AZ FTNP GRCA 11(4), Desert View Drive

Award Notice Posted

Solicitation number
DTFH6817B00017
Agency
Awarded
to Fann Contracting, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
6982AF18C000007 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Grand Canyon National Park, Arizona, United States

Notice details come from SAM.gov. Updated .

Notice text

AZ FTNP GRCA 11(4) Desert View Drive Synopsis:

Location: Grand Canyon National Park South Rim
County: Coconino, Arizona


Set-aside: Full and open


PROJECT DETAILS: This project in includes reconstruction of 7.47 miles of Desert View Drive, 1.1 miles of Yaki Point and Kaibab Trail Access Road, 3.59 South Entrance Road, 1.17 Village Loop Drive in Grand Canyon National Park.


Type of Construction: subgrade grading, concrete paving, concrete curb, CMP culverts, concrete headwalls, and riprap, aggregate base course, asphalt pulverizing and paving, traffic control, public information.


This project consists of:


Schedule A: Phased Construction of 7.47 miles of Desert View Drive roadway reconstruction and paving.


Significant Items for Schedule A include: 3,100 LF of fiber rolls; 2,000 CY of roadway excavation; 300 sub excavation; 300 CY of riprap; 3,200 tons of aggregate base; 28,500 tons of hot asphalt paving; 200 LF of pipe culvert placement; 600 LF of concrete curb; 70 miles of pavement markings; 2,600 flagger hours


Option W: Phased Construction of 1.00 miles of Rowe Well Road roadway reconstruction and paving.


Significant Items for Option W include: 3,070 tons of asphalt concrete pavement, 750 CUYD of subexcavation, 910 tons of roadway aggregate, 14,500 SQYD of full depth reclamation and 400 flagger hours.


Option X: Phased Construction of .5 miles of roadway reconstruction and paving.


Significant Items for Option X include: 2,900 LF of fiber rolls; 5,000 CY of roadway excavation; 300 CY sub-excavation waste; 50 CY of riprap; 3,400 tons of aggregate base; 10,645 SY minor concrete pavement; 200 LF of pipe culvert placement; 5 miles of pavement markings; 5,000 flagger hours.


Option Y: Phased Construction of 3.52 miles of South Entrance Drive reconstruction and paving.


Significant Items for Option Y include: 600 LF of fiber rolls; 3,000 CY of roadway excavation; 200 CY sub-excavation; 50 CY of riprap; 2,000 tons of aggregate base; 16,390 tons of hot asphalt paving; 30 LF of pipe culvert placement; 8 miles of pavement markings; 3,200 flagger hours.


Option Z: Phased Construction of 1.15 miles of Village Loop Drive and Bypass reconstruction and paving.


Significant Items for Option Y include: 900 LF of fiber rolls; 400 CY of roadway embankment; 200 CY sub-excavation; 60 CY of riprap; 2,500 tons of aggregate base; 6,000 tons of hot asphalt paving; 30 LF of pipe culvert placement; 2 miles of pavement markings; 3,200 flagger hours.


 

Files

File Type Posted
Bid_Tabs.pdf PDF
AZ_FTNP_GRCA_11(4)_Bid_Opening_Summary.pdf PDF
QnA_11.21.17.pdf PDF
QnA_11.14.17.pdf PDF
AZ_FTNP_GRCA_11(4)_Desert_View_Drive_Pavement_Report.pdf PDF
DTFH6817B00017.pdf PDF
AZ_GRCA_11(4)_Final_Plans.pdf PDF