Arapaho& Roosevelt National Forests and Pawnee NG Roads IDIQ

Award Notice Posted

Solicitation number
AG-82AT-S-14-0009
Agency
Awarded
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-82AT-C-14-0012_AG-82AT-C-14-0013
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Colorado, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

AWARDED CONTRACTORS INFORMATION


AG-82AT-C-14-0012 HYDRO Construction Company, Inc.
301 E. Lincoln Ave., Fort Collins, CO 80524
DUNS # 078346590


AG-82AT-C-14-0013 Elk Creek Sand & Gravel, LLC.
12997 S. Elk Creek Rd., Pine CO 80470
DUNS # 132987624


 

Update #4 ·

AMENDMENT 000002 - See attached Amendment to include the following:

Post additional questions and answers.


See SF 30 and Continuation Summary of Changes Amend 000002

Proposal due date is NOT extended.

Update #3 ·

AMENDMENT 000001 - See attached Amendment to include the following:
1. Make corrections to Solicitation (see summary of changes).
2. To post s pre-bid meeting /site visit notes, questions and answers.
3. Provide revised solicitation document

SF 30 Continuation Summary of Changes Amend 000001

Update #2 ·

SOLICITATION: AG-82AT-S-14-0009
Arapaho and Roosevelt National Forests and Pawnee National Grassland Roads IDIQ 

SEE ATTACHED SOLICITATION DOCUMENTS: 

The Arapaho and Roosevelt National Forests and Pawnee National Grassland have a requirement for a Road maintenance IDIQ contract. The project includes, but is not limited to, the following work: Road and parking area reconstruction, construction and maintenance; road obliteration; road maintenance; clearing and grubbing; culvert installation and repair; sign installation and repair; erosion control; gate and fencing installation and repair; cattle guard installation and repair; material haul; haul and placement of imported borrow or aggregate; geotextile placement; and other related road work as described in the Statement of Work under each Task order.


Contractor shall provide all necessary heavy equipment, manpower, transportation and operating supplies and other incidentals to accomplish this work


Specific work locations will be identified on individual task orders and will be performed within the Arapaho and Roosevelt National Forests and the Pawnee National Grassland, Colorado.


The intent of this solicitation is to award multiple contracts covering the Arapaho and Roosevelt National Forests and the Pawnee National Grassland. Each Contract will have a base year with four one year options. Performance period is 365 calendar days, for the base and each exercised option year. Minimum cumulative (all three years) guarantee $100,000. Task orders range between $15,000 and $200,000. Any task order exceeding $30,000 will require applicable payment bonds. Five year total value will not exceed $9,999,900.00.


Pre- proposal Conference is Currently Scheduled for 2 April @ 0900.
Verify Date time and location in solicitation.
Supervisors Office, Arapaho & Roosevelt and Pawnee NG
2150 Centre Ave. Bld. E
Fort Collins, CO 80525
If you plan to attend RSVP both tparanda@fs.fed.us and cida@fs.fed.us


Set Aside: Total Small Business
NAICS 237310-Highway, Street, and Bridge Construction


All solicitation documents will be posted to this website approximately 19 March 2014. Proposals are estimated to be due 30 days after issue of solicitation (actual due date will be listed in the solicitation).


This notice does not obligate the Government to award a contract nor does it obligate the Government to pay for bid/proposal preparation costs.

Update #1 ·

Solicitation: AG-82AT-S-14-0009
Arapaho and Roosevelt National Forests and Pawnee National Grassland Roads IDIQ

The Arapaho and Roosevelt National Forests and Pawnee National Grassland have a requirement for a Road maintenance IDIQ contract. The project includes, but is not limited to, the following work: Road and parking area reconstruction, construction and maintenance; road obliteration; road maintenance; clearing and grubbing; culvert installation and repair; sign installation and repair; erosion control; gate and fencing installation and repair; cattle guard installation and repair; material haul; haul and placement of imported borrow or aggregate; geotextile placement; and other related road work as described in the Statement of Work under each Task order.


Contractor shall provide all necessary heavy equipment, manpower, transportation and operating supplies and other incidentals to accomplish this work


Specific work locations will be identified on individual task orders and will be performed within the Arapaho and Roosevelt National Forests and the Pawnee National Grassland, Colorado.


The intent of this solicitation is to award multiple contracts covering the Arapaho and Roosevelt National Forests and the Pawnee National Grassland. Each Contract will have a base year with four one year options. Performance period is 365 calendar days, for the base and each exercised option year. Minimum cumulative (all three years) guarantee $100,000. Task orders range between $15,000 and $200,000. Any task order exceeding $30,000 will require applicable payment bonds. Five year total value will not exceed $9,999,900.00.


Pre- proposal Conference is Currently Scheduled for 2 April @ 0900.
Verify Date time and location in solicitation.
Supervisors Office, Arapaho & Roosevelt and Pawnee NG
2150 Centre Ave. Bld. E
Fort Collins, CO 80525
If you plan to attend RSVP both tparanda@fs.fed.us and cida@fs.fed.us


Set Aside: Total Small Business
NAICS 237310-Highway, Street, and Bridge Construction


All solicitation documents will be posted to this website approximately 19 March 2014. Proposals are estimated to be due 30 days after issue of solicitation (actual due date will be listed in the solicitation).


This notice does not obligate the Government to award a contract nor does it obligate the Government to pay for bid/proposal preparation costs.

Files

File Type Posted
Amend_000002_Summary_of_Changes_pg2.docx DOCX document
SF_30_Amend_000002_AG-82AT-S-14-0009.pdf PDF
SF_30_Amend_000001_AG-82AT-S-14-0009.pdf PDF
AG-82AT-S-14-0009_Sol_pgs_4-41_rev1.rtf RTF text file
Amend_000001_Summary_of_Changes_pg2-4.docx DOCX document
Attach_02_CanyonLakesRangerDistrictMaps.pdf PDF
Attach_04_Wage_Decision_CO16.docx DOCX document
AG-82AT-S-14-0009_Sol_pgs_4-41.rtf RTF text file
AG-82AT-S-14-0009_1442_pgs_1-3.pdf PDF
Attach_Weblink_Rd_Mant_Video.docx DOCX document
Attach_05_Wage_Decision_CO17.docx DOCX document
Attach_06_Wage_Decision_CO24.docx DOCX document
Attach_03_Drawings.pdf PDF
Attach_01_FP03Supplemental_Specs.docx DOCX document
Show all 14