About this opportunity
This Special Notice from the Department of the Army Corps of Engineers Engineering District Omaha concerns a two-step sealed bid solicitation for replacement of the Big Bend Left Abutment Collector Pipe System in South Dakota. In the first step, technical submissions from three contractors - ESI, Fenton Construction Inc., and Montcal LLC - were deemed acceptable to proceed to the next step.
The Special Notice provides updates to the solicitation opportunity. It announces the posting of an abstract for step two sealed bids and lists the three contractors determined technically qualified in step one. The key deadlines and requirements outlined are that sealed price bids are due on March 28, 2023 from the three prequalified offerors. Eligible contractors must have been evaluated as technically acceptable in step one. The objective of the solicitation is to award a contract for replacement of the existing collector pipe system at the Big Bend Left Abutment through a two-step sealed bid process.
Notice text
5 versions
Update #5 · Latest ·
***Bid Abstract Posted in Attachments***
**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**
Results of Step 1 - Technical Evaluation of the Two Step IFB process
The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.
ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109
Fenton Construction Inc. PO Box 2669, Sioux City, Iowa 51106
Montcal LLC. PO Box 1119, Plains, Montana 59859
- Bids will be due on 16 March 2023 -
***NOTE*** AM0004 Step-2 IFB is posted with supporting documents. ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments.
***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
***NOTE*** AM0006 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
- Bides are due on 28 March 2023 by 2:00 PM CT
Update #4 ·
**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**
Results of Step 1 - Technical Evaluation of the Two Step IFB process
The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.
ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109
Fenton Construction Inc. PO Box 2669, Sioux City, Iowa 51106
Montcal LLC. PO Box 1119, Plains, Montana 59859
- Bids will be due on 16 March 2023 -
***NOTE*** AM0004 Step-2 IFB is posted with supporting documents. ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments.
***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
***NOTE*** AM0006 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
- Bides are due on 28 March 2023 by 2:00 PM CT
Update #3 ·
**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**
Results of Step 1 - Technical Evaluation of the Two Step IFB process
The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.
ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109
Fenton Construction Inc. PO Box 2669, Sioux City, Iowa 51106
Montcal LLC. PO Box 1119, Plains, Montana 59859
- Bids will be due on 16 March 2023 -
***NOTE*** AM0004 Step-2 IFB is posted with supporting documents. ONLY the companies listed above are to provide the final Bids with acknowledgement of all amendments.
***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
- Bides are due on 23 March 2023 by 2:00 PM CT
Update #2 ·
**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**
Results of Step 1 - Technical Evaluation of the Two Step IFB process
The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.
ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109
Fenton Construction Inc. PO Box 2669, Sioux City, Iowa 51106
Montcal LLC. PO Box 1119, Plains, Montana 59859
- Bids will be due on 16 March 2023 -
***NOTE*** AM0005 Time extension has been posted for the above IFB Step-2 contractors. Only the three contractors listed above are to proved the final Step-2 IFB Bids and acknowledgement of all Amendments.
- Bides are due on 23 March 2023 by 2:00 PM CT
Update #1 ·
**UPDATE 1 March 2023 - Abstract for Step-Two Sealed Bids Posted**
Results of Step 1 - Technical Evaluation of the Two Step IFB process
The following firms submissions have been identified as being technically acceptable and shall proceed to Step 2 of the Two Step IFB process.
ESI (Elite Surface Infrastructure) 1199 Atchison Court, Castle Rock, Colorado 80109
Fenton Construction Inc. PO Box 2669, Sioux City, Iowa 51106
Montcal LLC. PO Box 1119, Plains, Montana 59859
- Bids will be due on 16 March 2023 -
Attachments
| File | Type | Posted |
|---|---|---|
| IFB Bid Abstract_Signed.pdf | ||
| BB Left Abutment AM0006 - Time Extension.pdf | ||
| W9128F23B0005_1 of 4 BB Left Abutment Step-2 Bid AM0004.pdf | ||
| W9128F23B0005_2 of 4 Contract Specs.pdf | ||
| W9128F23B0005_3 of 4 BB90_Plans_Step_2_Final_Set_02-27-23.pdf | ||
| W9128F23B0005_4 of 4 BB90 Geotechnical Data Report STEP 2.pdf | ||
| BB Left Abutment AM0005 - Time Extension.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Big Bend Left Abutment Collector Pipe System | Special Notice | |
| Big Bend Left Abutment Collector Pipe System | Solicitation | |
| Big Bend Left Abutment Collector Pipe System | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity