Big Bend Left Abutment Collector Pipe System

Closed Special Notice Posted

Solicitation number
W9128F23B0005
Agency
ENDIST Omaha US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y1QA Construction Of Restoration Of Real Property (Public Or Private)
Place of performance
Fort Thompson, South Dakota 57339, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This Special Notice from the Department of the Army Corps of Engineers Engineering District Omaha concerns a two-step sealed bid solicitation for replacement of the Big Bend Left Abutment Collector Pipe System in South Dakota. In the first step, technical submissions from three contractors - ESI, Fenton Construction Inc., and Montcal LLC - were deemed acceptable to proceed to the next step.

The Special Notice provides updates to the solicitation opportunity. It announces the posting of an abstract for step two sealed bids and lists the three contractors determined technically qualified in step one. The key deadlines and requirements outlined are that sealed price bids are due on March 28, 2023 from the three prequalified offerors. Eligible contractors must have been evaluated as technically acceptable in step one. The objective of the solicitation is to award a contract for replacement of the existing collector pipe system at the Big Bend Left Abutment through a two-step sealed bid process.

Notice text

5 versions

Update #5 · Latest ·

***Bid Abstract Posted in Attachments***

**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**

Results of Step 1 - Technical Evaluation of the Two Step IFB process

The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.

 ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109

 Fenton Construction Inc.  PO Box 2669, Sioux City, Iowa 51106

 Montcal LLC.  PO Box 1119, Plains, Montana 59859                                                                 

                                                                - Bids will be due on 16 March 2023  -

***NOTE*** AM0004 Step-2 IFB is posted with supporting documents.  ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments. 

***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

***NOTE*** AM0006 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

                                                               - Bides are due on 28 March 2023 by 2:00 PM CT

Update #4 ·

**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**

Results of Step 1 - Technical Evaluation of the Two Step IFB process

The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.

 ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109

 Fenton Construction Inc.  PO Box 2669, Sioux City, Iowa 51106

 Montcal LLC.  PO Box 1119, Plains, Montana 59859                                                                 

                                                                - Bids will be due on 16 March 2023  -

***NOTE*** AM0004 Step-2 IFB is posted with supporting documents.  ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments. 

***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

***NOTE*** AM0006 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

                                                               - Bides are due on 28 March 2023 by 2:00 PM CT

Update #3 ·

**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**

Results of Step 1 - Technical Evaluation of the Two Step IFB process

The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.

 ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109

 Fenton Construction Inc.  PO Box 2669, Sioux City, Iowa 51106

 Montcal LLC.  PO Box 1119, Plains, Montana 59859                                                                 

                                                                - Bids will be due on 16 March 2023  -

***NOTE*** AM0004 Step-2 IFB is posted with supporting documents.  ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments. 

***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

                                                               - Bides are due on 23 March 2023 by 2:00 PM CT

Update #2 ·

**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**

Results of Step 1 - Technical Evaluation of the Two Step IFB process

The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.

 ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109

 Fenton Construction Inc.  PO Box 2669, Sioux City, Iowa 51106

 Montcal LLC.  PO Box 1119, Plains, Montana 59859                                                                 

                                                                - Bids will be due on 16 March 2023  -

***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors.  Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.  

                                                               - Bides are due on 23 March 2023 by 2:00 PM CT

Update #1 ·

**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**

Results of Step 1 - Technical Evaluation of the Two Step IFB process

The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.

 ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109

 Fenton Construction Inc.  PO Box 2669, Sioux City, Iowa 51106

 Montcal LLC.  PO Box 1119, Plains, Montana 59859                                                                 

                                                                - Bids will be due on 16 March 2023  -

Attachments

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Big Bend Left Abutment Collector Pipe System This notice · Latest special notice Special Notice
Big Bend Left Abutment Collector Pipe System Solicitation
Big Bend Left Abutment Collector Pipe System Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity