Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912HN21B5003
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Savannah, Georgia 31401, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation is for maintenance dredging services along the Atlantic Intracoastal Waterway in Georgia and South Carolina. The U.S. Army Corps of Engineers Savannah District seeks a contractor to dredge two sites totaling approximately 3.6 miles using a hydraulic cutterhead dredge to a depth of -12 feet MLLW with a 2 foot overdepth allowance. Dredged material will be placed at designated disposal sites, with some used to create 13.2 acres of temporary bird habitat. A virtual pre-bid conference will be held on July 8, 2021 and sealed bids must be submitted by August 6, 2021, with evaluation based on price.

This requirement has a 100% small business set-aside designation with a projected award value between $1-5 million. The primary NAICS code is 237990 and PSC code is D301. The maintenance dredging is to be completed within 180 days of notice to proceed in the Savannah, Georgia area. Approximately 376,000 cubic yards of material will be dredged from Elba Cut and placed in an existing disposal area, with additional material from Altamaha Sound used to create the bird habitat island and any remainder deposited at an unconfined site.

Notice text

6 versions

Update #6 · Latest ·

***************************************************************

Bid Abstract and Bid Opening Attendee List are now posted.

****************************************************************

ProjNET questions and answers are now posted.  

****************************************************************

Amendment 0002 has been posted and includes specification changes.  Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

Amendment 0001 has been posted and includes solicitation and specification changes. Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

A Pre-Bid Conference was held 8 July 2021, the attendee list is now posted in attachments. 

*****************************************************************

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Update #5 ·

****************************************************************

ProjNET questions and answers are now posted.  

****************************************************************

Amendment 0002 has been posted and includes specification changes.  Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

Amendment 0001 has been posted and includes solicitation and specification changes. Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

A Pre-Bid Conference was held 8 July 2021, the attendee list is now posted in attachments. 

*****************************************************************

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Update #4 ·

****************************************************************

Amendment 0002 has been posted and includes specification changes.  Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

Amendment 0001 has been posted and includes solicitation and specification changes. Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

A Pre-Bid Conference was held 8 July 2021, the attendee list is now posted in attachments. 

*****************************************************************

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Update #3 ·

*****************************************************************

Amendment 0001 has been posted and includes solicitation and specification changes. Please use the most recent conformed solicitation for preparation of your bid.

*****************************************************************

A Pre-Bid Conference was held 8 July 2021, the attendee list is now posted in attachments. 

*****************************************************************

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Update #2 ·

*****************************************************************

A Pre-Bid Conference was held 8 July 2021, the attendee list is now posted in attachments. 

*****************************************************************

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Update #1 ·

This solicitation is for the Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging.  This acquisition is being offered as a 100% small business set-aside competitive solicitation and will result in a Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1M and $5M.

Project Location: The work is located within the Savannah District’s portion of the AIWW shallow draft waterway in the states of Georgia and South Carolina.  The AIWW in Savannah District begins in Port Royal Sound, South Carolina (Mile 552) and ends in Cumberland Sound, Georgia (Mile 713).  The AIWW project depth is -12.0’ Mean Lower Low Water (MLLW) to include -2.0’ of allowable pay overdepth (-14.0’ MLLW). The widths vary from 90 feet in land cuts to 150 feet in natural waterways

Project Description: The Atlantic Intracoastal Waterway (AIWW) Altamaha Sound Beneficial Use of Dredged Material project and Selective Sites Maintenance Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging and the pilot project.  This requirement has been traditionally performed with a hydraulic cutterhead dredge and the estimated construction duration is 180 calendar days after issuance of the Notice to Proceed.

Maintenance dredging will be performed in two selected sites on the AIWW; Altamaha Sound and Elba Cut.  The maintenance material from Elba Cut (mile 576 to mile 576.4) will be placed in Disposal Area (DA) 14B which is across the Savannah River from the dredging site.

The maintenance material in Altamaha Sound (mile 656.4 to mile 660) will be placed in an open water site to create a temporary 13.2 acre bird nesting site to assist Georgia Department of Natural Resources with available migratory shorebird habitat lost due to the last two hurricanes along the coast within the State.  Any shoaled material not being use for the bird island will be placed on Tract 36A which is an unconfined placement site on an island (Hammock) in the Altamaha River. 

Evaluation Criteria: The contract will be solicited and procured using Sealed Bidding Procedures under FAR Part 14.

Pre-Bid Conference:

Location: A Virtual Pre-Bid Conference will be held for this project.

Date/Time: Thursday, July 8, 2021 at 10:00 a.m. Eastern Daylight Time.

Special Instructions. See attached IFB for instructions on attendance. 

NOTE: Bid opening date is specified in the attached IFB. No additional media (CD-ROM, floppy disks, faxes, etc.) are provided. Any prospective Offeror must register in the System for Award Management (SAM) at https://sam.gov. After completing SAM registration, interested Contractors and their subcontractors can obtain solicitation documents, plans and specifications for this solicitation within the same site under Contract Opportunities. Contractors that have an existing account should be able to use their existing logins to search for the solicitation number.  It is the Offeror’s responsibility to check the Internet address provided as necessary for any amendments that may be posted to this solicitation. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.

Contractual Questions should be forwarded to Contract Specialist, David Jimenez at David.A.Jimenez@usace.army.mil or to the attention of Contracting Officer, Whittni Hiscox at Whittni.C.Hiscox@usace.army.mil.

Files

Show all 13

Notice history

Notice Type Posted
Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging Award Award Notice
This notice Latest solicitation Solicitation
Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging Pre-Solicitation
Atlantic Intracoastal Waterway (AIWW) Maintenance Dredging Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Sources Sought for FY26 Atlantic Intracoastal Waterway Maintenance Dredging ��������� Select Sites NAICS 237990 ENDIST Savannah No set-aside
Maintenance Dredging of the Isle au Haut Thoroughfare near Isle au Haut, Maine NAICS 237990 ENDIST New England Total Small Business
W912EE27BA002 - Lease of One Cutterhead, Hydraulic Pipeline Dredge (Not Less Than 24-Inch Diameter) Fully Operated with Attendant Plant and Personnel, and with a Draft not to Exceed 9 Feet, for Construction and Maintenance Dredging - JBJ Waterway Vicksburg, Mississippi 39183, United States · NAICS 237990 ENDIST Vicksburg No set-aside
Tybee Island Shoreline Protection Project Tybee Island, Chatham County, Georgia. Tybee Island, Georgia 31328, United States · NAICS 237990 ENDIST Savannah No set-aside
Annual Maintenance Dredging of Morehead City Inner Harbor Morehead City, North Carolina, United States · NAICS 237990 ENDIST Wilmington No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors