This document contains questions and answers regarding a federal transportation contract opportunity to rehabilitate 6.54 miles of Donner Pass Road in California. The project involves full depth reclamation of the existing pavement, widening shoulders to add 4-foot bike lanes, improving drainage, signing, striping, guardrails and paving select pullouts. Significant work includes 7,500 cubic yards of roadway excavation, 195 cubic yards of rock excavation, 12,000 cubic yards of aggregate base and 20,000 tons of asphalt pavement. The contract also includes 6,000 linear feet of guardrail, linear payment items for erosion control and traffic control, and has a cost range of $10-14 million. Construction is scheduled from Spring 2020 to Fall 2021, with advertisement in late winter 2019, anticipated bid opening in late winter/early spring 2020 and award in late winter/early spring 2020.

View the file

Other files

File Type Posted
Bid Tabs.pdf PDF
Bid Opening Summary Donner Pass.pdf PDF
A009.pdf PDF
A008.pdf PDF
A007.pdf PDF
A006.pdf PDF
A005.pdf PDF
A004.pdf PDF
QnA_11.1.2019.pdf PDF
A003.pdf PDF
QnA_10.30.2019.pdf PDF
A002.pdf PDF
A001.pdf PDF
QnA_10.17.2019.pdf PDF
QnA_10.9.2019.pdf PDF
QnA_10.3.2019.pdf PDF
Hydraulics_Report.pdf PDF
Donner_Pass_Plans.pdf PDF
6982AF19B000002.pdf PDF
Pavements_Report.pdf PDF
Geotech_Report.pdf PDF
Donner_Pass_Road_X-Z_Sheets_Stamped.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CA FLAP NEV 40(1) Donner Pass Road

October 1, 2019

Questions Answers

1 Requesting clarification for bid item A2120 63402-2300

PAVEMENT MARKINGS, TYPE L, SOLID:

What is the required formulation for Type L Markings for the above referenced project (4:1) or (98:2)? Caltrans always requires

4:1 within this region as this is the most common equipment available for this region.

Use a 4:1 formulation.

2 For the blue this would have to be a 98:2 material as blue is not manufactured as a 4:1. Will Type D epoxy Paint or Preformed

Thermoplastic be acceptable for the 400 LF of Blue 4” Lines?

Yes, either would be acceptable. However, Paint is preferred to remain consistent with other longitudinal markings.

3 What is the required mill thickness for the Type L Pavement markings 60Mils, 90Mils, ETC

Install the pavement markings at 90Mils

4 Are the Type L Line being recessed and if So what is the required depth of the recess?

Recess depth should be a minimum of .11 inches.

October 9, 2019

5 Does the MMA on this project get recessed? Yes

October 10, 2019

6 Bid Item 62510-2000 Seeding, Hydraulic Method is for 8.3 Acres.

Can you provide the acres for both the upland and wetland seed mixes?

Bid Item 62515-2000 Mulching, Hydraulic Method if for 8.3

Acres.

Upland Seed = 8.25 Ac, Wetland seed = 0.05 ac.

7 Section 625: Material rates for hydraulic method fertilizer, seed and mulching are not included in the specifications. Can you please provide?

Fertilizer is not required for this project.

Material rates for hydraulic method seeding is shown in 625.07 of FP-14

Material rates for hydraulic method mulching is shown in 625.08 of FP-14

8 Section 713: Roadside Improvement Material - Materials for fertilizer, mulch and tackifier are not included in the specifications. Can you please provide?

Fertilizer is not required for this project.

Materials for mulch are included in 713.05 of FP-14

Materials for tackifier are included in 713.11 of FP-14

9 Will the use of an excavator with breaker attachment be allowed for the sliver rock cuts?

If so, with the excavated material be paid for as Item A0620, Rock

Excavation?

The use of a hoe-ram or breaker is specifically excluded by the specifications for sliver cuts. The work is controlled rock excavation as described in the specifications in detail.

October 17, 2019

10 Regarding bid item A0800, 25501-1000, will Federal Highway allow an alternative, previously-used, welded wire-faced MSE system, with 24” lifts and inextensible steel soil reinforcements instead of geogrid?

No, bid item A0800, 25501-1000 as specified. After award of the project

CFLHD may consider a value engineering approach for alternative systems.

11 I am inquiring about the Donner Pass Rd. project

#6982AF19B000002 with Class 1 Type F fabric on page G30 of the drawings on the backfill side of the wire face wall . There is no such type and I would like to clarify what fabric is being used in this section ?

It should be Class 1, Type E. An upcoming amendment will correct this on the plan set.

October 28, 2019

12 The specs and plans for the Donner Pass project state there is wet and dry land area. Could you point me in the direction as to where to find the specs for the size of each area? I just see 8.3 acres total.

Upand Seed = 8.25 Ac, Wetland seed = 0.05 ac.

13 For the various pullout areas that include note 5 “Delineate edge of pull out limits with excavated boulders from the current pull out site, or the other proposed pull out areas”, will placement of boulders be paid for with labor and equipment hours or will just the removal and excavation be paid for (per note 7)?

a. If placement is incidental, what is the typical spacing required between boulders?

Boulder placement is incidental to boulder removal and boulder excavation

(i.e. equipment hours). The objectives of delineating the edge of the pullouts is to reuse onsite material and prevent vehicles from encroaching past designated pullouts, thus boulder placement should be determined during construction based on available material. Six foot spacing would be ideal but it depends on available material.

15 SCR 304.03 General, first paragraph, second sentence states

“Before pulverizing, rip the existing pavement and subgrade to identify areas of hard rock and flush out boulders or roots”. Is it the Government’s intent that the Contractor mechanically rip the entire length of the roadway (STA 304+50 to 442+50) to receive full depth reclamation in order to identify potentially shallow bedrock and/or hard boulders that may be within the subgrade section?

Ripping is specified for these areas. The intent of the ripping is to allow the Contractor to do investigative work to identify areas of hard rock that could damage the pulverizing equipment if hard rock was encountered unexpectantly and flush out boulders, or if the pulverizer cannot get beneath the asphalt pavement due to encountering rock. The key areas of concern are where bedrock is exposed in the roadside cuts and ditches along the uphill side of the road. Rockfill is present below the existing pavement. Generally, there is a potential to encounter localized boulders composed of hard rock during pulverization. The Contractor is directed to the boring logs and discussion presented in the Pavement Design and

Geotechnical Report for information regarding cobble- to boulder-sized encountered within the subgrade.

16 Detail A, Plan Sheet A7 states “FDR material or millings will not be accepted as shouldering material”. In addition, SCR 203.04

Removing Material, second paragraph, last sentence states

“Asphalt millings and FDR material shall not be used as shouldering material”.

Asphalt millings and FDR material shall not be used to shoulder up along the roadway (see detail A on sheet A7), however FDR material can be used

(if excess material is available) for the pullouts shown in the D sheets.

17 Details on the pull out sheets (D2 through D7) indicate to “Place

6” of FDR material or aggregate base.” Please clarify if FDR material is acceptable for use in the pull out areas.

FDR material can be used (if excess material is available) for the pullouts shown in the D sheets.

18 How will SCR 204.06 (d) Sinhole Patching be paid for?

Sinkhole patching shall be paid for with Soil Erosion Control Rock Mulch and Geotextile Filter Class 2 Type E. See sheet F2 and remarks in the

Summary of Quantities for additional information.