About this opportunity
This solicitation seeks rehabilitation and widening improvements for 6.54 miles of Donner Pass Road in California. The Department of Transportation Federal Highway Administration is procuring these roadway construction services. Significant work includes resurfacing existing pavement, widening shoulders to add bike lanes, improving drainage, installing guardrails and signs, and restriping. Bids are due in late winter/early spring 2020, with evaluation based on price. Construction must be completed between spring 2020 and fall 2021.
There is no set-aside designation. The project involves 7,500 cubic yards of roadway excavation, 195 cubic yards of rock excavation, 12,000 cubic yards of aggregate base, and 20,000 tons of asphalt pavement. The cost range is estimated between $10-14 million. Four contractors submitted bids for the work, with Herback General Engineering providing the lowest bid of $16.5 million. The place of performance is Donner Pass Road from I-80 Exit 174 in Soda Springs, California to the Truckee city limits.
Notice text
3 versions
Update #3 · Latest ·
THIS PROJECT WILL BE ADVERTISED ON A FULL AND OPEN BASIS.
The project is located just west of Truckee, California and will rehabilitate the existing pavement and widen shoulders for bike lanes on 6.54 miles of Donner Pass Road from I-80 Exit 174 in Soda Springs, CA to the Truckee City limits. Selected pullouts will also be paved and improvements include drainage, signing, striping, and guardrail. The proposed typical section is a 22 foot traveled way with 4 foot paved shoulders serving as Class II bike lanes. The bike lanes will be on the uphill direction only, east of Donner Pass. The bike lanes will be in both directions, west Donner Pass. Work will not be conducted on Rainbow Bridge. The elevation of Donner Pass is 7,056 feet.
COST RANGE: $10 TO $14M
Update #2 ·
THIS PROJECT WILL BE ADVERTISED ON A FULL AND OPEN BASIS.
PROJECT NUMBER: CA FLAP NEV 40(1)
PROJECT NAME: Donner Pass Road
PROJECT DESCRIPTION:
The project is located just west of Truckee, California and will rehabilitate the existing pavement and widen shoulders for bike lanes on 6.54 miles of Donner Pass Road from I-80 Exit 174 in Soda Springs, CA to the Truckee City limits. Selected pullouts will also be paved and improvements include drainage, signing, striping, and guardrail. The proposed typical section is a 22 foot traveled way with 4 foot paved shoulders serving as Class II bike lanes. The bike lanes will be on the uphill direction only, east of Donner Pass. The bike lanes will be in both directions, west Donner Pass. Work will not be conducted on Rainbow Bridge. The elevation of Donner Pass is 7,056 feet.
SIGNIFICANT QUANTITIES (Schedule A):
Roadway Excavation = 7,500 CY
Rock Excavation = 195 CY
Aggregate Base = 12,000 CY
Asphalt Pavement = 20,000 TONS
Guardrail = 6,000 LF
Erosion Control = LPSM
Traffic Control = LPSM
COST RANGE: Schedule A: $10M to $14M
CONSTRUCTION DURATION: Spring 2020 to Fall 2021
ADDITIONAL INFORMATION:
Anticipated advertisement in late winter 2019
Anticipated bid opening in late winter to early spring 2020
Anticipated Award in late winter to early spring 2020
Anticipated Notice to Proceed in spring 2020
Due to weather restrictions, on-site construction typically cannot occur until after May. Night work with full closures may be permitted east of Donner Pass. 1-lane closures, with maximum 10 minute delays, will be permitted throughout the project.
Update #1 ·
THIS PROJECT WILL BE ADVERTISED ON A FULL AND OPEN BASIS.
THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
PROJECT NUMBER: CA FLAP NEV 40(1)
PROJECT NAME: Donner Pass Road
PROJECT DESCRIPTION:
The project is located just west of Truckee, California and will rehabilitate the existing pavement and widen shoulders for bike lanes on 6.54 miles of Donner Pass Road from I-80 Exit 174 in Soda Springs, CA to the Truckee City limits. Selected pullouts will also be paved and improvements include drainage, signing, striping, and guardrail. The proposed typical section is a 22 foot traveled way with 4 foot paved shoulders serving as Class II bike lanes. The bike lanes will be on the uphill direction only, east of Donner Pass. The bike lanes will be in both directions, west Donner Pass. Work will not be conducted on Rainbow Bridge. The elevation of Donner Pass is 7,056 feet.
SIGNIFICANT QUANTITIES (Schedule A):
Roadway Excavation = 7,500 CY
Rock Excavation = 195 CY
Aggregate Base = 12,000 CY
Asphalt Pavement = 20,000 TONS
Guardrail = 6,000 LF
Erosion Control = LPSM
Traffic Control = LPSM
COST RANGE: Schedule A: $10M to $14M
CONSTRUCTION DURATION: Spring 2020 to Fall 2021
ADDITIONAL INFORMATION:
Anticipated advertisement in late winter 2019
Anticipated bid opening in late winter to early spring 2020
Anticipated Award in late winter to early spring 2020
Anticipated Notice to Proceed in spring 2020
Due to weather restrictions, on-site construction typically cannot occur until after May. Night work with full closures may be permitted east of Donner Pass. 1-lane closures, with maximum 10 minute delays, will be permitted throughout the project.
Files
| File | Type | Posted |
|---|---|---|
| Bid Tabs.pdf | ||
| Bid Opening Summary Donner Pass.pdf | ||
| A009.pdf | ||
| A008.pdf | ||
| A007.pdf | ||
| A006.pdf | ||
| A005.pdf | ||
| A004.pdf | ||
| QnA_11.1.2019.pdf | ||
| A003.pdf | ||
| QnA_10.30.2019.pdf | ||
| A002.pdf | ||
| QnA_10.28.2019.pdf | ||
| A001.pdf | ||
| QnA_10.17.2019.pdf | ||
| QnA_10.9.2019.pdf | ||
| QnA_10.3.2019.pdf | ||
| Pavements_Report.pdf | ||
| Geotech_Report.pdf | ||
| Donner_Pass_Road_X-Z_Sheets_Stamped.pdf | ||
| Hydraulics_Report.pdf | ||
| Donner_Pass_Plans.pdf | ||
| 6982AF19B000002.pdf |
Show all 23
Notice history
| Notice | Type | Posted |
|---|---|---|
| CA FLAP NEV 40(1) Donner Pass Road | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| ND NP THRO 204(1) Buck Hill Road | Federal Highway Administration | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity