This solicitation requests proposals for the rehabilitation of portions of the Cleveland East Breakwater West Extension. Work includes supplying plant, labor, equipment, and materials to install new sheet pile with an additional layer of concrete. The Government intends to award a single firm fixed price contract for a period of 364 days to complete all base work and optional items. Offerors must be designated as a Small Business by FAR 52.219-6. The cost is estimated between $1-5 million. A bid guarantee of 20% of the bid amount or $3 million, whichever is less, is required. The applicable wage determination is IL20200018. The soliciting agency is the Department of the Army Corps of Engineers Buffalo District. The pre-bid and bid opening call-in information is provided on page 10.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidder 1 and 2 (2)

W912P4-19-B-0012response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
GEOGRADEL CONSTRUCTIONKovilic Construction
FY 20 CLE BreakwaterA. HIRED LABORFAIRVIEW, PACHEBOYGAN, MI
Cleveland, OhioB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 376,744.80$ 50,000.00$ 250,000.00
2Record (As-built) Draw1JA$ 48,822.85$ 7,500.00$ 20,000.00
3Sheet Pile (incl Survey)7,632SF$ 80.00$ 610,560.00$ 75.50$ 576,216.00$ 200.00$ 1,526,400.00
4Concrete (incl Survey)180CY$ 1,226.75$ 220,815.00$ 1,100.00$ 198,000.00$ 400.00$ 720,000.00
5Sheet Pile Drive Line Clearing1JA$ 45,923.55$ 20,000.00$ 180,000.00
6Stone Related Survey
6.1Before Survey of Breakwater1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
6.2Final After Cap/Armor Stone1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
6.3Final After Underlayer Stone Slope Timber2,661EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
6.4Final After Armor Stone Placement2,661EA$ 2,661.40$ 2,664.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
7Exisiting Cap/Armor Removal Placment577TN$ 36.10$ 20,829.70$ 150.00$ 86,550.00$ 200.00$ 115,400.00
8Underlayer Stone Slope Timber153TN$ 81.80$ 12,515.40$ 110.00$ 16,830.00$ 250.00$ 38,250.00
9New Armor Stone821TN$ 111.70$ 91,705.70$ 120.00$ 98,250.00$ 700.00$ 574,700.00
10Bedding Stone for Voids in Timber Crib46TN$ 78.90$ 3,629.40$ 180.00$ 8,280.00250$ 11,500.00
Total Estimated Amount (Items 1-10)$ 1,442,195.00$ 1,115,896.00$ 3,476,250.00
Option "A" Sta 61+00 - Sta 61+75
11Record (As-built) Draw1JA$ 33,156.05$ 5,000.00$ 20,000.00
12Stone Related Survey
12.1Before Survey of Breakwater1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
12.2Final After Cap/Armor Stone1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
12.3Final after Bedding Stone on Lake Bottom1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
12.4Final after Underlayer Stone1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
12.5Final After Underlayer Stone Timbercrib1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
12.6Final After Armor Stone Placement1EA$ 2,661.40$ 2,661.40$ 13,500.00$ 13,500.00$ 10,000.00$ 10,000.00
13Exisiting Cap/Armor Removal Placment614TN$ 36.30$ 22,288.20$ 150.00$ 92,100.00$ 200.00$ 122,850.00
14Bedding Stone Placed on Bed Stone115TN$ 126.00$ 14,490.00$ 125.00$ 14,375.00$ 250.00$ 28,750.00
15Underlayer Stone on bed stone317TN$ 81.70$ 25,898.90110$ 34,870.00$ 250.00$ 79,250.00
16Underlayer Stone for Slope timber144TN$ 81.80$ 11,779.20$ 110.00$ 15,840.00$ 250.00$ 36,000.00
17New Armor Stone1,278TN$ 111.70$ 142,752.60$ 110.00$ 140,580.00$ 350.00$ 447,300.00
18Bedding Stone for Voids in Timber Crib46TN$ 75.90$ 3,491.40$ 180.00$ 8,280.00$ 350.00$ 187,500.00
Total Estimated Amount 11-18$ 269,824.75$ 383,765.00$ 810,250.00
Option "B"
19Additional Underlayer Stone300TN$ 81.80$ 25,540.00$ 110.00$ 33,000.00$ 250.00$ 75,000.00
Option "C"
20Additional Underlayer Stone200TN$ 81.50$ 16,300.00$ 110.00$ 22,000.00$ 250.00$ 50,000.00
Option :D"
21Additional Bedding Stone750TN$ 76.15$ 57,112.50$ 90.00$ 67,500.00$ 250.00$ 187,500.00
Option E
22Additional Bedding Stone250TN$ 76.15$ 19,037.50$ 90.00$ 22,500.00$ 250.00$ 62,500.00
Option F
23Bedding Stone for Tie in BRKWATR350TN$ 76.00$ 26,600.00$ 120.00$ 42,000.00$ 250.00$ 87,500.00
Option G
24Underlayer stone for Tie in to Existing BW500TN$ 81.70$ 40,850.00$ 110.00$ 55,000.00$ 250.00$ 125,000.00
Option H
25Armor Stone for Tie in to Exisiting BW680TN$ 111.80$ 76,024.00$ 110.00$ 74,800.00$ 350.00$ 238,000.00
Total Estimated Amount (Items 1~25)$ 1,972,480.75$ 1,816,461.00$ 5,112,000.00
*May contain rounding ErrorsApparent Low

Bidder 3 and 4

W912P4-20-B-0012response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
GLDMHuffman
FY 20 CLE BreakwaterA. HIRED LABORMuskegon, MIEastlake Ohio
Cleveland, OhioB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 376,744.80$ 334,470.00$ 455,760.00
2Record (As-built) Draw1JA$ 48,822.85$ 18,000.00$ 45,000.00
3Sheet Pile (incl Survey)7,632SF$ 80.00$ 610,560.00$ 63.00$ 480,816.00$ 79.85$ 609,415.20
4Concrete (incl Survey)180CY$ 1,226.75$ 220,815.00$ 1,044.00$ 187,920.00$ 1,400.00$ 252,000.00
5Sheet Pile Drive Line Clearing1JA$ 45,923.55$ 175,133.00$ 205,340.00
6Stone Related Survey
6.1Before Survey of Breakwater1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 15,000.00$ 15,000.00
6.2Final After Cap/Armor Stone1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
6.3Final After Underlayer Stone Slope Timber2,661EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
6.4Final After Armor Stone Placement2,661EA$ 2,661.40$ 2,664.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
7Exisiting Cap/Armor Removal Placment577TN$ 36.10$ 20,829.70$ 61.00$ 35,197.00$ 75.00$ 43,275.00
8Underlayer Stone Slope Timber153TN$ 81.80$ 12,515.40$ 90.00$ 13,770.00$ 83.00$ 12,699.00
9New Armor Stone821TN$ 111.70$ 91,705.70$ 113.00$ 92,773.00$ 113.00$ 92,773.00
10Bedding Stone for Voids in Timber Crib46TN$ 78.90$ 3,629.40$ 85.00$ 3,910.0065$ 2,990.00
Total Estimated Amount (Items 1-10)$ 1,442,195.00$ 1,367,589.00$ 1,749,252.20
Option "A" Sta 61+00 - Sta 61+75
11Record (As-built) Draw1JA$ 33,156.05$ 6,000.00$ 20,000.00
12Stone Related Survey
12.1Before Survey of Breakwater1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 10,000.00$ 10,000.00
12.2Final After Cap/Armor Stone1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
12.3Final after Bedding Stone on Lake Bottom1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
12.4Final after Underlayer Stone1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
12.5Final After Underlayer Stone Timbercrib1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
12.6Final After Armor Stone Placement1EA$ 2,661.40$ 2,661.40$ 6,400.00$ 6,400.00$ 5,000.00$ 5,000.00
13Exisiting Cap/Armor Removal Placment614TN$ 36.30$ 22,288.20$ 61.00$ 37,454.00$ 75.00$ 46,050.00
14Bedding Stone Placed on Bed Stone115TN$ 126.00$ 14,490.00$ 85.00$ 9,775.00$ 50.00$ 5,750.00
15Underlayer Stone on bed stone317TN$ 81.70$ 25,898.90$ 90.00$ 28,530.00$ 68.00$ 21,556.00
16Underlayer Stone for Slope timber144TN$ 81.80$ 11,779.20$ 90.00$ 12,960.00$ 68.00$ 9,792.00
17New Armor Stone1,278TN$ 111.70$ 142,752.60$ 113.00$ 144,414.00$ 80.00$ 102,240.00
18Bedding Stone for Voids in Timber Crib46TN$ 75.90$ 3,491.40$ 85.00$ 3,910.00$ 50.00$ 2,300.00
Total Estimated Amount 11-18$ 269,824.75$ 281,443.00$ 242,688.00
Option "B"
19Additional Underlayer Stone300TN$ 81.80$ 25,540.00$ 90.00$ 27,000.00$ 68.00$ 20,400.00
Option "C"
20Additional Underlayer Stone200TN$ 81.50$ 16,300.00$ 90.00$ 18,000.00$ 68.00$ 13,600.00
Option :D"
21Additional Bedding Stone750TN$ 76.15$ 57,112.50$ 85.00$ 63,750.00$ 50.00$ 37,500.00
Option E
22Additional Bedding Stone250TN$ 76.15$ 19,037.50$ 85.00$ 21,250.00$ 50.00$ 12,500.00
Option F
23Bedding Stone for Tie in BRKWATR350TN$ 76.00$ 26,600.00$ 85.00$ 29,750.00$ 50.00$ 17,500.00
Option G
24Underlayer stone for Tie in to Existing BW500TN$ 81.70$ 40,850.00$ 90.00$ 45,000.00$ 68.00$ 34,000.00
Option H
25Armor Stone for Tie in to Exisiting BW680TN$ 111.80$ 76,024.00$ 113.00$ 76,840.00$ 80.00$ 54,400.00
Total Estimated Amount (Items 1~25)$ 1,972,480.75$ 1,930,622.00$ 2,181,840.20