Cleveland East Breakwater West Extension Repair
Closed Solicitation Posted
- Solicitation number
- W912P420B0012
- Agency
-
ENDIST Buffalo
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Cleveland OH 44102 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals to rehabilitate portions of the Cleveland East Breakwater West Extension in Cleveland, Ohio. The U.S. Army Corps of Engineers Buffalo District intends to award a single firm fixed price contract for a period of 364 days to supply all plant, labor, equipment, and materials necessary to install new sheet pile with an additional layer of concrete. Offerors must be designated as a small business by FAR 52.219-6 and comply with wage determination IL20200018 and the Buy American Act. The evaluation criteria will select the lowest priced technically acceptable offer. The closing date for receipt of proposals is August 25, 2020.
The opportunity is set aside for total small businesses. The NAICS code is 237990 and PSC code is R499. The cost is estimated between $1-5 million. A bid guarantee of 20% of the bid amount or $3 million, whichever is less, is required. The period of performance is 364 days to complete all work at the place of performance in Cleveland, Ohio.
Notice text
3 versions
Update #3 · Latest ·
Work on the Cleveland East Breakw ater includes but is not limited to supplying all plant, labor, equipment, and materials necessary to rehabilitate portions of the Cleveland East Breakw ater West Extension. The project is the repair of a portion of the breakwater to include new sheet pile installed w ith an additional layer of concrete.
The Government intends to aw ard one Firm Fixed Price contract f or the Cleveland East Breakw ater project as a result of this solicitation. The contract w ill have a period of performance of 364 days on all work including base and all options if aw arded. Please see Section 01 35 13 of the specifications and FAR Clause 52.211-10 for more information.In order to compete, offerors must be a Small Business as designated by
FAR Clause 52.219-6. The applicable Wage Determination is
IL20200018. The Wage Determination is attached in the solicitation.
The cost of this project is estimated at $1,000,000 to $5,000,000. The Buy American Act is applicable to this acquisition. A Bid Guarantee shall
be submitted w ith the bid to be considered responsive. The amount of the guarantee shall be 20 percent of the bid amount or $3,000,000
whichever is less, see FAR Clause 52.228-1.
Call in Information for both the Pre-bid and Bid Opening will be the same and is listed on page 10 of the attached Solicitation.
Amendment 0001 is adding two additional clauses to Solicitation.
Please see attachment with Bid Abstract.
Update #2 ·
Work on the Cleveland East Breakw ater includes but is not limited to supplying all plant, labor, equipment, and materials necessary to rehabilitate portions of the Cleveland East Breakw ater West Extension. The project is the repair of a portion of the breakwater to include new sheet pile installed w ith an additional layer of concrete.
The Government intends to aw ard one Firm Fixed Price contract f or the Cleveland East Breakw ater project as a result of this solicitation. The contract w ill have a period of performance of 364 days on all work including base and all options if aw arded. Please see Section 01 35 13 of the specifications and FAR Clause 52.211-10 for more information.In order to compete, offerors must be a Small Business as designated by
FAR Clause 52.219-6. The applicable Wage Determination is
IL20200018. The Wage Determination is attached in the solicitation.
The cost of this project is estimated at $1,000,000 to $5,000,000. The Buy American Act is applicable to this acquisition. A Bid Guarantee shall
be submitted w ith the bid to be considered responsive. The amount of the guarantee shall be 20 percent of the bid amount or $3,000,000
whichever is less, see FAR Clause 52.228-1.
Call in Information for both the Pre-bid and Bid Opening will be the same and is listed on page 10 of the attached Solicitation.
Amendment 0001 is adding two additional clauses to Solicitation.
Update #1 ·
Work on the Cleveland East Breakw ater includes but is not limited to supplying all plant, labor, equipment, and materials necessary to rehabilitate portions of the Cleveland East Breakw ater West Extension. The project is the repair of a portion of the breakwater to include new sheet pile installed w ith an additional layer of concrete.
The Government intends to aw ard one Firm Fixed Price contract f or the Cleveland East Breakw ater project as a result of this solicitation. The contract w ill have a period of performance of 364 days on all work including base and all options if aw arded. Please see Section 01 35 13 of the specifications and FAR Clause 52.211-10 for more information.In order to compete, offerors must be a Small Business as designated by
FAR Clause 52.219-6. The applicable Wage Determination is
IL20200018. The Wage Determination is attached in the solicitation.
The cost of this project is estimated at $1,000,000 to $5,000,000. The Buy American Act is applicable to this acquisition. A Bid Guarantee shall
be submitted w ith the bid to be considered responsive. The amount of the guarantee shall be 20 percent of the bid amount or $3,000,000
whichever is less, see FAR Clause 52.228-1.
Call in Information for both the Pre-bid and Bid Opening will be the same and is listed on page 10 of the attached Solicitation.
Files
| File | Type | Posted |
|---|---|---|
| Abstract IGE adjusted_CLE 20.xls | XLS spreadsheet | |
| Amendment 0001 W912P420B0012_17Aug2020.pdf | ||
| Certified Final - RTA - W912P420B0012(21July).pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Cleveland East Breakwater West Extension Repair | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| FY27 Euclid Creek Fishway Construction | ENDIST Buffalo | Total Small Business | |
| Mill Creek Section 205 Flood Risk Management Improvements | ENDIST Walla Walla | No set-aside | |
| Duluth Vessel Yard Phase III Repairs | ENDIST Detroit | Total Small Business | |
| W9123627BA004: NASA Wallops Breakwater Project in Wallops Island, Virginia | ENDIST Norfolk | Total Small Business | |
| TC Dock Structural Repairs | ENDIST Charleston | No set-aside |