CJAG Power Distribution
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9136426P0000040397
- Agency
-
Ohio National Guard
Army National Guard, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Place of performance
- Ravenna, Ohio 44266, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Ohio Army National Guard seeks construction of the CJAG Load Line 6 Electrical System, an underground medium-voltage electrical service installation, with quotations due September 21 and questions due September 14. This is a 100% small business set-aside with a small business size standard of $45 million.
Place of performance is Ravenna, Ohio at Camp James A. Garfield Joint Training Center. The scope includes approximately 1,400 linear feet of underground medium-voltage electrical service terminating at a new pad-mounted transformer in the Load Line 6 area, encompassing utility coordination, route surveying, underground utility location, trenching, conduit installation, concrete encasement, cable installation, transformer installation, grounding, testing, energization, restoration, quality control, and safety compliance. The system must deliver 750 kilowatts of steady-state power with surge capacity to 2,000 kV for peak loads. Performance commences 10 days after receipt of order and concludes by December 1, 2026, with work conducted Monday through Friday between 0730 and 1630 hours.
Contractor deliverables include civil and electrical stamped drawings and testing results, both due within 15 calendar days of project completion. Amendment 1 requires performance and payment bonds within 10 calendar days after order receipt. The NAICS code is 237130, Power and Communication Line and Related Structures Construction; PSC is Y1PZ, Construction of Other Non-Building Facilities. Evaluation criteria are technical acceptability, past performance relevance, and price reasonableness, with award to the responsible quoter offering best value without discussions. Quotations remain valid 60 days after the due date. Site visits are encouraged; contact 1SG Brian Persing at 330-984-8130 or CW2 Grant Stoner at 614-336-6580 for visit coordination only.
Notice text
2 versions
Update #2 · Latest ·
Amendment: 1
Bonding Requirements:
An offer guarantee IS required
Contractor must furnish any required performance and payment bonds within 10 calendar days after receipt of order (ARO)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary to construct the CJAG Load Line 6 Electrical System.
The requirement includes construction of approximately 1,400 linear feet of underground medium-voltage electrical service terminating at a new pad-mounted transformer at the Load Line 6 area of Camp James A. Garfield Joint Training Center.
The contractor shall perform all work in accordance with Attachment 1, including all requirements for utility coordination, route surveying, underground utility location, trenching, conduit installation, concrete encasement, backfill and compaction, cable installation, transformer installation, grounding, testing, energization, restoration, quality control, safety, security, and required deliverables.
Site Visits are encouraged, call 1SG Brian Persing 330-984-8130 or CW2 Grant Stoner 614-336-6580. Do not contact these individuals for any reason other than coordinating site visit.
Update #1 ·
The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary to construct the CJAG Load Line 6 Electrical System.
The requirement includes construction of approximately 1,400 linear feet of underground medium-voltage electrical service terminating at a new pad-mounted transformer at the Load Line 6 area of Camp James A. Garfield Joint Training Center.
The contractor shall perform all work in accordance with Attachment 1, including all requirements for utility coordination, route surveying, underground utility location, trenching, conduit installation, concrete encasement, backfill and compaction, cable installation, transformer installation, grounding, testing, energization, restoration, quality control, safety, security, and required deliverables.
Site Visits are encouraged, call 1SG Brian Persing 330-984-8130 or CW2 Grant Stoner 614-336-6580. Do not contact these individuals for any reason other than coordinating site visit.
Files
| File | Type | Posted |
|---|---|---|
| Combined Synopsis Solicitation_Power Distribution_Amendment1.docx | DOCX document | |
| PWS_Electrical Installation_V2.docx | DOCX document | |
| Combined Synopsis Solicitation_Power Distribution.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| CJAG Power Distribution | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| J061--541 Electrical Power Distribution Equipment Testing, Inspection, and Maintenance - VAMC Cleveland | Veterans Integrated Service Network 10 | Total Small Business | |
| Electricity 2027 | Reserve Command | No set-aside | |
| Repair Electrical Systems | AFLCMC Wright Patterson AFB | No set-aside | |
| Cable, power, electrical | Land and Maritime | Total Small Business | |
| Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT | ENDIST New England | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity