Amend_000002_Summary_of_Changes_pg2.docx

DOCX document 22 KB Posted

Attached to
Arapaho& Roosevelt National Forests and Pawnee NG Roads IDIQ
Solicitation number
AG-82AT-S-14-0009
Issued by

About this file

Amend 000002 Summary of Changes pg2

View the file

Other files

File Type Posted
SF_30_Amend_000002_AG-82AT-S-14-0009.pdf PDF
SF_30_Amend_000001_AG-82AT-S-14-0009.pdf PDF
AG-82AT-S-14-0009_Sol_pgs_4-41_rev1.rtf RTF text file
Amend_000001_Summary_of_Changes_pg2-4.docx DOCX document
Attach_Weblink_Rd_Mant_Video.docx DOCX document
Attach_05_Wage_Decision_CO17.docx DOCX document
Attach_06_Wage_Decision_CO24.docx DOCX document
Attach_03_Drawings.pdf PDF
Attach_01_FP03Supplemental_Specs.docx DOCX document
Attach_02_CanyonLakesRangerDistrictMaps.pdf PDF
Attach_04_Wage_Decision_CO16.docx DOCX document
AG-82AT-S-14-0009_1442_pgs_1-3.pdf PDF
AG-82AT-S-14-0009_Sol_pgs_4-41.rtf RTF text file
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 000002 AG-82AT-S-14-0009 Arapaho & Roosevelt National Forests Arapaho & Roosevelt National Forests and Pawnee National Grassland Roads IDIQ

SUMMARY OF CHANGES:

Questions and Answers:

Question 11: How do we submit the “Quality of Equipment” listing?

Answer: Offeror should provide a listing of specific equipment available for use under each pay item, and shall include make, model, and year, listing of attachments if applicable and any other pertinent information to enable the government to accurately evaluate the proposal. Address all the pay items; you may do this by grouping items with equipment.

Question12: 1. What line items should include General Conditions (we normally see this included under Mobilization, however, the items included in this bid are per mile and there are several line items depending on which equipment is to be used) or will this be negotiated on a per Task Order Basis?

Answer: General conditions should be included in the pay items that are most related to the work involved. General conditions shall be considered incidental to the pay item and contractor shall bid accordingly.

Question 13: 2. For the purposes of pricing out Labor which Wage Decision should be utilized since we do not know which county the work will be performed in yet (Should we use the most expensive for the purposes of this Solicitation)?

Answer: Please use the most expensive labor rate.

Section L

C. Quality of Equipment: Offeror is required to furnish, with their proposal, a listing of specific equipment available for use under each pay item, and shall include make, model, and year, present value, listing of attachments if applicable and any other pertinent information to enable the government to accurately evaluate the proposal.

Delete “present value”