B18 Chiller Repair
Closed Solicitation Posted
- Solicitation number
- FA706024RMS01
- Agency
- District Washington Headquarters Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 811310 Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance
- PSC
- J041 Maint/Repair/Rebuild Of Equipment- Refrigeration, Air Conditioning, And Air Circulating Equipment
- Place of performance
- Bolling AFB, District of Columbia 20032, United States
- Points of contact
-
- Christian Barnett christian.barnett.1@us.af.mil (202) 854-9133
- Melvin Spann melvin.spann@us.af.mil (202) 284-3335
Notice details come from SAM.gov. Updated .
About this opportunity
Paragraph 1:
The Department of the Air Force Headquarters District Washington is seeking a contractor to repair the B18 chiller at Joint Base Anacostia-Bolling in Washington, DC. The scope of work includes repairing leaks, purging the system, evacuating and recharging the refrigerant, reinsulating areas, and inspecting/calibrating the safety controls. The contractor will also provide condenser tube cleaning. The contract will be awarded based on the contractor's ability to meet the technical requirements and provide the best value to the government. Offers are due by 4:00 PM EST on September 25, 2024 and must remain valid for at least 60 days.
Paragraph 2:
This is a 100% small business set-aside contract under NAICS code 811310 with a size standard of $12,500,000. The contract is for a single CLIN with a period of performance of 60 days. The contractor will be required to provide a 12-month warranty on any replaced parts. The place of performance is Bolling Air Force Base Heliport in Washington, DC 20032.
Notice text
The Contractor shall repair the leaks previously found on Chiller 1. Purge connection, solenoid valves, and evaporator charging valves. Evacuate the system refrigerant and recharge the Chiller with recovered refrigerant. Trim the charge with 300 pounds of new R123 refrigerant. Finally, reinsulate all areas that were removed due to leak check.
The Contractor shall conduct electronic leak test as required and report minor leaks. Tighten all exposed flanges and seal all bolts. Inspect purge system and inspect and calibrate safety controls. Change oil & purge filters. Report any uncorrected deficiencies noted. Condenser tube cleaning provided machine is flanged so that heads can be readily removed, and valves are in good operating condition.
The Contractor will clean up any debris, dust, or other materials that may have been generated during the duct cleaning process. They will also dispose of any waste materials adequately, ensuring that the workspace remains clean and debris-free after cleaning.
Attachments
| File | Type | Posted |
|---|---|---|
| B18 Chiller Repair_PWS_final.docx | DOCX document | |
| Combined Synopsis Solicitation_B18 Chiller Repair signed.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity