Bldg. 175 Replace Fuel Underground Storage Tank, NAS Lemoore, CA
Awarded Award Notice Posted
- Solicitation number
- N62473-25-R-J514
- Agency
- Naval Facilities Engineering Command Department of the Navy, Department of Defense
- Awarded
- to WU & Associates Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- N62473-20-D-1103-N62473-26-F-0039 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Lemoore, California 93246, United States
- Points of contact
-
- Antonio B. Harley antonio.b.harley1@navy.mil (559) 998-2086
- Nathalie Zielinski nathalie.m.zielinski.civ@us.navy.mil (559) 998-3892
Notice details come from SAM.gov. Updated .
About this opportunity
This Award Notice, issued by the Department of the Navy Naval Facilities Engineering Command on February 3, 2026, concerns the replacement of an underground jet fuel storage tank at Building 175 of Naval Air Station Lemoore, California. The awarded contract involves comprehensive construction and demolition work to replace the existing underground tank with a new 20,000-gallon double-wall, above-ground jet fuel storage tank, along with associated infrastructure including concrete pads, containment curbs, fuel pumps, electrical systems, stainless steel piping, bollards, lighting, a fire hydrant, and safety equipment such as an eyewash station. The contract was awarded on December 9, 2025, and encompasses all requisite equipment testing and verifications to ensure proper installation and functionality of the new storage system. While the Award Notice does not specify the contract value, the scope of work indicates a substantial construction project involving site preparation, tank installation, utility relocation, and safety infrastructure upgrades.
Notice text
The intent of this project is to replace the underground jet fuel storage
tank at the B-175 Jet Engine Test Cell with a new, double-wall,
aboveground storage tank. Specific methods shall be as described below.
Work Requirements:
a. Construction:
1. Install new concrete pad, tank footings, and containment curb in
accordance with the drawing requirements including piping and conduit
penetrations.
2. Install a new 20,000 gallon factory fabricated, double wall, protected,
above-ground jet fuel storage tank including platform and stairway as
indicated on the drawing.
3. Install new concrete fuel pipe trench with traffic rated grating as
indicated on the drawing.
4. Install new electrical pull boxes, concrete ductbank, and conduits as indicated on the drawing.
5. Install new two new fuel pumps in accordance with the pump schedule.
6. Relocate indicated devices and piping including new cathodic protection
for underground piping.
7. Relocate existing emergency stop panel as indicated and add a new
readout for the automatic tank gauge system.
8. Install new stainless steel piping and valves as indicated to
re-establish all connections with the new above-ground tank.
9. Install bollards all the way around the new tank and pad area as
indicated on the drawing.
10. Install new light post where indicated on the drawing, including switch
near the stairwell.
11. Install new fire hydrant where indicated on the drawing.
12. Install a new eyewash station as indicated.
13. Perform all requisite equipment testing and verifications in
accordance with specification requirements.
b. Demolition:
1. Demolish and remove all concrete as indicated above the underground
tank to provide access for excavation of the tank.
2. Remove existing devices and piping to be relocated as indicated on the
drawing.
3. Remove existing emergency stop panel and associated conduit to be
relocated as indicated on the drawing.
4. Remove existing cathodic protection test wells and associated cabling
and anodes where indicated.
5. Remove existing fiberglass transition sump and concrete collar as
indicated.
6. Remove the existing fuel pumps, associated devices, and electrical
boxes and conduits as indicated.
7. Excavate and completely remove the 20,000 gallon underground jet fuel
storage tank. This tank removal must be completed (out of the ground) by
December 31st 2025. Liquidated damages may be assessed as detailed in
Section 1.7 for this activity.
8. Remove the concrete base beneath the existing underground tank.
9. Perform all requisite clean-up and testing associated with the removal
in accordance with all of the federal, state, and local environmental
requirements.
10. Remove existing fire hydrant and associated piping as indicated.
10. Remove existing valve, valve box, pedestal type hose bib, and
associated piping as indicated.
11. Remove existing bollards where indicated.
12. Remove existing concrete ductbank and conduits back to the building as
indicated.
13. Remove existing double wall fuel supply and return pipes back to the
building as indicated.
Awarded contract N62473-20-D-1103 to WU & ASSOCIATES INC for 2640000.00 on 2025-12-09.
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity