Clearwater Station Water Tank Replacement

Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
12970223Q0055
Agency
Forest Service Department of Agriculture
Responses due
Not on record
Set-aside
No set-aside

Opportunity facts

NAICS code
237110 Water and Sewer Line and Related Structures Construction
PSC
Y1NE Construction Of Water Supply Facilities
Place of performance
Clovis, California 93611, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This notice provides an opportunity to replace water tanks and infrastructure at the Clearwater Fire Station in California for the U.S. Department of Agriculture Forest Service. The contractor will demolish two existing 5,000 gallon tanks; install one new 31,000 gallon tank; connect it to distribution lines; install electrical controls and 350 linear feet of waterline; and a new hydrant, valve and box. The performance period is 45 days beginning no later than June 1, 2023. Proposals are due by May 22, 2023. The requirement will be awarded as a firm-fixed-price contract to a small business.

The requirement has been set aside for small businesses under NAICS code 237110 for Water System Storage Tank and Tower Construction with a size standard of $45 million. The estimated value is between $100,000 to $250,000. Interested vendors must be registered in the System for Award Management database and obtain the full solicitation on SAM.gov, including any amendments, by the response due date.

Notice text

Pre-Solicitation Synopsis

Clearwater Station Water Tank Replacement, Bass Lake Ranger District, Sierra National Forest

Description of Work

Furnish all labor, equipment and material to accomplish the Work under this contract.  Work includes but is not limited to the following major items:

  • Demolish and dispose of two water tanks and base (approximately 5,000 gallons each).
  • Furishing and installing new water tank 31,000 gallons.
  • Connecting water tank back to the distribution lines for the station.
  • Connecting electrical controls for the tank.
  • Disinfecting the entire water system.
  • Installing approximately 350 LF of 4” waterline for the new hydrant.
  • Installing a new tanker fir hydrant, control valve, and box.

Project Location

The project is located on the Bass Lake Ranger District of the Sierra National Forest.  From Fresno, proceed North approximately 20 miles on State Highway 41 to County Road 200. Proceed East on road 200 approximately 21 miles to the town of  North Fork. From North Fork continue East on County Road 225 approximately 5 miles to forest road 4S81 (Minarets Highway). Proceed North East on 4S81 approximately 10 miles to the Clearwater Fire Station, the project site.

Contract Time

The anticipated project performance period for this project is 45 days, including delays for weather, locating, transporting supplies and materials, and final project inspection and site cleanup.

Anticipated schedule for solicitation, award, and completion of projects is as follows:

RFQ Posted: May 15, 2023

RFQ Close: May 22, 2023

Project Start: No later than June 1, 2023

Magnitude

$100,000 to $250,000

This requirement is being solicited as a Total Small Business set-aside, under North American Industry Classification System (NAICS) code 237110 Water System Storage Tank and Tower Construction, with a Small Business Size Standard of $45M. The Forest Service intends to award one (1) Firm-Fixed-Price (FFP) contract resulting from this solicitation.

All interested vendors must be registered in the System for Award Management (SAM) database at SAM.gov | Entity Registrations before award of contract; failure to register in the SAM database may cause your firm to be ineligible for award and removed from consideration.

Interested vendors must obtain complete solicitation package on SAM.gov; copies will not be mailed from the Contracting Office. All amendments will be posted on SAM.gov and vendors will be solely responsible for viewing the solicitation posting in SAM.gov for amendments to the RFQ.

This notice does not obligate the Government to award a contract, nor does it obligate the Government to pay for any proposal preparation costs.

Attachments

Files attached to this notice, newest first
File Type Posted
SPECS_Clearwater Station Water Tank Replacement.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Clearwater Station Water Tank Replacement Award Award Notice
Clearwater Station Water Tank Replacement Latest solicitation Solicitation
Clearwater Station Water Tank Replacement Solicitation
Clearwater Station Water Tank Replacement This notice · Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity