally in fair to poor condition. The road has been segmented into three sections based on priority and condition. The upper section from mileposts 0.0 to 2.2, the middle section from mileposts 2.2 to 5.3 and the lower section from mileposts 5.3 to 6.8. The middle section is characterized by steep grades of up to 16%, tall rock cuts (with rockfall problems), poor geometrics, and poor pavement conditions. The focus of the project will be the first 5.3 miles.
The scope of the project would be to pulverize and overlay the pavement 5 miles and reconstruct 0.3 miles. The major items of work will include paving, rock excavation (blasting) and rock removal (scaling), rockfall protection, cleaning the ditches and culverts, and full depth reclamation and paving.
SIGNIFICANT QUANTITIES:
Schedule A:
- 20401-0000 Roadway Excavation: 14,500 CUYD
- 26001-0000 Rock Bolt: 200 LNFT
- 26002-000 Rock Dowel: 100 LNFT
- 30202-2000 Roadway Aggregate, Method 2: 3,500 TON
- 30401-5500 Full Depth Reclamation, Method 2, 8-Inch Depth: 4.890 Mile
- 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, ½-Inch or ¾-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL: 30,000 TON: 11,500 TON
- 623032-0100 Special Labor, Slope Scaling: 150 Hours
- 63401-0300 Pavement Markings, Type B, Solid (White): 110,000 LNFT
- 63401-0300 Pavement Markings, Type B, Solid (Double Yellow): 110,000 LNFT
- 65101-1000 Draped Rockfall Protection, Wire Mesh: 2,250 SQYD
- 65101-2000 Draped Rockfall Protection, Cable Net: 5,000 SQYD
Anticipated Schedule
The anticipated advertisement date is December/January 2020. Construction is anticipated from March 2021 to November 2021.
Funding
The estimated cost range is between $4.5 million and $5.5 million.
Notice history
| Notice | Type | Posted |
|---|---|---|
| CO FTBR Crystal Dam (1), East Portal Access Road | Award Notice | |
| CO FTBR Crystal Dam (1), East Portal Access Road | Solicitation | |
| CO FTBR Crystal Dam (1), East Portal Access Road | Pre-Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| ND NP THRO 204(1) Buck Hill Road | Federal Highway Administration | No set-aside | |
| WY BR WYAO US20(1) US 20 and Hayden Arch Bridge Repairs | Federal Highway Administration | No set-aside | |
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity