CO FTBR Crystal Dam (1), East Portal Access Road

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF21B000004
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Montrose CO 81401 USA

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is for reconstruction and resurfacing work along 5.3 miles of the East Portal Access Road located in Montrose County, Colorado. The Bureau of Reclamation seeks to pulverize and overlay 5 miles of pavement and reconstruct 0.3 miles. Major work includes paving, rock excavation, rockfall protection, cleaning ditches and culverts, and full depth reclamation and paving. Proposals are due by February 27, 2021. The evaluation criteria will focus on experience with similar road construction projects involving steep grades, rock cuts, and pavement rehabilitation.

There is no set-aside designation. Significant quantities of work include 14,500 cubic yards of roadway excavation, 200 linear feet of rock bolting, 100 linear feet of rock doweling, 3,500 tons of roadway aggregate, 4.890 miles of full depth reclamation at an 8-inch depth, and 0.3 to 0.5 miles of asphalt concrete pavement. The primary NAICS code is 237110 (Water and Sewer Line and Related Structures Construction) and the predominant PSC code covers road construction and repair. No incumbents or current contractors were identified.

Notice text

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT DETAILS: CO FTBR Crystal Dam(1) East Portal Access Road

The East Portal Access Road is located in Montrose County, Colorado.  The road begins at the intersection with State Highway 347 at the entrance station to the Black Canyon National Park about 6 miles north of US-50. The road continues for 6.85 miles to the northeast where it terminates at the gate to the Crystal Dam facilities road.  The Bureau of Reclamation (BOR) maintains the road for access to its Crystal Dam and Power Plant and to the recreational facilities along the Gunnison River.  The 21-foot wide road was originally constructed in 1973 and has had no major maintenance projects other than a chipseal done in 2015.   The roadway pavement is generally in fair to poor condition. The road has been segmented into three sections based on priority and condition.  The upper section from mileposts 0.0 to 2.2, the middle section from mileposts 2.2 to 5.3 and the lower section from mileposts 5.3 to 6.8.   The middle section is characterized by steep grades of up to 16%, tall rock cuts (with rockfall problems), poor geometrics, and poor pavement conditions.  The focus of the project will be the first 5.3 miles.

The scope of the project would be to pulverize and overlay the pavement 5 miles and reconstruct 0.3 miles.  The major items of work will include paving, rock excavation (blasting) and rock removal (scaling), rockfall protection, cleaning the ditches and culverts, and full depth reclamation and paving.

SIGNIFICANT QUANTITIES:

Schedule A:

  • 20401-0000 Roadway Excavation: 14,500 CUYD
  • 26001-0000 Rock Bolt: 200 LNFT
  • 26002-000 Rock Dowel: 100 LNFT
  • 30202-2000 Roadway Aggregate, Method 2: 3,500 TON
  • 30401-5500 Full Depth Reclamation, Method 2, 8-Inch Depth: 4.890 Mile
  • 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, ½-Inch or ¾-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL: 30,000 TON: 11,500 TON
  • 623032-0100 Special Labor, Slope Scaling: 150 Hours
  • 63401-0300 Pavement Markings, Type B, Solid (White): 110,000 LNFT
  • 63401-0300 Pavement Markings, Type B, Solid (Double Yellow): 110,000 LNFT
  • 65101-1000 Draped Rockfall Protection, Wire Mesh: 2,250 SQYD
  • 65101-2000 Draped Rockfall Protection, Cable Net: 5,000 SQYD

Anticipated Schedule

The anticipated advertisement date is March 2021.  Construction is anticipated from May 2021 to September 2021.

Funding

The estimated cost range is between $4.5 million and $5.5 million.

Notice history

Notice Type Posted
CO FTBR Crystal Dam (1), East Portal Access Road Award Award Notice
CO FTBR Crystal Dam (1), East Portal Access Road Latest solicitation Solicitation
This notice Pre-Solicitation
CO FTBR Crystal Dam (1), East Portal Access Road Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
ND NP THRO 204(1) Buck Hill Road Medora, North Dakota, United States · NAICS 237310 Federal Highway Administration No set-aside
East canal efficiency improvements NAICS 237110 Bureau of Reclamation Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors