Lakeside Drive Over Lake Rowena/Lake Sue Pipe Culvert Repair – Supplemental Conditions Summary

This supplemental conditions document outlines the special provisions and requirements for Orange County, Florida's civil infrastructure project involving the structural rehabilitation of a 120-inch diameter corrugated metal pipe culvert beneath Lakeside Drive. The primary deliverable requires installation of a centrifugally cast concrete pipe (CCCP) structural lining system using high-strength, corrosion-resistant, fiber-reinforced cementitious geopolymer material to address pipe deterioration while protecting an existing water main and sealing separated joints and deteriorated sections. The project necessitates substantial completion within 150 consecutive calendar days and final completion within 180 consecutive calendar days from the Notice to Proceed, with liquidated damages assessed at $500 per day for non-compliance. Site access is restricted exclusively to waterway access via barge, with no vehicle access permitted on Lakeside Drive. The contractor must submit a detailed work progress schedule, comprehensive maintenance of traffic plan, video documentation of before and after conditions, and coordinate all utility relocations and adjustments throughout the construction period. A non-mandatory pre-bid conference is scheduled for March 5, 2026, with sealed bids due electronically by 4:00 p.m. EST on Thursday, March 26, 2026, and questions due by Wednesday, March 11, 2026 at 5:00 p.m. EST.

The estimated project cost is $628,577.09, with payment structured as 95 percent of completed work and subject to 5 percent retainage until final completion. Contractors must possess at least five years of experience with CCCP systems and provide references for at least three similar projects completed within the last ten years involving centrifugally cast concrete pipes of 72-inch or larger diameter. The contractor bears full responsibility for all site investigation, subsurface condition assessment, groundwater determination, utility location identification, and compliance with all federal, state, and local permits, including St. Johns River Water Management District General Environmental Resource Permit No. 226907-1, United States Army Corps of Engineers Nationwide Permit SAJ-2024-02220, and National Pollutant Discharge Elimination System requirements. No claims for extras are permitted based on actual subsurface or groundwater conditions encountered. The contractor must provide a licensed Professional Surveyor and Mapper to establish field benchmarks, survey staking, and control points; furnish a competent superintendent at the site during all working hours; maintain 24-hour emergency contact availability; comply with all environmental and endangered species regulations at no additional cost; and assume responsibility for all property damage, utility damage, and restoration costs arising from construction activities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLEMENTAL CONDITIONS / SPECIAL PROVISIONS

LAKESIDE DRIVE OVER LAKE ROWENA/LAKE SUE PIPE CULVERT REPAIR

1. DRAINAGE IMPROVEMENTS: The primary objective of this project involves the structural rehabilitation of the existing 120-inch diameter corrugated metal pipe (CMP) under Lakeside Drive using a centrifugally cast concrete pipe (CCCP) coating system. The pipe lining mortar used will be a high-strength, corrosion resistant, fiber reinforced, cementitious geopolymer material specifically designed to form a structural pipe within the existing CMP.

The structural CCCP coating system will support all dead and live loads, and the lining will be applied to the existing CMP. The existing protruding water main is to be protected and coated.

Separated joints and deteriorated holes in the existing pipe will be sealed with a high-strength grout. Cofferdams will be installed on both sides of the pipe during the duration of construction. All work is within Orange County right-of-way and Orange County easements.

The project is only accessible via waterways (barge) and no access is allowed along Lakeside Drive.

2. UTILITY IMPROVEMENTS: N/A

3. CONSTRUCTION SCHEDULE / LIQUIDATED DAMAGES: This work requires

Substantial Completion in 150 days from the date of Notice of Proceed with Final Completion in 180 days. If final completion is not met by the required time, liquidated damages will be applied at the rate of $500.00 per day as per the provisions in the Contract governing liquidated damages.

4. CONTRACTOR’S RESPONSIBILITIES:

a. Site Investigation: The CONTRACTOR shall be responsible for satisfactorily determining, prior to the submission of a bid, the nature and location of the work, the conformation of the ground, the character and quality of the substrata, the types and quantity of materials to be encountered, the nature of the groundwater conditions and all other matters which can in any way affect the work under this contract. The prices established for the work to be done will reflect all costs pertaining to the work. Any claims for extras based on substrate or groundwater table conditions will not be allowed.

Information available to the COUNTY on subsoil conditions is available to bidders as information only and solely for the convenience of bidders. The accuracy or correctness of this information may not be actual subsurface conditions. The CONTRACTOR agrees that he will make no claims against the COUNTY if, in carrying out the work, he finds that actual conditions encountered do not conform to those indicated.

The information shown on these drawings concerning type and location of underground and other utilities is based on information provided by the utility owners, available records, and surveyed field information. The information may not reflect actual conditions or be all inclusive regarding all utilities in the area, either in service or abandoned, or that the utilities are in the horizontal or vertical locations shown. The

CONTRACTOR shall make his own determination as to the type and location of utilities as necessary to establish their locations and avoid damage. Damage to existing utilities because of the CONTRACTOR’s work or his subcontractors shall be the sole responsibility of the CONTRACTOR to repair, pay all fines, pay all fees, and all other cost associated with restoring the utility. The CONTRACTOR must notify Sunshine State One-Call at least 5 days prior to construction.

Unless otherwise noted, the CONTRACTOR shall take ownership of all materials encountered which are designated to be removed or not incorporated into the Work, such as paving materials, paving brick, asphalt block, RAP/Milled material, concrete slab, sidewalk, curb and gutter, pipe materials, etc., excavated in the removal of existing pavements, and dispose of them outside of the right-of-way. Payment for this item shall be included in Pay Item No. 110-1 Clearing and Grubbing.

b. Video Survey: The CONTRACTOR shall submit a quality video documenting before and after construction field conditions for the entire project. The COUNTY will approve all views. Payment included in the price for Mobilization.

c. Supervision and Superintendence: The CONTRACTOR shall provide a competent superintendent at the site at all times while work is in progress to act as the CONTRACTOR’S agent. The superintendent shall be capable of properly interpreting the Contract Documents, have sufficient experience in highway/street construction, and be able to speak and understand English. The superintendent shall have full authority to receive instructions from the COUNTY and to execute the orders or directions of the COUNTY, including promptly supplying any materials, tools, equipment, labor, and incidentals that may be required. The CONTRACTOR shall furnish the qualifications of the proposed superintendent to the COUNTY at the preconstruction conference. The COUNTY will be the sole determiner of whether or not the experience of the superintendent is sufficient for the purposes of this paragraph. At least one other responsible person who speaks and understands English shall be on the project during all working hours.

d. Supervision for Emergencies: A responsible person, who speaks and understands

English, shall be available at or reasonably near the worksite on a 24 hour basis, seven days a week. This person shall be designated as the point of contact for emergencies and in cases that require immediate action to maintain traffic or to resolve any other problem that might arise. A list of the phone numbers and names of personnel designated to be contacted in cases of emergency, along with a description of the project location, shall be submitted, by certified mail, to the Florida Highway Patrol and all other local law enforcement agencies.

e. Protection of Property: The CONTRACTOR shall be responsible for any damage whatsoever whether occurring within or outside of the boundaries of the PROJECT including any property adjacent to the PROJECT when such damage is caused in whole or in part by any act of the CONTRACTOR or any employee, agent or subcontractor working under, with or in privity to the CONTRACTOR. The CONTRACTOR and all the aforementioned parties shall stay off private property adjacent to the PROJECT unless the CONTRACTOR receives from the affected property owner a written release, which specifically releases the COUNTY from any liability for any damage to such property caused by any acts other than those of the COUNTY. This written release must be acceptable in form to the COUNTY and delivered to and accepted by the COUNTY before the CONTRACTOR makes any entry upon such private property. The CONTRACTOR shall also obtain all necessary permits and approvals from all regulatory agencies for all activities to be conducted by the CONTRACTOR on private property. Necessary approvals may include but are not limited to the United States Army Corps of Engineers, the United States Environmental Protection Agency, the Florida Department of Environmental Protection, the Florida Department of Transportation, the applicable Water Management District, the Orange County Environment Protection Division (EPD), and applicable municipal agencies for properties located within incorporated areas. The CONTRACTOR shall provide written documentation to the COUNTY of the necessary approvals and permits which have been obtained.

The CONTRACTOR shall provide copies of these written agreements, clearly indicating that the County is not liable. Use of private property without such agreements will necessitate the immediate cessation of work, removal of all CONTRACTOR materials, and complete cleanup of the private property. No cost or time extensions will be granted due to work stoppages, restarts, or property restoration.

At the preconstruction conference, the CONTRACTOR shall submit to the COUNTY a current aerial map (11” x 17” minimum size) depicting at a minimum the temporary staging area including property lines, easement lines, and right-of-way lines.

f. Compliance with Time Requirements: The CONTRACTOR shall commence work in accordance with the accepted Work Progress Schedule and provide sufficient labor, materials and equipment to complete the work within the time limit(s) set forth. Should the CONTRACTOR fail to furnish sufficient and suitable equipment, forces, and materials, as necessary to prosecute the work in accordance with the accepted schedule, the COUNTY may withhold all estimates that are, or may become due, and/or suspend the work until the CONTRACTOR corrects such deficiencies.

g. Project Progress Aerial Photographs: N/A

h. Use of Public Roads and Streets: Use of public streets shall be such as to provide a minimum of inconvenience to the public and to traffic. Any earth or excavated material spilled from trucks shall be removed by the CONTRACTOR and streets cleaned to the satisfaction of the COUNTY. Cleaning may include street sweeping and/or washing, if so directed by the COUNTY.

The CONTRACTOR shall provide vehicular access to each residence, subdivision and other public roads at all times.

No CONTRACTOR activity allowed on Lakeside Drive. Site access is via waterways by barge.

i. Use of Explosives: No blasting shall be done except upon approval by the COUNTY and the governmental agency or political subdivision having jurisdiction. When the use of explosives is approved by the COUNTY as necessary for the execution of the work, the CONTRACTOR shall use the utmost care so as not to endanger life or property, and assume responsibility for any such damage resulting from his blasting operations, and whenever directed, the number and size of the charges shall be reduced.

All explosives shall be stored in a secure manner and all such storage places shall be clearly marked, "DANGER EXPLOSIVES" and shall be in care of competent watchmen. All permits required for the use of explosives shall be obtained by the CONTRACTOR at his expense. All requirements of the governmental agency issuing permit shall be observed.

j. Damage to Existing Structures and Utilities: The CONTRACTOR shall be responsible for and make good all damage resulting from his activities, both within and beyond the limits of this contract, to buildings, telephone, power or other cables, water pipes, storm sewer facilities, sanitary pipes, gas lines, traffic signalization, or other utilities or structures, which may be encountered, whether or not shown on the plans.

k. Submission of Working Schedule: The CONTRACTOR shall provide a schedule that shows the various activities of work in sufficient detail to demonstrate a reasonable and workable plan to complete the project within the established Contract Time. The order and interdependence of activities and the sequence for accomplishing the work shall be shown. All activities shall be described in sufficient detail so that the COUNTY can readily identify the planned work and measure the progress of each activity. Each activity will be shown with a beginning work date, duration, and monetary value.

Activities for the procurement, fabrication, and/or delivery of materials, batch plants, and equipment shall be included.

Activities for the review of shop drawings and submittals shall be included.

Activities indicating coordination with utility owners that have facilities within the limits of construction requiring adjustment or relocation shall be included.

Milestone activities, when required by the Contract Documents, shall be included.

In a project with more than one phase, each phase and its completion date shall be adequately identified. Activities will not be allowed to span more than one phase.

The CONTRACTOR shall submit a narrative with the schedule, consisting of a concise written description of the construction plan.

An updated Work Progress Schedule shall be submitted monthly to the COUNTY. All changes in the planned order start or finish dates, or duration of an activity will be applied.

A revised Work Progress Schedule shall be submitted to the COUNTY for acceptance when significant changes are made to the logic or durations of the activities. The COUNTY will review the corrected schedule and respond within 7 calendar days of receipt.

The COUNTY will return inadequate schedules to the CONTRACTOR for corrections.

A corrected schedule shall be resubmitted within 15 calendar days from the date of the COUNTY’s return transmittal. By acceptance of the schedule, the COUNTY does not endorse or otherwise certify the validity or accuracy of the activity durations or sequencing of activities.

The COUNTY will use the initially accepted schedule as the baseline against which to measure progress and identify critical activities that are controlling items of work.

If the CONTRACTOR fails to finalize either the initial or a revised schedule in the time specified, the COUNTY will withhold all Contract payments until the schedule is accepted.

l. Work Hours: Project work hours shall be between 7:00 AM and 6:00 PM Monday through Friday, excluding normal Orange County holidays, unless approved otherwise by the COUNTY. The CONTRACTOR shall request approval from the COUNTY at least 72 hours in advance for work outside those hours. Work before 7:00AM or after 6:00PM, or on days other than the above-described normal workdays, and requiring the presence of the COUNTY'S RESIDENT PROJECT REPRESENTATIVE shall require that the CONTRACTOR reimburse the COUNTY for the salary and overtime cost of the RESIDENT PROJECT REPRESENTATIVE. Reimbursement shall be made by the CONTRACTOR at the rate of $45.00 per hour by check payable to the Board of County Commissioners accompanying each monthly pay request. Each pay request shall include a tabulation of the overtime dates, times, hours and costs for the pay period.

The amount of the check shall agree with the tabulated total. In the event the CONTRACTOR chooses to not submit a pay request when normally due for work he has completed, reimbursement still required for the resident project representative on monthly basis and shall include the tabulation of the overtime worked during the preceding month. Payment must be made for overtime work performed to address emergencies outside the above-described normal working hours, unless the RESIDENT PROJECT REPRESENTATIVE determines, at his or her sole discretion that the emergency is the result of actions by third parties.

m. Care of trees, Shrubs and Grass: The CONTRACTOR shall maintain in good condition all cultivated grass plots, trees and shrubs beyond the grading limits of this Contract. Please note there is extensive landscaping along Lakeside Drive that should not be disturbed or damaged. After completion of the work, the CONTRACTOR shall replace or restore to the original condition all destroyed or damaged shrubbery or grass areas. Tree limbs, which interfere with equipment operation and are approved for pruning, shall be neatly trimmed and the tree cut coated with tree paint.

n. Final Clean Up: The entire street shall be cleaned by sweeping or washing, as determined by the COUNTY, prior to final acceptance.

5. WORK BY OTHERS AND UTILITY COORDINATION: The CONTRACTOR shall cooperate with owners of any underground or overhead utilities in their removal and relocation operations, in order that these operations may progress in a timely, reasonable and orderly manner and that service rendered by these parties will not be interrupted.

Excavators shall comply with Florida Statutes, Chapter 556, regarding notification of existing gas and oil pipeline company owners prior to excavating. Evidence of such notice shall be furnished to the COUNTY prior to excavating. During the period of this contract the CONTRACTOR shall coordinate all utility relocations and adjustments necessary for the project. The CONTRACTOR shall conduct meetings weekly or at a frequency approved by the Engineer with all affected Utility Owners, and the minutes of those meetings shall be distributed to each Utility owner, the COUNTY, and any other affected entity. The CONTRACTOR shall incorporate the durations listed in the Utility Relocation

Schedules into his Contract Schedule, and transmit copies of that schedule to each Utility owner. The CONTRACTOR shall constantly communicate the status of the progress of the project to the Utility Owners, and advise them of any potential impacts to the progress due to the presence of the utilities. The CONTRACTOR shall keep the COUNTY apprised of all developments related to Utility Relocation and job progress. The CONTRACTOR shall coordinate during the period of this contract with the applicable lighting facility owners for the installation of roadway lighting facilities for the project. The CONTRACTOR shall not be entitled to additional compensation from the COUNTY as a result of failure of any utility to remove, relocate, or install their facilities within any particular time frame.

6. CHANGE OF CONTRACT AMOUNT AND CONTRACT TIME: The number of days of any change to the contract time incorporated by Change Order shall be applied to both the Substantial Completion time and the Final Completion time, unless otherwise established by the COUNTY in these specifications.

7. WARRANTY AND GUARANTEE, ACCEPTANCE OF DEFECTIVE WORK:

a. Tests and Inspections: The CONTRACTOR shall be solely responsible for all costs associated with laboratory testing, whether performed on-site or after the collection of samples from the job site. Payment for such testing is included in the items requiring testing as specified in the Contract Documents, including all applicable specifications and technical provisions. All testing results shall be signed and sealed by a Professional Engineer licensed in the State of Florida or by an accredited testing laboratory that has been approved by the COUNTY. The CONTRACTOR shall ensure compliance with these requirements prior to submission of any test results.

8. SURVEY REQUIREMENTS:

a. General: The CONTRACTOR shall employ a Professional Surveyor and Mapper

(PSM), registered in the State of Florida and satisfactory with the COUNTY, to lay out the work for benchmarks, vertical and horizontal features noted on the Contract Documents, established at the site, or supplied by the COUNTY. The CONTRACTOR shall provide the COUNTY at the pre-construction conference, the name of the Professional Surveyor and Mapper to perform Project survey work. All work of every description shall be laid out and checked by the CONTRACTOR who will be held solely responsible for its correctness. Work may be checked by the COUNTY and, in the event of a discrepancy, the COUNTY'S decision shall be final.

No special compensation will be made to the CONTRACTOR to defray costs of surveys and measurements.

Prior to the beginning of any construction the CONTRACTOR shall submit to the COUNTY a set of field notes verifying that the existing benchmark elevations are relative to at least two reference benchmarks shown on the construction plans and a tie to one established Orange County Vertical Benchmark. The CONTRACTOR shall also verify ties from project control points to reference points as shown on the construction plans. A set of field notes for all additional benchmark and reference point ties shall be submitted to the COUNTY. All submittals shall be signed and sealed by a Professional Surveyor and Mapper registered in the State of Florida.

Within twenty-one (21) calendar days after receiving the Notice to Proceed, the CONTRACTOR shall have a licensed Professional Surveyor and Mapper establish in the field the right-of-way, baseline of construction, and limits of construction using wooden 1" X 4" X 4'0" stakes at a maximum spacing of 100 feet. Stations shall be marked on each stake and shall be of sufficient size and clarity that they can be easily read by the unaided eye at a distance of 150 feet. Right-of-way and limits of construction staking shall be maintained by the CONTRACTOR throughout construction. No invoice for payment will be processed until the survey staking is complete to the satisfaction of the ENGINEER. Payment is included in the price for bid item number 101-1 “Mobilization”. The CONTRACTOR shall pay all expenses in connection with this work.

All survey work shall comply with Chapter 5J-17 Standards of Practice, Florida Administrative Code (F.A.C.), regarding minimum technical standards for land surveying in the State of Florida.

The CONTRACTOR shall perform all calculations required, and set all stakes needed such as grade stakes, offset stakes, reference point stakes, slope stakes, and other reference marks or points necessary to provide lines and grades for construction. When performing utility construction as part of the project, the CONTRACTOR shall establish all horizontal and vertical controls necessary to carry out such work.

b. Specific Staking Requirements: When performing new base construction as part of the project, the CONTRACTOR shall set stakes to establish lines and grades for subgrade, base, curb, and related items at intervals along the line of the work no greater than 50 feet on tangents and 25 feet on curves. The CONTRACTOR shall set grade stakes at locations that the Engineer directs to facilitate checking of subgrade, base, and pavement elevations in crossovers, intersections, and irregular shaped areas.

For bridge construction stakes and other control, the CONTRACTOR shall set references at sufficiently frequent intervals to ensure construction of all components of a structure in accordance with the lines and grades shown in the plans.

For projects where the plans do not show a centerline or other survey control line for construction of the work (resurfacing, safety modifications, etc.), the CONTRACTOR shall provide only such stakes as necessary for horizontal and vertical control of work items.

For resurfacing and resurfacing-widening type projects, the CONTRACTOR shall establish horizontal controls adequate to ensure that the asphalt mix added matches with the existing pavement. In tangent sections, set horizontal control points at 100 foot intervals by an instrument survey. In curve sections, set horizontal control points at 25 foot intervals by locating and referencing the centerline of the existing pavement.

The CONTRACTOR shall establish by an instrument survey, and mark on the surface of the finished pavement at 25 foot intervals, the points necessary for striping of the finished roadway. As an exception, for resurfacing and resurfacing/widening projects, the CONTRACTOR shall establish these points in the same manner as used for horizontal control of paving operations. The CONTRACTOR shall mark the pavement with white paint. If performing striping, the COUNTY may approve an alternate method for layout of striping provided that the CONTRACTOR achieves an alignment equal to or better than the alignment that would be achieved using an instrument survey.

For projects that include temporary or permanent striping of “no passing zones”, the CONTRACTOR shall provide the location and length of these zones as shown in the plans, except projects where the vertical or horizontal alignment is new or altered from the preconstruction alignment. For projects that consist of new or altered vertical or horizontal alignment, the COUNTY will provide the location and length of the "no passing zones" during construction. For these projects, the CONTRACTOR shall notify the COUNTY not less than 21 calendar days prior to beginning striping.

c. Benchmarks: During construction the CONTRACTOR shall provide a Control Point Aluminum Disk set in concrete (e.g. in headwalls, back of sidewalks, back of inlets, etc.) at the beginning and end of the project and at a maximum of 1100 feet between existing or established benchmarks along the project alignment – (see attached disc requirements). The CONTRACTOR’S PSM shall conduct a three-wire leveling run (closed loop) through the benchmarks based on Orange County Datum NAVD88 (or other datum as specified on the Engineering plans). The level work will be performed to Second Order, Class II standards (or better) and the maximum allowable error will be no more than 8 mm times the square root of “K”, where “K” is the total distance in kilometers. This is also approximately equivalent to 0.035 feet times the square root of “K”, where “K” is the total distance in miles. The level run will be performed with a geodetic automatic level or better whose three wires will be read to 0.001 meters or

0.001 feet. Invar rods are preferred but not required. Digital automatic levels with associated bar code rods are also acceptable. Prior to the issuance of final completion, the CONTRACTOR shall submit a copy of the field notes certified by the PSM to the COUNTY. Benchmark elevations shall be expressed in English units.

Orange County survey monuments shall be aluminum or brass stamped as shown on the attached sketch. The CONTRACTOR shall procure the monuments from any commercial supplier of survey monuments. The CONTRACTOR is advised that the County obtains its monuments from Berntsen International, Inc.; www.berntsen.com Berntsen disc no. C35D-(3-1/2" domed) Logo no. B9119 (800-356-7388).

d. Control Points: Upon completion of construction, all permanent control points (PCPs) depicted on the survey control sheet of the construction plans shall be established along the construction centerline. PCPs located on hard surfaces such as pavement or concrete shall be installed as “P.K.” nails and discs or another durable and identifiable form of monumentation, subject to approval by the County Surveyor or authorized agent. PCPs located on soft surfaces shall be marked with 4” x 4” concrete monuments, ensuring a minimum length of 24”. Each point will bear a durable cap or disk inscribed with either the Florida registration number of the professional surveyor and mapper in charge or the certificate of authorization number of the legal entity, preceded by LS or LB as applicable, and the letters "PCP."

e. Property Corners: For property corners disturbed during construction, new markers shall be established at the intersections of property lines and right-of-way lines for all Orange County construction projects. At every juncture in right-of-way lines, points of curvature (PCs), and points of tangency (PTs), as well as at intervals no greater than 1,000 feet along the right-of-way line, markers meeting the specifications outlined in the "Control Points" section will be installed. These markers will display either the surveyor's registration number or the licensed business number.

f. Public Land Corners: All public land corners within the limits of construction shall be protected. If a corner monument is in danger of being destroyed or disturbed, the CONTRACTOR shall notify the COUNTY, and the COUNTY SURVEYOR, without delay, by telephone. The CONTRACTOR shall provide written follow-up confirmation within forty-eight (48) hours of telephone notification. In the event that a land corner is disturbed or damaged it will be reset with a 4” x 4” concrete monument, which shall be protected in a cast iron valve box, if in pavement.

Prior to the issuance of final completion, the CONTRACTOR shall submit certified corner records, prepared by a Professional Surveyor and Mapper, for all altered, reset and/or relocated public land corners to the Florida Department of Environmental Protection, Bureau of Survey and Mapping, in accordance with the requirements of Chapter 177.507 of the Florida Statutes. A certified copy shall also be provided to the COUNTY. Furthermore, the Professional Surveyor and Mapper will note on the AS- BUILT PLANS the location of all corners set or found and submit copies of all field notes to the County Surveyor or his/her agent.

g. National Geodetic Survey (N.G.S.) / United States Coast & Geodetic Survey

(U.S.C. & G.S.) Monuments: The CONTRACTOR shall immediately notify the COUNTY of any N.G.S. / U.S.C. & G.S. monuments which may be in danger of being disturbed. For instructions on how to relocate any N.G.S. monuments the CONTRACTOR shall notify in writing:

State Geodetic Advisor Orange County Surveyor Bureau of Surveying and Mapping Public Works Engineering Division 3900 Commonwealth Blvd., Suite 105 4200 S. John Young Parkway Tallahassee, FL 32399-3000 Orlando, FL 32839-9205 Phone: (850) 245-2606 Phone: (407) 836-8672 Fax: (850) 245-2645

h. The CONTRACTOR shall bear all costs of establishing, relocating or re-establishing all disturbed N.G.S. monuments, public land corners, property corners, or right-of-way monuments.

Survey field book(s) shall be used throughout the course of the project by the CONTRACTORs PSM.

The complete survey field book(s) shall be submitted to the County Surveyor concurrently with the submission of the CONTRACTOR’S requisition for final payment. When a data collector is used, the CONTRACTOR shall also submit a paper copy of the raw data files bound in a book, together with the electronic copy on a thumb drive.

9. BRIDGE REQUIREMENTS: N/A

10. RAILROAD CROSSING: N/A

11. RIGHT-OF-WAY / PARCEL CONSIDERATIONS: The CONTRACTOR is notified that at the time of this bid, the COUNTY owns all right-of-way and easements required to complete the project.

12. MAINTENANCE OF TRAFFIC: At the pre-construction conference the CONTRACTOR shall submit a detailed Maintenance of Traffic plan for approved by Orange County, Traffic Engineering to the Orange County Highway Construction Division.

The Maintenance of Traffic plan shall address the maintenance of vehicular and pedestrian traffic between the limits of construction, as well providing business signage for all business along the corridor and must be signed and sealed by a Professional Engineer registered in the State of Florida. The attached Maintenance of Traffic plans provided by the COUNTY is for reference and guidance only. The CONTRACTOR shall not be entitled to any additional compensation as a result of the Maintenance of Traffic plan he/she chooses to use, whether or not he/she prepared such plan.

The CONTRACTOR will not be allowed any nighttime work. Variable message board (VMB) signs shall be installed ten (10) days prior to all day lane closures and major traffic impacts to major roads (as directed by the engineer). The Contractor shall submit a Start Work Notice at least seven (7) days prior to installing VMB’s. The Cost shall be included in pay item number 102-1, Maintenance of Traffic.

13. PEDESTRIAN WALKWAY: The CONTRACTOR shall provide and maintain a safe walkway for pedestrians, in compliance with the Americans with Disability Act, along the limits of the project and for the entire project duration. The cost will be included under Pay Item 102-1 Maintenance of Traffic.

14. LANDSCAPE ESTABLISHMENT AND MAINTENANCE: N/A

15. LANDSCAPE AND MITIGATION RETAINAGE: N/A

16. SITE CONTAMINATION: N/A

17. SEPTIC TANKS & WELLS: N/A

18. PAY ITEMS: The cost of all equipment, materials and labor for temporary or permanent facilities necessary to construct the improvements identified in the plans, specifications, or other Contract Documents shall be deemed to be included in the various items making up the Contract Price. No separate payment shall be made to the CONTRACTOR for any such equipment, materials and labor for which a separate Pay Item has not been provided.

19. COORDINATION: N/A

20. DRIVEWAY CONSTRUCTION: N/A

21. MILLING & RESURFACING: N/A

22. DAMAGES: Any damages caused by the Contractor to sidewalks, driveways, curbs, sod, etc. not scheduled for replacement shall be removed and replaced at the Contractor's expense. Patching, surface repairs, coating or overlaying of affected sections shall not be allowed.

23. ENVIRONMENTAL CONCERNS:

FEDERALLY OR STATE DESIGNATED LISTED SPECIES: The Florida Fish and Wildlife Conservation Commission maintains the state list of animals designated as Federally-designated Endangered or Threatened, State-designated Threatened, or State designated Species of Special Concern, in accordance with Rules 68A-27.003 and 68A-

27.005. The CONTRACTOR must comply with the above-mentioned rules at no cost to the COUNTY. There also shall be no additional compensation in the event the CONTRACTOR is required to modify his means and methods or construction schedule in order to comply with the requirements of any regulatory agency with regard to any Federally or State listed species which may be encountered within or in proximity to the project limits during construction. The CONTRACTOR may be granted non-compensable days to the extent the critical path of the project is impacted by temporary work stoppages that may be required to address the presence of listed species as mentioned above.

24. REQUEST FOR INFORMATION (RFI): The COUNTY will require a reasonable amount of time, at least 10 business days, to respond to any RFI submitted by the CONTRACTOR. Any delay in responding to the RFI cannot be used as a reason to reimburse for any additional compensation, including delay claims.

25. EARTHWORK: The CONTRACTOR shall note that the soil survey shown in the plans is based on limited geotechnical investigation. The CONTRACTOR shall field verify and test all excavated earthwork material to determine if the soil is classified as a Select soil and suitable for embankment utilization. In the event that any excavated earthwork material is not suitable for embankment utilization, the CONTRACTOR shall replace the unsuitable material with Select soil to furnish and install the required embankment at no additional cost to the COUNTY. The CONTRACTOR shall be responsible for the disposal of the unsuitable material at a COUNTY approved site at no additional cost to the

COUNTY.

The COUNTY grants access to all the bidders to the entire project limits. The bidders are responsible for obtaining approval from all the regulatory agencies that have jurisdiction for investigative work. A Right-of-Way Utilization Permit shall be issued by the Development Engineering Division for performing borings within the project limits. Contact the Development Engineering Division to obtain information regarding a Right-of-Way utilization permit. The bidders shall be entirely responsible to ensure that all the disturbed areas are restored to as good as or better than the existing conditions. The bidders shall be responsible for complying with all permit conditions, rules and regulations including but not limited to NPDES and threatened and endangered species.

26. ORANGE COUNTY INSPECTOR’S OFFICE: N/A

27. PIPE QUALITY CONTROL AND INSPECTION: The CONTRACTOR is hereby notified that at the COUNTY’S discretion the County will inspect the drainage pipes and / or drainage structures as they are being produced. This inspection by the COUNTY in no way precludes the COUNTY’S right and ability to reject damaged pipe as a result of manufacturing, transporting, handling, installing/laying, videoing, etc. The CONTRACTOR shall be responsible to coordinate this inspection with the COUNTY and to determine the manufacturer’s schedule and to ensure that the procurement of these materials does not impact the CONTRACTOR’S overall project schedule.

No additional time or compensation will be made to the CONTRACTOR to defray time or costs of any of the work or delays for complying with the requirements set forth above, but such costs shall be considered as having been included in the price stipulated for the several items of work to be done under this contract.

28. PERMITS

a. St. Johns River Water Management District (SJRWMD) Permit

i. General Permit No. 226907-1, dated January 23, 2025 and expires January 23, 2030.

ii. WATER MANAGEMENT DISTRICT: The CONTRACTOR shall be responsible for compliance with all applicable requirements of Rule 40C-2.042(9), Florida Administrative Code (F.A.C.), for a General Permit for Dewatering. If the CONTRACTOR’s proposed work is expected to exceed the time duration and/or the volume limits, or does not meet any of the other requirements listed with the requirements of Rule 40C-2.042(9), the CONTRACTOR must apply for and obtain such other water use permit to authorize dewatering that may be required by the Water Management District, at no cost to the COUNTY.

b. United States Army Corps of Engineers (USACE) Permit - SAJ-2024-02220

(NWP-BW)

i. Nationwide Permit SAJ-2024-02220 (NWP-BAW), dated December 18, 2024 and expires March 14, 2026.

ii. The activities subject to this permit are authorized pursuant to authorities under Section 404 of the Clean Water Act (33 U.S.C. § 1344).

c. National Pollutant Discharge Elimination System (NPDES) permit

i. General: The CONTRACTOR shall to obtain or modify, as necessary, all dewatering and land clearing permits required by STATE and COUNTY agencies pursuant to 62-621.300 F.A.C. and Orange County Code.

ii. Land Clearing: The CONTRACTOR shall be responsible to prepare and submit the Notices of Intent (NOI) and the Notice of Termination (NOT) to the Florida Department of Environmental Protection (FDEP). The CONTRACTOR shall be responsible to adhere to the construction plan sheet documents addressing the Stormwater Pollution Prevention Plan (SWPPP) and shall identify and incorporate any and all additional needs to prevent, control and reduce erosion and water pollution, meeting the requirements or special conditions of all permits authorizing project construction. In the event no SWPPP is provided the CONTRACTOR shall be responsible to prepare the SWPPP. The SWPPP and NOI forms, attached to this document, shall be completed and submitted by the CONTRACTOR to the COUNTY prior to the preconstruction meeting.

iii. Notice Of Intent (NOI): should be submitted at least two days prior to commencement of construction (permit fees are the responsibility of the

CONTRACTOR).

iv. Notice of Termination (NOT): should be submitted within 14 days of final completion of the project (permit fees, if any, are the responsibility of the

CONTRACTOR).

The CONTRACTOR shall be responsible for compliance with the EPA’s NPDES

Stormwater Construction permit, the Stormwater Pollution Prevention Plan and the FDEP Generic Permit for Stormwater Discharge from Construction Activities that Disturb One or More Acres of Land. Furthermore, the CONTRACTOR shall also comply with the FDEP Generic Permit for Stormwater Discharge from Large and Small Construction Activities. The CONTRACTOR shall comply with the requirements indicated by the Florida Department of Environmental Protection.

The cost of this work will be included under pay item No 104-14 - Prevention, control and abatement of erosion and water pollution.

v. Dewatering: The CONTRACTOR shall be responsible for compliance with the

FDEP Notice of Intent to Use the Generic Permit for Discharge of Groundwater from Dewatering Operations (FDEP Document 62-621.300(2)(b), which can be found at https://floridadep.gov/forms).

If it is determined that the disposal or discharge of the dewatering effluent is not authorized by this generic permit, the CONTRACTOR shall diligently pursue further required permit(s) from FDEP or other agencies.

Prior to submitting their bid, each prospective CONTRACTOR has the opportunity to perform a search to determine the extent, if any, of contaminated sites within 500 feet of the PROJECT boundaries. It is the intent of this paragraph to provide each prospective CONTRACTOR with an opportunity to investigate the water quality in the vicinity of the PROJECT in order to base his/her bid on means and methods of dewatering.

If, prior to or during the dewatering, it is determined that the disposal or discharge of the dewatering effluent is not authorized by the FDEP’s Generic Permit for Stormwater Discharge from Large and Small Construction Activities, the CONTRACTOR shall diligently pursue further required permit(s) from FDEP or other agencies without resort to delay claims or recompense from the COUNTY for either permit application activities or the time required to obtain such permits.

The CONTRACTOR shall be responsible for all costs for water quality monitoring, treatment, storage, and disposal of the groundwater in a manner acceptable to the COUNTY and to all applicable regulatory agencies to reduce the concentration of parameters with exceedances to acceptable levels. The CONTRACTOR will be responsible for obtaining any additional permits required by regulatory agencies to implement the CONTRACTOR’s chosen method of disposal and discharge of the groundwater. No additional compensation will be made to CONTRACTOR for permitting. The CONTRACTOR shall comply with Water Quality Requirements of the Special Provisions, related to the National Pollutant Discharge Elimination System (NPDES).

Because the CONTRACTOR’S means and methods of dewatering could lead to potential liability to third parties for damages resulting from the means and methods of dewatering, at the COUNTY’S discretion the means and methods for the dewatering plans are subject to a prior cursory review by the COUNTY, where issues and concerns may be submitted for the CONTRACTOR’S consideration.

The CONTRACTOR shall be deemed fully responsible for the means and method of the dewatering. Should the CONTRACTOR decide to modify or revise the means and method for the dewatering plan, another cursory review will have to be conducted by the COUNTY. Please note that containment on site of dewatering effluent is not considered treatment and disposal for purposes of payment under the pay item number 104-14.

CONTRACTOR shall be responsible to include in his/her bid all cost for treatment and disposal of dewatering effluent. Should it become necessary for the CONTRACTOR to treat and dispose dewatering effluent off site, Orange County will only compensate the CONTRACTOR for those activities at the unit price bid. No additional compensation will be paid to the CONTRACTOR for treatment and disposal of dewatering effluent, regardless of the actual cost incurred by the CONTRACTOR.

d. Certifications/Permit Compliance: The CONTRACTOR shall prepare and submit all certifications required by regulatory agencies having jurisdiction over the project, including Engineer's Certifications and as-built drawings required by the Water Management District(s).

29. REPORTS

The following Documents are being provided for informational purposes only and can be accessed at the following website:

1. Report of Geotechnical Engineering Evaluation LAKESIDE DRIVE PIPE CULVERT

REPAIR provided by Geotechnical and Environmental Consultants, Inc. (GEC) dated September 11, 2024.

2. PRELIMINARY SEASONAL HIGH WATER ASSESSMENT LAKESIDE DRIVE

DRAINAGE IMPROVEMENTS ORANGE COUNTY, FLORIDA provided by Halff & Associates, Inc. dated July 22, 2024.

THIS ENDS THE SPECIAL PROVISIONS