AF66

View the file

Other files for this federal contract opportunity

Other files attached to 4 Bridges, newest first.
File Type Posted
Sol-Conform-19RA002-Repair_4_Bridges.pdf PDF
Section_J-Atach_20-RFILog-19RA002-Repair_4_Bridges.xlsx XLSX spreadsheet
Section_J-Atach_20-RFILog-19RA002-Repair_4_Bridges.xlsx XLSX spreadsheet
Attachment_31-4bridges.dwg DWG drawing
FA468619RA0020006_Conformed.pdf PDF
Attachment_32.1-2014-02-10_4_Bridges_Updated_to_same_hort_vert_datum_as_AECOM.dwg DWG drawing
Attachments_32-2014-02-10_Modified_AECOM_Survey_Points_matches_4_bridges_NAVD29_dwg.csv CSV file
Attachment_9.1_Beale_AF_Basin-Wide_Comprehensive_Analysis.pdf PDF
Attachment_18_-_Gavin_Mandry_Bridge_Survey_Shots.pdf PDF
Attachment_25_-_G-01.dwg DWG drawing
Attachment_33_-_1822_BealeAFB_GavinMandry_Bridge_X-sections_REV.CSV CSV file
Attachment_30_-_BEALE_BRIDGES.DXF DXF file
Attachment_21_-_Data_Request_Form__LIDAR.xls XLS spreadsheet
Attachment_29_-_BEALE_BRIDGES.CSV CSV file
Attachment_31_-_Xref_Beale_AFB__Four_Bridges_T.Blk_INFO.dwg DWG drawing
Attachment_17_-__Consultation_Summary.pdf PDF
Attachment_22_-_C-01.dwg DWG drawing
Attachment_20_-_RFI_Log_25_Feb_19.xlsx XLSX spreadsheet
Attachment_27_-_G-03.dwg DWG drawing
Attachment_32_-_1822_BealeAFB_GavinMandry_Bridge_X-sections.dwg DWG drawing
Attachment_19_-_Sign-In_Sheet-Site_Visit_19_Feb_2019.pdf PDF
Attachment_16_-_Riparian_Mitigation_Planting_Guidelines.pdf PDF
Attachment_24_-_C-03_.dwg DWG drawing
Attachment_23_-_C-02_.dwg DWG drawing
Attachment_26_-_G-02.dwg DWG drawing
Attachment_28_-_S-01_to_S-05.dwg DWG drawing
Attachment_9.2_Beale_AF_Basin-Wide_Comprehensive_Analysis.pdf PDF
FA468619RA0020005_Conformed.pdf PDF
Attachment_1_-_Wage_Determination,_Dated_22_Feb_2019.pdf PDF
FA4686~2.PDF PDF
FA468619RA0020003_SF_30_.pdf PDF
Solicitation_Amendment_FA468619RA0020004_SF_30.pdf PDF
FA468619RA0020004_Conformed_Copy.pdf PDF
Atch_11_-_Amendment_01_Confirmation.pdf PDF
SOLICI~1.PDF PDF
Solicitation_-_FA468619RA002.pdf PDF
Atch_2_-_AF_3064_-_Progress_Schedule.pdf PDF
Atch_6_-_Work_Site_Boundary.pdf PDF
Atch_3_-_AF_3065_-_Progress_Report.pdf PDF
Atch_8_-_AECOM_Engineering_Assessment_Report.pdf PDF
Atch_7_-_AF_813.pdf PDF
Atach_10_-_Riparian_Mitigation_Planting_Guidelines.pdf PDF
Atch_1_-_Wage_Determination.pdf PDF
Atch_5_-_AF3000.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
BAEY XXXXXPAX Terminal Repair and RenovationFA4686-17-D-000X-00XX
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 3
Construction ScheduleXNTP + 7
TCN Schedule (electronic required, hard copy optional)XNTP + 7
Contractor's Health, Safety, and Environment PlanXNTP + 7
Contractor's QA/QC PlanXNTP + 7
Copy of Engineering License(s) of person or consultancy responsible for designXDesign
DESIGN
All submissions to be provided in hard copy and electronically unless noted otherwise. 65%, 95%, and 100% Design Documents to include:XNTP + 21 (65%) NTP + 35 (95%) NTP + 45 (100%)
Roof Drain Storm Sewer Tie InXNTP+45
Wind Loading Diagrams for RoofXXNTP+45PE STAMP REQ'D
Structural Connection Details for Shear WallsXXNTP+45PE STAMP REQ'D
Structural Connection Details for FramingXXNTP+45PE STAMP REQ'D
Structural Connection Details for Blast Resistant Doors & WindowsXXNTP+45PE STAMP REQ'D
HVAC CalculationsXXNTP+45
Sprinkler LayoutXNTP+45FPE or NICET Tech stamp req'd
Fire Alarm LayoutXNTP+45FPE or NICET Tech stamp req'd
Communications LayoutXNTP+45
Technical SpecificationsXNTP+45PE STAMP REQ'D, NO HARD COPY
DEMOLITION/ASBESTOS
Demolition PlanXXXNTP+45
Asbestoes PlanXXXNTP+45
CIVIL
Soil Gradations for each type of soil usedXXInstall -7
Moisture-Density curve for each type of soil usedXInstall -7
Nuclear Densometer CalibrationXInstall -7
Soil Compaction Test Results for Utilities, Facilities & PavementXXInstall+7
Storm PipeXDesign+14
ARCHITECTURAL
Blast Resistant Doors and FramesXXXNTP+45
Door HardwareXXNTP+45Hardware Schedule
Gypsum Board-Type XXXNTP+45
Gypsum Board-Type X-Mold ResistantXXNTP+45
Wood PanelingXXXNTP+45
Wood Chair RailsXXXNTP+45
Wood Ceiling CloudXXXNTP+45
Sheet Vinyl FlooringXXXNTP+45
Rubber BaseXXXNTP+45
Ceiling TilesXXXNTP+45
Blast Resistant WindowXXXXXXXNTP+45
GlazingXXXNTP+45
Solid Surface CountertopsXXXXNTP+45
Kitchen CabinetsXXXXXNTP+45
Garbage DisposalXXNTP+45
Interior PaintXXXNTP+45
Exterior PaintXXXNTP+45
Roofing SystemXXXXXNTP+45
Roofing InsulationXXXXXXNTP+45
Roof DrainsXXXXXNTP+45
ScuppersXXNTP+45
CopingXXNTP+45
FlashingXXNTP+45
STRUCTURAL
Reinforcing Steel DrawingsXNTP+45
Concrete Mix DesignXXNTP+45
Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion JointsXXXXXNTP+45
Concrete Field Test ResultsXNTP+45
Reinforcing Steel Mill CertificationsXXNTP+45
Slump Test results & Concrete Truck Tickets (per truck)XTest + 3
7-Day Concrete Compressive Strength TestXXTest + 3
28-Day Concrete Compressive Strength TestXXTest + 3
Blast Resistant Window AttachmentXXDesign + 14
MECHANICAL
HVAC BalancingXDesign+14
RegistersXXDesign+14
DampersXXDesign+14
DuctworkXDesign+14
Sprinkler HeadsXXNTP+14
Ductwork Pressure Drops Before RemovalXXNTP+14
Ductwork Pressure Drops After InstallationXXNTP+14
DuctworkXXNTP+14
ControlsXXDesign+14
PipingXDesign+14
HeatersXXDesign+14
ValvesXXDesign+14
PumpsXXDesign+14
Thermal InsulationXXDesign+14
InstrumentationXXDesign+14
PLUMBING
Plumbing FixturesXXXXXNTP+45
Piping for WaterXXNTP+45
Garbage DisposalXXNTP+45
Waste and VentXXXXNTP+45
INTERIOR ELECTRICAL
Cables(electrical,comm,fire alarm)XXXXXXXXNTP+45
SwitchesXXXXXXXXNTP+45
ReceptaclesXXXXXXXXNTP+45
PanelsXXXXXXXXNTP+45
BreakersXXXXXXXXNTP+45
ConduitsXXXXXXXXNTP+45
Lighting FixturesXXXXXXXXNTP+45
Lighting UPS units (if req'd)XXXXXXXNTP+45
Communication System Outlets(incl jacks)XXXXXXXXNTP+45
Communications patch panelsXXXXXXXNTP+45
PA SpeakersXXXXXXXNTP+45
Fire Alarm Devices (All)XXXXXXXXXXNTP+45
Occupancy SensorsXXXXXXXXNTP+45
Power PacksXXXXXXXNTP+45
EXTERIOR ELECTRICAL
ConduitsXXNTP+14
TransformerXXXXXXNTP+14
MeterXXXXXNTP+14
Cables(med & low voltage)XXXXNTP+14
SwitchesXXNTP+14
ContactorsXXXNTP+14
PanelsXXNTP+14
BreakersXXNTP+14
ControllerXXXNTP+14
Junction CabinetXXXXXNTP+14
Heating MatXXXXXXXXNTP+14
CLOSEOUT
O&M maint data and maint manuals & Manufacturer's Warranty for Communications EquipmentXXXInstall + 4
Factory and Field Test Certificates, Logs and Test ResultsXBefore Acceptance
Inspection LogbookXBefore Acceptance
As Builts (electronic in AutoCAD and hard copies on Mylar)XFinal + 7

&L&"Arial,Bold"&6AF FORM 66, OCT 99 &"Arial,Regular"Previous Edition Will Be Used