4 Bridges

Awarded Award Notice Posted

Solicitation number
FA468619RA002
Agency
Air Combat Command Air Force, Department of Defense
Awarded
to Nomlaki Technologies, LLC
Set-aside
Competitive 8(a)

Opportunity facts

Contract number
FA468619CA013 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Beale AFB Beale AFB, California 95903, United States

Notice details come from SAM.gov. Updated .

Notice text

9 versions

Update #9 · Latest ·

Awarded Vendors: Nomlaki Technologies, LLC. Contract Award Dollar Amount: $10,402,000.00. Contract Award Date: 2019-07-10.

Update #8 ·

Solicitation AMENDMENT 4:
A. Revise completion date for entire project from 15 Nov 19 to 540 calendar days ANP (After Notice to Proceed).
B. Incorporate FBO posting for amendment 04 into contract writing system.
C. Attach FBO posting for amendment 04.
FBO AMENDMENT 5: Post Solicitation amendment 05 to FBO.
Solicitation AMENDMENT 5: Updated the SF 1442, added attachments to section J, and revised clauses in multiple sections.
Remove and Replace Attachment 01 from original posting with Attachment 1 dated 22 Feb 2019.
Remove and Replace Attachment 09 from original posting with Attachment 9.1 and 9.2.
Add Attachments 17 through 33.
FBO AMENDMENT 6: Post Solicitation amendment 06 to FBO.
Solicitation AMENDMENT 6: Removed and Replaced Attachments 31 and 32 with three new attachments that are updated and current. These new files will effectively be numbered 31, 32, and 32.1.
Also added the conformed copy of the solicitation (FA468619RA0006) which updated the section J attachments list.
FBO AMENDMENT 7: Post Solicitation amendment 07 to FBO.
Solicitation AMENDMENT 7: Responded to RFI# 114. Posted updated attachment 20 with answer to latest RFI.
FBO AMENDMENT 8: Post Solicitation amendment 08 to FBO. Solicitation AMENDMENT 8: Responded to RFI# 115-119. Posted updated attachment 20 with answer to latest RFIs and revised Solicitation- 19RA002..

Update #7 ·

Solicitation AMENDMENT 4:
A. Revise completion date for entire project from 15 Nov 19 to 540 calendar days ANP (After Notice to Proceed).
B. Incorporate FBO posting for amendment 04 into contract writing system.
C. Attach FBO posting for amendment 04.
FBO AMENDMENT 5: Post Solicitation amendment 05 to FBO.
Solicitation AMENDMENT 5: Updated the SF 1442, added attachments to section J, and revised clauses in multiple sections.
Remove and Replace Attachment 01 from original posting with Attachment 1 dated 22 Feb 2019.
Remove and Replace Attachment 09 from original posting with Attachment 9.1 and 9.2.
Add Attachments 17 through 33.
FBO AMENDMENT 6: Post Solicitation amendment 06 to FBO.
Solicitation AMENDMENT 6: Removed and Replaced Attachments 31 and 32 with three new attachments that are updated and current. These new files will effectively be numbered 31, 32, and 32.1.
Also added the conformed copy of the solicitation (FA468619RA0006) which updated the section J attachments list.
FBO AMENDMENT 7: Post Solicitation amendment 07 to FBO.
Solicitation AMENDMENT 7: Responded to RFI# 114. Posted updated attachment 20 with answer to latest RFI..

Update #6 ·

Solicitation AMENDMENT 4:
A. Revise completion date for entire project from 15 Nov 19 to 540 calendar days ANP (After Notice to Proceed).
B. Incorporate FBO posting for amendment 04 into contract writing system.
C. Attach FBO posting for amendment 04.
FBO AMENDMENT 5: Post Solicitation amendment 05 to FBO.
Solicitation AMENDMENT 5: Updated the SF 1442, added attachments to section J, and revised clauses in multiple sections.
Remove and Replace Attachment 01 from original posting with Attachment 1 dated 22 Feb 2019.
Remove and Replace Attachment 09 from original posting with Attachment 9.1 and 9.2.
Add Attachments 17 through 33.
FBO AMENDMENT 6: Post Solicitation amendment 06 to FBO.
Solicitation AMENDMENT 6: Removed and Replaced Attachments 31 and 32 with three new attachments that are updated and current. These new files will effectively be numbered 31, 32, and 32.1.
Also added the conformed copy of the solicitation (FA468619RA0006) which updated the section J attachments list..

Update #5 ·

Solicitation AMENDMENT 4:
A. Revise completion date for entire project from 15 Nov 19 to 540 calendar days ANP (After Notice to Proceed).
B. Incorporate FBO posting for amendment 04 into contract writing system.
C. Attach FBO posting for amendment 04.
FBO AMENDMENT 5: Post Solicitation amendment 05 to FBO.
Solicitation AMENDMENT 5: Updated the SF 1442, added attachments to section J, and revised clauses in multiple sections.
Remove and Replace Attachment 01 from original posting with Attachment 1 dated 22 Feb 2019.
Remove and Replace Attachment 09 from original posting with Attachment 9.1 and 9.2.
Add Attachments 17 through 33..

Update #4 ·

Solicitation AMENDMENT 4:
A. Revise completion date for entire project from 15 Nov 19 to 540 calendar days ANP (After Notice to Proceed).
B. Incorporate FBO posting for amendment 04 into contract writing system.
C. Attach FBO posting for amendment 04..

Update #3 ·

AMENDMENT Tracker:
There is a discrepancy between the Solicitation Amendments and FBO. FBO was incorrectly used to upload the actual documents/changes instead of incorporating them into the solicitation as an amendment then uploading the amendment into FBO (with the associated attachments). This notice is to correct that discrepancy. Moving forward amendments shall follow this format: 9 CONS creates amendment in contract writing system then posts final (unsigned) notice in FBO. Contracting Officer will then release amendment and sign copy. This will allow for uniformity of all posts and eliminate discrepancies.
The below is a summary of the current amendments as of 13 Feb 19 at 1430 PST.
FBO AMENDMENT 1: Post the solicitation to FBO.
Solicitation AMENDMENT 1: Conform the solicitation to the FBO post that was posted on 11 Feb 19. The original post did not include the solicitation to FBO. This has now been accomplished and has attached as Atch 11 titled 'Amendment 01 Confirmation dated 11 Feb 19.'


FBO AMENDMENT 2: Post EAL to FBO along with note to ensure potential offerors know time and date of Site Visit.
Solicitation AMENDMENT 2: Post an EAL template to FBO and inform contractors that a 'Site Visit will be held on 19 Feb 2019 at 1000 hrs. Attendees will meet at the 9th Contracting Squadron at 6500 B St. Beale AFB CA 95903. All attendees must submit an EAL 4 business days before site visit for access to the installation. EAL template has been added to this post as an amendment.' Update Section A - Contract Description 'This award will be an 8(a) competitive acquisition.' Add Atch 12 titled 'EAL Template' and Atch 13 titled 'Amendment 02 FBO Confirmation dated 12 Feb 19'



FBO AMENDMENT 3: Post solicitation amendment 01 to FBO.


Solicitation AMENDMENT 3: Created to allow for conformity of the amendment numbers and uniformity with FBO and the local contract writing system. No changes were made to the solicitation with this amendment.
Please submit all RFIs in writing after the site visit per the RFP. An amendment will be issued including all RFIs and any revisions.

.

Update #2 ·

Demolish, and dispose of all debris of four (4) reinforced concrete bridges (bridges 3111, 3112, 3113, and 3114) at Beale AFB, California in accordance with all local city ordinances, state, and federal regulations. Design and construct a bridge system (up to four bridges) to cross the four (4) water ways and replace bridges 3111, 3112, 3113, and 3114 at Beale AFB, California, in accordance with the criteria contained herein and using industry standard materials and efficient practices. In addition to the bridges, this project requires improvements to Gavin Mandery Drive through the four bridges area to meet current two way traffic standards, and construction of below ground communication and electrical lines. The road updates shall meet the California Department of Transportation (Caltrans) Highway Design Manual standards. Existing traffic lights and poles shall be removed and recycled. The road barriers and bridge approach shall be designed by the Contractor per the Caltrans standards. All existing signage shall be removed, and new signs shall be provided in accordance with the Caltrans (MUTCD) standard specifications. Maintain access to existing dirt roads within the work site boundary. A private consultant (AECOM) was hired by the Air Force to perform an engineering assessment and 35% concept design package (Engineering Report). The Engineering Report includes a geotechnical study, hydrologic and hydraulic analysis, 35% concept design drawings, and engineering cost estimates. The Engineering Report and drawings are included for the contractor's reference, however, the Design does not need to follow the concepts conveyed in the Engineering Report.
****FOR THE PDF BEALE AFB BASIN-WIDE COMPREHENSIVE ANAYLSIS HYDROLOGY REPORT PLEAST CONTACT THE POCS DIRECTLY****
AMENDMENT***Site Visit will be held on 19 Feb 2019 at 1000 hrs. Attendees will meet at the 9th Contracting Squadron at 6500 B St. Beale AFB CA 95903. All attendees must submit an EAL 4 buisness days before site visit for access to the installation. EAL template has been added to this post as an amendment. Please submit all RFIs in writing after this site visit per the RFP****

.

Update #1 ·

Demolish, and dispose of all debris of four (4) reinforced concrete bridges (bridges 3111, 3112, 3113, and 3114) at Beale AFB, California in accordance with all local city ordinances, state, and federal regulations. Design and construct a bridge system (up to four bridges) to cross the four (4) water ways and replace bridges 3111, 3112, 3113, and 3114 at Beale AFB, California, in accordance with the criteria contained herein and using industry standard materials and efficient practices. In addition to the bridges, this project requires improvements to Gavin Mandery Drive through the four bridges area to meet current two way traffic standards, and construction of below ground communication and electrical lines. The road updates shall meet the California Department of Transportation (Caltrans) Highway Design Manual standards. Existing traffic lights and poles shall be removed and recycled. The road barriers and bridge approach shall be designed by the Contractor per the Caltrans standards. All existing signage shall be removed, and new signs shall be provided in accordance with the Caltrans (MUTCD) standard specifications. Maintain access to existing dirt roads within the work site boundary. A private consultant (AECOM) was hired by the Air Force to perform an engineering assessment and 35% concept design package (Engineering Report). The Engineering Report includes a geotechnical study, hydrologic and hydraulic analysis, 35% concept design drawings, and engineering cost estimates. The Engineering Report and drawings are included for the contractor's reference, however, the Design does not need to follow the concepts conveyed in the Engineering Report.
****FOR THE PDF BEALE AFB BASIN-WIDE COMPREHENSIVE ANAYLSIS HYDROLOGY REPORT PLEAST CONTACT THE POCS DIRECTLY****

.

Attachments

Files attached to this notice, newest first
File Type Posted
Sol-Conform-19RA002-Repair_4_Bridges.pdf PDF
Section_J-Atach_20-RFILog-19RA002-Repair_4_Bridges.xlsx XLSX spreadsheet
Section_J-Atach_20-RFILog-19RA002-Repair_4_Bridges.xlsx XLSX spreadsheet
Attachment_31-4bridges.dwg DWG drawing
FA468619RA0020006_Conformed.pdf PDF
Attachments_32-2014-02-10_Modified_AECOM_Survey_Points_matches_4_bridges_NAVD29_dwg.csv CSV file
Attachment_32.1-2014-02-10_4_Bridges_Updated_to_same_hort_vert_datum_as_AECOM.dwg DWG drawing
Attachment_9.1_Beale_AF_Basin-Wide_Comprehensive_Analysis.pdf PDF
Attachment_18_-_Gavin_Mandry_Bridge_Survey_Shots.pdf PDF
Attachment_25_-_G-01.dwg DWG drawing
Attachment_33_-_1822_BealeAFB_GavinMandry_Bridge_X-sections_REV.CSV CSV file
Attachment_30_-_BEALE_BRIDGES.DXF DXF file
Attachment_21_-_Data_Request_Form__LIDAR.xls XLS spreadsheet
Attachment_9.2_Beale_AF_Basin-Wide_Comprehensive_Analysis.pdf PDF
FA468619RA0020005_Conformed.pdf PDF
Attachment_1_-_Wage_Determination,_Dated_22_Feb_2019.pdf PDF
Attachment_19_-_Sign-In_Sheet-Site_Visit_19_Feb_2019.pdf PDF
Attachment_16_-_Riparian_Mitigation_Planting_Guidelines.pdf PDF
Attachment_24_-_C-03_.dwg DWG drawing
Attachment_23_-_C-02_.dwg DWG drawing
Attachment_26_-_G-02.dwg DWG drawing
Attachment_28_-_S-01_to_S-05.dwg DWG drawing
Attachment_29_-_BEALE_BRIDGES.CSV CSV file
Attachment_31_-_Xref_Beale_AFB__Four_Bridges_T.Blk_INFO.dwg DWG drawing
Attachment_17_-__Consultation_Summary.pdf PDF
Attachment_22_-_C-01.dwg DWG drawing
Attachment_20_-_RFI_Log_25_Feb_19.xlsx XLSX spreadsheet
Attachment_27_-_G-03.dwg DWG drawing
Attachment_32_-_1822_BealeAFB_GavinMandry_Bridge_X-sections.dwg DWG drawing
FA4686~2.PDF PDF
FA468619RA0020004_Conformed_Copy.pdf PDF
FA468619RA0020003_SF_30_.pdf PDF
Solicitation_Amendment_FA468619RA0020004_SF_30.pdf PDF
SOLICI~1.PDF PDF
Atch_11_-_Amendment_01_Confirmation.pdf PDF
Solicitation_-_FA468619RA002.pdf PDF
Atch_2_-_AF_3064_-_Progress_Schedule.pdf PDF
Atch_6_-_Work_Site_Boundary.pdf PDF
Atch_3_-_AF_3065_-_Progress_Report.pdf PDF
Atch_4_-_AF66_Schedule_of_Material_Submittals.xls XLS spreadsheet
Atch_8_-_AECOM_Engineering_Assessment_Report.pdf PDF
Atch_7_-_AF_813.pdf PDF
Atach_10_-_Riparian_Mitigation_Planting_Guidelines.pdf PDF
Atch_5_-_AF3000.pdf PDF
Atch_1_-_Wage_Determination.pdf PDF
Show all 45

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity