Pedestrian and Bicycle Paths - Harvey County
The Kansas Department of Transportation is requesting bids for pedestrian and bicycle paths construction in the City of Sedgwick in Harvey County, with electronic proposals due August 19, 2026 at 1:00 PM Local Time via Bid Express, and bids opening and reading at 3:00 PM the same day at the Eisenhower State Office Building in Topeka.
The scope encompasses 0.08 miles of pedestrian and bicycle paths west of North Commercial Avenue from 5th Street to 6th Street, including site clearing and grubbing, excavation, sidewalk and concrete pavement construction, drainage systems, erosion control, signage, pavement markings, lighting systems, seeding and sodding, and site improvements and utilities. Work must comply with KDOT's 2015 Standard Specifications for State Road and Bridge Construction and applicable special provisions.
Contractors must be prequalified with KDOT and register as bid holders by 5:00 PM on the Monday preceding the letting date. The earliest start date is December 14, 2026, and the latest start date is June 7, 2027. The contract includes 70 restricted days and 90 total contract working days. Contractors must submit a current Tax Clearance Certificate from the Kansas Department of Revenue at contract award and must observe the minimum wage rate applicable to Harvey County.
Standard provisions require noncollusion certification, financial prequalification, debarment history disclosure, federal lobbying restrictions, foreign drone prohibitions, affirmative action compliance, and equal employment opportunity assurances. Unit cost spreadsheets for plant materials, electric lighting systems, and water system items are due no later than noon on the Friday following the letting day. Contract award must be executed within ten business days of notice.
The project is identified as State Project Number 040 TE 0576-01, Federal Project Number ACTA-T057(601), and Contract Number 526082515, and is funded through federal and state sources.
Kansas 8/19/26, 1:00 AM 8/16/26, 1:00 AM PCCP Patching I-135 Harvey County
The Kansas Department of Transportation is requesting sealed bids for Portland Cement Concrete Pavement (PCCP) patching on Interstate 135 in Harvey County, with bids due August 19, 2026.
The work covers a 5.985-mile segment of I-135 extending from 0.3 miles north of Southeast 54th Street North to the K-151-135 Junction. The scope includes all materials, labor, and equipment necessary to complete pavement patching in accordance with Kansas Department of Transportation specifications and standards. Bidding is on a unit-price basis.
The contract will be awarded to the lowest responsive and responsible bidder. Contractors must review all bid documents, including scope of work and technical specifications, to ensure accurate cost estimation.
Kansas 8/19/26, 1:00 AM 8/17/26, 1:00 AM Newton APAC Facility Hauck Avenue - Paving, Sanitary Sewer, & Water Distribution
Harper County, Kansas is soliciting bids for infrastructure construction at the Newton APAC Facility, with proposals due October 2, 2026. The work encompasses approximately 5,070 square yards of 8-inch concrete pavement, 400 square yards of 8-inch reinforced concrete pavement, 1,000 linear feet of 8-inch sanitary sewer line, and 1,805 linear feet of 8-inch waterline.
The contractor must comply with applicable Kansas construction standards and specifications, including proper grading, compaction, and installation procedures for both pavement and underground utilities. Experience with municipal paving and utility installation projects of similar scope and complexity is required. The contractor is responsible for obtaining necessary permits, coordinating with existing utility providers, and ensuring all work meets local codes and engineering standards prior to project completion and acceptance.
Kansas 10/2/26, 1:00 AM 9/20/26, 1:00 AM