Y23-784_Technical_Specifications.pdf

PDF 459 KB Posted

Attached to
Orange County Landfill Roadway Improvements at Old Scale House
Solicitation number
Y23-784
Issued by
Orange County, Orlando City, Florida

About this file

The file is a comprehensive set of technical specifications for the Orange County Landfill Exit Road Improvements project in Orange County, Florida. The project involves constructing an additional outbound scale, modifying traffic lanes, and improving overall traffic movement at the landfill facility. Key components include building a new 60-foot outbound truck scale with a 200,000-pound gross capacity, installing a new operator's booth, refurbishing the existing operator's booth, constructing roadways, and implementing stormwater improvements. The County will be accepting sealed bids electronically through the ProcureNow OpenGov e-Procurement Platform until 4:00 pm EST on Thursday, July 27, 2023, with an estimated project cost of $1,513,000.00.

The technical specifications detail extensive requirements for the truck scale system, including specific equipment specifications such as stainless steel load cells, digital weight indicators, totalizers, automated gate, stoplight, and compatibility with the County's existing computer systems. The project is divided into two bid alternatives: the primary scope of work and optional additional work for the area behind the Citizens Drop-Off Area and full-depth shoulders. Bidders must provide comprehensive documentation, including shop drawings, operation and maintenance manuals, warranties, and meet specific quality assurance standards. The scale must comply with State of Florida weights and measure requirements, NIST Handbook 44, and National Electric Code, with the manufacturer required to have at least five years of similar installation experience in solid waste transfer stations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exit Road Improvements 01000 - 1 March 2023 Orange County, Florida

SECTION 01000

GENERAL REQUIREMENTS

PART 1 – GENERAL

1.01 DESCRIPTION OF WORK

A. Description: The work to be done consists of the furnishing of all labor, materials and equipment, and the performance of all work included in this Contract. The summary of the work is presented in Section 01010.

B. Requirements Included:

1. The Contractor shall furnish all labor, superintendence, materials, plant, power, light, heat, fuel, water, tools, appliances, equipment, supplies, and other means of construction necessary or proper for performing and completing the work, from the date of Notice to Proceed until the date of Final Completion and Acceptance by County. The Contractor shall obtain and pay for all required permits. The Contractor shall perform and complete the work in the manner best calculated to promote rapid construction consistent with safety of life and property and to the satisfaction of the County, and in strict accordance with the Contract Documents. The Contractor shall clean up the work and maintain it during and after construction, until accepted, and shall do all work and pay all costs incidental thereto. The Contractor shall repair or restore all structures and property that may be damaged or disturbed during performance of the work.

2. The cost of incidental work described in these General Requirements, for which there are no specific Contract Items, shall be considered as part of the general cost of doing the work and shall be included in the prices for the various Contract Items. No additional payment will be made, therefore.

3. The Contractor shall provide and maintain such modern plant, tools, and equipment as may be necessary, in the opinion of the Engineer, to perform in a satisfactory and acceptable manner all the work required by this Contract. Only equipment of established reputation and proven efficiency shall be used. The Contractor shall be solely responsible for the adequacy of Contractor’s workmanship, materials and equipment, prior approval of the Engineer notwithstanding.

C. Utility Installations and Structures:

1. Utility installations and structures shall be understood to include all poles, tracks, pipes, wires, conduits, house service connections, vaults, manholes and all other appurtenances and facilities pertaining thereto whether owned or controlled by the County, other governmental bodies or privately owned by individuals, firms or corporations, used to serve the public with transportation, traffic control, gas, electricity, telephone, sewerage, drainage, water or other public or private property which may be affected by the work shall be deemed included hereunder.

Exit Road Improvements 01000 - 2 March 2023

2. The Contract Documents contain data relative to existing utility installations and structures above and below the ground surface. These data are not guaranteed as to their completeness or accuracy, and it is the responsibility of the Contractor to investigation on its own to be fully informed of the character, condition and extent of all such installations and structures as may be encountered and as may affect the construction operations.

3. The Contractor shall protect all utility installations and structures from damage during the work. Access across any buried utility installation or structure shall be made only in such locations and by means approved by the Engineer. The Contractor shall so arrange its operations as to avoid any damage to these facilities. All required protective devices and construction shall be provided by the Contractor at the Contractor’s expense. All existing utilities damaged by the Contractor, which are shown on the Drawings or have been located in the field by the utility, shall be repaired by the Contractor, at the Contractor’s expense, as directed by the Engineer. No separate payment shall be made for such protection or repairs to utility installations or structures.

4. Utility installations or structures owned or controlled by the County or other governmental body which are shown on the Drawings to be removed, relocated, replaced or rebuilt by the Contractor shall be considered as a part of the general cost of doing the work and shall be included in the prices bid for the various contract items.

5. Where utility installations of structures owned or controlled by the County or other governmental body are encountered during the course of the work, and are not indicated on the Drawings or in the Specifications, and when, in the opinion of the Engineer, removal, relocation, replacement or rebuilding is necessary to complete the work under this Contract, such work shall be accomplished by the utility having jurisdiction, or such work may be ordered, in writing by the Engineer, for the Contractor to accomplish. If such work is accomplished by the utility having jurisdiction it will be carried out expeditiously and the Contractor shall give full cooperation to permit the utility to complete the removal, relocation, replacement or rebuilding as required. If the Contractor accomplishes such work, it will be paid for as extra work as provided in the General Conditions.

6. The Contractor shall, at all times in performance of the work, employ approved methods and exercise reasonable care and skill so as to avoid unnecessary delay, injury, damage or destruction of utility installations and structures; and shall, at all times in the performance of the work, avoid unnecessary interference with, or interruption of, public utility services, and shall cooperate fully with the County thereof to that end.

7. All County and other governmental utility departments and other owners of public utilities which may be affected by the work will be informed in writing by the County within two weeks after the execution of the Contract or Contracts covering the work.

Such notice will set out, in general, and direct attention to, the responsibilities of the County and other governmental utility departments and other owners of utilities for such installations and structures as may be affected by the work and will be accompanied by one set of Drawings and Specifications covering the work under such Contract or Contracts.

Exit Road Improvements 01000 - 3 March 2023

8. In addition to the general notice given by County, the Contractor shall give written notice to County and other governmental utility departments and other owners of utilities of the location of the proposed construction operations, at least 72 hours in advance of breaking ground in any area or on any unit of the work.

9. The maintenance, repair, removal, relocation or rebuilding of utility installations and structures, when accomplished by the Contractor as herein provided, shall be done by methods approved by the owners of such utilities.

1.02 DRAWINGS AND PROJECT MANUAL

A. Drawings:

1. The Drawings referred to in the Contract Documents bear the general project name and number as shown in the Notice to Bidders (Advertisement).

2. When obtaining data and information from the Drawings, figures shall be used in preference to scaled dimensions, and large-scale drawings in preference to small-scale drawings.

B. Copies Furnished to Contractor:

1. After the Contract has been executed, the Contractor will be furnished one (1) complete set of printed sheets (22 inches by 34 inches), electronic files, and one (1) copy of the Project Manual (Contract Requirements and Specifications) and all addenda.

2. The Contractor shall furnish each of the subcontractors, manufacturers, and material men such copies of the Contract Documents as may be required for their work. All copies of the Contract Documents shall be printed from the reproducible sets furnished to the Contractor. All costs of reproduction and printing shall be borne by the Contractor.

C. Supplementary Drawings:

1. When, in the opinion of the Engineer, it becomes necessary to explain more fully the work to be done or to illustrate the work further or to show any changes which may be required, drawings known as Supplementary Drawings, with specifications pertaining thereto, will be prepared by the Engineer and the Contractor will be furnished one (1) complete set of printed sheets (22 inches by 34 inches), electronic files, and one (1) copy of the Specifications.

2. The Supplementary Drawings shall be binding upon the Contractor with the same force as the Drawings. Where such Supplementary Drawings require either less or more than the estimated quantities of work, credit to the County or compensation therefore to the Contractor shall be subject to the terms of the Contract Documents.

Exit Road Improvements 01000 - 4 March 2023

D. Contractor to Check Drawings and Data:

1. The Contractor shall verify all dimensions, quantities and details shown on the Drawings, Supplementary Drawings, schedules, Specifications or other data received from the Engineer, and shall notify Engineer of all errors, omissions, conflicts, and discrepancies found therein. Failure to discover or correct errors, conflicts or dis-crepancies shall not relieve the Contractor of full responsibility for unsatisfactory work, faulty construction or improper operation resulting therefrom nor from rectifying such conditions at the Contractor’s own expense. Contractor will not be allowed to take advantage of any errors or omissions, as the Engineer will furnish full instructions, should such errors or omissions be discovered.

2. All schedules are given for the convenience of the Engineer and the Contractor and are not guaranteed to be complete. The Contractor shall assume all responsibility for the making of estimates of the size, kind, and quality of materials and equipment included in work to be done under the Contract.

E. Specifications: The Technical Specifications consist of three parts: General, Products and

Execution. The General Section contains General Requirements, which govern the work.

Products and Execution modify and supplement these by detailed requirements for the work and shall always govern whenever there appears to be a conflict.

F. Intent:

1. All work called for in the Specifications applicable to this Contract, but not shown on the Drawings in their present form, or vice versa, shall be of like effect as if shown or mentioned in both. Work not specified in either the Drawings or in the Specifications, but involved in carrying out their intent or in the complete and proper execution of the work, is required and shall be performed by the Contractor as though it were specifically delineated or described.

2. The apparent silence of the Specifications as to any detail, or the apparent omission from them of a detailed description concerning any work to be done and materials to be furnished, shall be regarded as meaning that only the best general practice is to prevail and that only material and workmanship of the best quality is to be used, and interpretation of these Specifications shall be made upon that basis. In the event of inconsistencies in the requirements of the Drawings and Specifications, the more expensive will be required.

1.03 MATERIALS

A. Manufacturer:

1. The names of proposed manufacturers, suppliers and dealers who are to furnish materials, fixtures, or other fittings shall be submitted to the Engineer for approval, as early as possible, to afford proper investigation and checking. Such approval must be obtained before Shop Drawings will be checked. No manufacturer will be approved for any materials to be furnished under this Contract unless manufacturer shall be of good reputation and have a plant of ample capacity. Manufacturer shall, upon the request of

Exit Road Improvements 01000 - 5 March 2023 the Engineer, be required to submit evidence that they have manufactured a similar product to the one specified and that it has been previously used for a like purpose for a sufficient length of time to demonstrate its satisfactory performance.

2. All transactions with the manufacturers or subcontractors shall be through the

Contractor, unless the Contractor shall request, in writing to the Engineer, that the manufacturer or subcontractor deal directly with the Engineer. Any such transactions shall not in any way release the Contractor from the Contractor’s full responsibility under this Contract.

3. Any two or more pieces of material of the same kind, type or classification, and being used for identical types of service, shall be made by the same manufacturer.

B. Delivery:

1. The Contractor shall deliver materials in ample quantities to insure the most speedy and uninterrupted progress of the work so as to complete the work within the allotted time.

2. The Contractor shall also coordinate deliveries in order to avoid delay in, or impediment of, the progress of the work of any related Contractor.

1.04 INSPECTION AND TESTING

A. General:

1. The Contractor will provide for the testing of materials unless otherwise specified.

2. For tests specified to be made by the County, the testing personnel shall make the necessary inspections and tests and the reports thereof shall be in such form as will facilitate checking to determine compliance with the Contract Documents. Five copies of the reports shall be submitted, and authoritative certification thereof must be furnished to the County as a prerequisite for the acceptance of any material.

3. If, in the making of any test of any material, it is ascertained by the County that the material does not comply with the Contract Documents, the Contractor will be notified thereof and will be directed to refrain from delivering said material, or to remove it promptly from the site or from the work and replace it with acceptable material, without cost to the County.

B. Costs:

1. All inspection and testing of materials furnished under this Contract will be provided by the Contractor, unless otherwise expressly specified.

2. Materials submitted by the Contractor as the equivalent to those specifically named in the Contract may be tested by the County for compliance. The Contractor shall reimburse the County for the expenditures incurred in making such tests of materials, which are rejected, for noncompliance.

Exit Road Improvements 01000 - 6 March 2023

C. Inspection of Materials:

1. The Contractor shall give notice in writing to the County, sufficiently in advance of their intention to commence the manufacture or preparation of materials especially manufactured or prepared for use in or as part of the permanent construction. Such notice shall contain a request for inspection, the date of commencement and the expected date of completion of the manufacture or preparation of materials. Upon receipt of such notice, the County will arrange to have a representative present at such times during the manufacture as may be necessary to inspect the materials or the County will notify the Contractor that the inspection will be made at a point other than the point of manufacture.

2. The Contractor must comply with these provisions before shipping any material. Such inspection shall not release the Contractor from the responsibility for furnishing materials meeting the requirements of the Contract Documents.

D. Certificate of Manufacture:

1. When inspection is waived or when the County so requires, the Contractor shall furnish to County authoritative evidence in the form of Certificate of Manufacture that the materials to be used in the work have been manufactured and tested in conformity with the Contract Documents.

2. These certificates shall be notarized and shall include copies of the results of physical tests and chemical analyses, where necessary, that have been made directly on the product or on similar products of the manufacturer.

E. Failure of Tests:

1. Any defects in the materials or their failure to meet the tests, guarantees or requirements of the Contract Documents shall be promptly corrected by the Contractor by replacements or otherwise. The decision of the County as to whether or not the Contractor has fulfilled its obligations under the Contract shall be final and conclusive.

2. The Contractor shall reimburse the County for all failed tests or shall pay for all re-tests.

3. If the Contractor fails to make these corrections or if the improved materials, when tested, shall again fail to meet the guarantees or specified requirements, the County, notwithstanding its partial payment for work, and materials, may reject the materials and may order the Contractor to remove them from the site at their own expense.

4. In case the County rejects any materials, then the Contractor shall replace the rejected materials within a reasonable time. If the Contractor fails to do so, the County may, after the expiration of a period of thirty (30) calendar days after giving Contractor notice in writing, proceed to replace such rejected materials and the cost thereof shall be deducted from any compensation due or which may become due the Contractor under the Contract.

Exit Road Improvements 01000 - 7 March 2023

F. Final Inspection: During such final inspections, the work shall be clean and free from water. In no case will the final estimate be prepared until the Contractor has complied with all requirements set forth and the County has made the final inspection with the Contractor of the entire work and is satisfied that the entire work is properly and satisfactorily constructed in accordance with the requirements of the Contract Documents.

1.05 TEMPORARY STRUCTURES

A. Temporary Fences:

1. If, during the course of the work, it is necessary to remove or disturb any fence or part thereof, the Contractor shall provide a suitable temporary fence at its own expense.

2. The Engineer shall be solely responsible for the determination of the necessity for approving a temporary fence and the type of temporary fence to be used.

B. Responsibility for Temporary Structures: In accepting the Contract, the Contractor assumes full responsibility for the sufficiency and safety of all temporary structures or work and for any damage which may result from their failure or their improper construction, maintenance or operation and will indemnify and save harmless the County from all claims, suits or actions and damages or costs of every description arising by reason of failure to comply with the above provisions.

1.06 TEMPORARY SERVICES

A. Accident Prevention:

1. Precautions shall be exercised at all times for the protection of person and property.

The safety provisions of applicable laws, building and construction codes shall be observed.

2. The Contractor shall comply with the U.S. Department of Labor Safety and Health

Regulations for construction promulgated under the Occupational Safety and Health Act of 1970 (PL 91-596). Hours and Safety Standards Act (PL 91-54), except where state and local safety standards exceed the federal requirements and except where state safety standards have been approved by the Secretary of Labor in accordance with provisions of the Occupational Safety and Health Act, shall be complied with.

B. First Aid: The Contractor shall keep upon the site, at each location where work is in progress, a completely equipped first aid kit and shall provide ready access thereto at all times when personnel are employed on the work.

1.07 LINES AND GRADES

A. Grade:

1. All work under this Contract shall be constructed in accordance with the lines and grades shown on the Drawings, or as given by the Engineer. The full responsibility for keeping alignment and grade shall rest upon the Contractor.

Exit Road Improvements 01000 - 8 March 2023

2. The County has established benchmarks and base line controlling points for the Contractor to use. Reference marks for lines and grades as the work progresses will be located to cause as little inconvenience to the prosecution of the work as possible.

3. The Contractor shall so place excavation and other materials as to cause no inconvenience in the use of the reference marks provided. Contractor shall remove any obstructions placed by Contractor contrary to this provision.

B. Surveys:

1. The Contractor shall furnish and maintain, at their own expense, stakes and other such materials for setting project control points.

2. The Contractor shall check the County’s permanent reference points by such means as may deemed necessary and, before using them, shall call the Engineer's attention to any inaccuracies.

3. The Contractor shall, at their own expense, establish all working or construction lines and grades as required from the County’s permanent reference marks set by the County, and shall be solely responsible for the accuracy thereof. Contractor shall, however, be subject to the check and review of the County.

C. Safeguarding Marks:

1. The Contractor shall safeguard all points, stakes, grade marks, monuments and bench marks made or established on the work, bear the cost of reestablishing them if disturbed, and bear the entire expense of rectifying work improperly installed due to not maintaining or protecting or to removing without authorization such established points, stakes and marks.

2. The Contractor shall safeguard all existing and known property corners, monuments and marks adjacent to but not related to the work and, if required, shall bear the cost of reestablishing them if disturbed or destroyed.

1.08 ADJACENT STRUCTURES AND LANDSCAPING

A. Responsibility:

1. The Contractor shall also be entirely responsible and liable for all damage or injury as a result of the Contractor’s operations to all other adjacent public and private property, structures of any kind and appurtenances thereto met with during the progress of the work.

2. The cost of protection, replacement in their original locations and conditions or payment of damages for injuries to such adjacent public and private property and structures affected by the work, whether or not shown on the Drawings, and the removal, relocation and reconstruction of such items called for on the Drawings or specified shall be included in the various Contract Items.

Exit Road Improvements 01000 - 9 March 2023

3. Contractor is expressly advised that the protection of buildings, structures, tunnels, tanks, pipelines, etc. and related work adjacent and in the vicinity of the Contractor’s operations, wherever they may be, is solely the Contractor’s responsibility.

4. Conditional inspection of buildings or structures in the immediate vicinity of the project which may reasonably be expected to be affected by the work shall be performed by and be the responsibility of the Contractor.

5. Contractor shall, before starting operations, make an examination of the interior and exterior of the adjacent structures, buildings, facilities, etc., and record by notes, measurements, photographs, etc., conditions which might be aggravated by open excavation and construction. Repairs or replacement of all conditions disturbed by the construction shall be made to the satisfaction of the County. This does not preclude conforming to the requirements of the insurance underwriters. Copies of surveys, photographs, reports, etc., shall be given to the County.

6. Prior to the beginning of any excavations, the Contractor shall advise the County of all buildings or structures on which work is intended to be performed or which performance of the project work will affect.

B. Protection of Trees:

1. All trees and shrubs shall be adequately protected by the Contractor with boxes and otherwise and in accordance with ordinances governing the protection of trees. No excavated materials shall be placed so as to injure such trees or shrubs. Trees or shrubs destroyed by negligence of the Contractor or employees of the Contractor shall be replaced by Contractor with new stock of similar size and age, at its proper season and at the sole expense of the Contractor.

2. Beneath trees or other surface structures, where possible, pipelines may be built in short tunnels, backfilled with excavated materials, except as otherwise specified, or the trees or structures carefully supported and protected from damage.

3. The County may order the Contractor, for the convenience of the County, to remove trees along the line or trench excavation. If so ordered, the County will obtain any permits required for removal of trees.

C. Lawn Areas: Lawn areas shall be left in as good condition as before the starting of the work.

Where sod is to be removed, it shall be carefully removed, and later replaced, or the area where sod has been removed shall be restored with new sod in the manner described in the Workmanship and Materials section.

D. Restoration of Fences:

1. Any fence, or part thereof, that is damaged or removed during the course of the work shall be replaced or repaired by the Contractor and shall be left in as good condition as before the starting of the work.

Exit Road Improvements 01000 - 10 March 2023

2. The manner in which the fence is repaired or replaced and the materials used in such work shall be subject to the approval of the County.

3. The cost of all labor, materials, equipment, and work for the replacement or repair of any fence shall be deemed included in the appropriate Contract Item or items, or if no specific item is provided therefor, as part of the overhead cost of the work, and no additional payment will be made, therefore.

1.09 PROTECTION OF WORK AND PUBLIC

A. The Contractor shall submit a Maintenance of Traffic (MOT) Plan based on the Uniform Traffic Control Manual. The MOT Plan must be approved by the Engineer.

B. Barriers and Lights:

1. During the prosecution of the work, the Contractor shall put up and maintain at all times such barriers and lights as will effectually prevent accidents.

2. The Contractor shall provide suitable barricades, red lights, "danger" or "caution" or

"street closed" signs and watchmen at all places where the work causes obstructions to the normal traffic or constitutes in any way a hazard to the public.

C. Smoke Prevention: The Contractor shall use hard coal, coke, oil or gas as fuel for equipment generating steam. A strict compliance with ordinances regulating the production and emission of smoke will be required.

D. Noise:

1. The Contractor shall eliminate noise to as great an extent as practicable at all times. Air compressing plants shall be equipped with silencers and the exhaust of all gasoline motors or other power equipment shall be provided with mufflers.

2. Except in the event of an emergency, no work shall be done between the hours of 5:00

P.M. and 7:00 A.M. Monday through Friday, on weekends and legal holidays without written permission of the County. If the proper and efficient prosecution of the work requires operations during the night or on weekends, the written permission of the County shall be obtained before starting such items of the work.

E. Access to Public Services: Neither the materials excavated nor the materials or plant used in the construction of the work shall be so placed as to prevent free access to all fire hydrants, valves or manholes.

F. Dust Prevention: The Contractor shall prevent dust nuisance from its operations or from traffic by keeping the roads and/or construction areas sprinkled with water at all times.

Exit Road Improvements 01000 - 11 March 2023

1.10 CUTTING AND PATCHING

A. The Contractor shall do all cutting, fitting or patching of its portion of the work that may be required to make the several parts thereof join and coordinate in a manner satisfactory to the Engineer and in accordance with the Drawings and Specifications.

B. The work must be done by competent personnel skilled in the trade required by the restoration.

C. Where existing pavement, curb, curb and gutter, sidewalk, or unpaved road is removed only for the purposes of constructing or removing culverts, pipes, etc., such pave, etc., shall be replaced and restored to as good condition, as determined by the Engineer, as before removal. The replaced pavement or unpaved road shall be the same or similar type as removed unless otherwise directed.

1.11 CLEANING

A. During Construction:

1. During construction of the work, the Contractor shall, at all times, keep the site of the work and adjacent premises as free from material, debris and rubbish as is practicable and shall remove the same from any portion of the site if, in the opinion of the County and Engineer, such material, debris, or rubbish constitutes a nuisance or is objectionable.

2. The Contractor shall remove from the site all of surplus materials and temporary structures used by the Contractor when no further need therefore develops. Contractor shall be responsible and liable for all spillage and incur all associated costs including, but not limited to, costs related to repair and maintenance resulting from damages thereof.

B. Final Cleaning:

1. At the conclusion of the work, all erection plant, tools, temporary structures and materials belonging to the Contractor shall be promptly taken away, and Contractor shall remove and promptly dispose of all water, dirt, rubbish or any other foreign substances.

2. The Contractor shall thoroughly clean all materials installed by Contractor and shall deliver such materials undamaged in a bright, clean, polished and new operation condition.

1.12 MISCELLANEOUS

A. Protection Against Siltation and Bank Erosion:

1. The Contractor shall arrange its operations and construct erosion control devices to minimize siltation and bank erosion on construction sites and on existing or proposed watercourse and drainage ditches.

Exit Road Improvements 01000 - 12 March 2023

2. At the Contractor’s own expense, Contractor shall remove any siltation deposits and correct any erosion problems as directed by the County, which results from Contractor's construction operations.

B. Protection of Wetland Areas:

1. The Contractor shall properly dispose of all surplus material, including soil, in accordance with local, State and federal regulations and Section 01010 Part 1.02 (A) of the Technical Specifications.

2. Under no circumstances shall surplus material be disposed of in wetland areas as defined by the Florida Department of Environmental Protection or U.S. Army Corps of Engineers.

C. Existing Facilities: The work shall be so conducted to maintain existing facilities in operation insofar as is possible. Requirements and schedules of operations for maintaining existing facilities in service during construction shall be as described in the Specific Provisions.

D. Use of Chemicals: All chemicals used during project construction or furnished for project operation, whether herbicide, pesticide, disinfection, polymer, reactant, or of other classification, must show approval of either EPA or USDA. Use of all such chemicals and disposal of residues shall be in strict conformance with instructions. Contractor must maintain a file on site of SDSs for above materials.

E. Cooperation With Other Contractors and Forces:

1. During progress of work under this Contract, it may be necessary for other contractors and persons employed by the County to work in or about the project.

2. The County reserves the right to put such other contractors to work and to afford such access to the site of the work to be performed hereunder at such times as the County deems proper.

3. The Contractor shall not impede or interfere with the work of such other contractors engaged in or about the work and shall so arrange and conduct work that such other contractors may complete their work at the earliest date possible.

F. Construction shall be conducted and shall result in construction of the improvements of this project in full accordance with the conditions of the permits granted for the project.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

\\file-server\data\working files\s2li projects\orange county\17-737-9 additional outbound scales\specifications\01000 - general requirements chh 3-2-23.doc

Exit Road Improvements 01000 - 13 March 2023

CONTRACTOR’S AFFIDAVIT VERIFYING ACCURACY

OF

DRAWINGS AND SPECIFICATIONS

(This Affidavit shall be submitted to the Engineer prior to the start of Construction)

STATE OF )

COUNTY OF )

The undersigned being first duly sworn as provided by law, deposes and certifies that:

1. The undersigned is authorized to make this Affidavit on behalf of, (Name of Corporation, Partnership, Individual, etc.)

A , formed under the laws of of which he/she is

(Sole Owner, Partner, President, etc.)

2. Prior to the start of work on the site, Affiant has carefully studied, reviewed, and compared the Drawings and Specifications and checked and verified all pertinent figures shown thereon and all applicable field measurements;

3. Affiant hereby verified that the Drawings and Specifications in the Contract Documents for the

(Project Name) accurately represent the existing site conditions and do not contain any conflicts, errors, ambiguities, or discrepancies except as specifically noted below.

4. Number of exceptions _____________ (if none, please indicate zero in the space provided). Each exception is explained in detail on the attached sheets. ____________ additional sheets are attached.

Affiant

BY: _____________________________

Sworn and subscribed before me this ____ day of ________________, 20___.

Notary Public

My Commission Expires:

END OF CONTRACTOR VERIFICATION FORM

Exit Road Improvements 01010 - 1

Orange County, Florida Revised May 2023

SECTION 01010

SUMMARY OF WORK

1.01 LOCATION OF WORK

A. Work included in this Contract will be performed at the Orange County Landfill, located at 5901

Young Pine Road in Orlando, Florida 32829. The Orange County Landfill is owned by the

Orange County Board of County Commissioners (County) and operated by the Orange

County Utilities Solid Waste Division.

1.02 DESCRIPTION OF WORK

A. The County has been experiencing long queuing lines of vehicles attempting to exit the landfill. The primary cause of the queuing lines is the presence of only a single exit lane and single outbound scale. The Work of this construction project, in general, is the construction of an additional outbound scale and new operator’s booth for this scale, refurbishment of the existing operator’s booth, and modifying the inbound and outbound traffic lanes, as shown on the plans. The Work includes furnishing all labor, materials, equipment, tools, transportation, services, incidentals, and performing all work necessary to construct a new outbound traffic lane and improve overall traffic movement on site consisting of:

• Providing a maintenance of traffic (MOT) plan and flagging personnel during construction activities.

• Since the modification of the roadways will cause additional traffic flow problems during construction, the County requires the additional outbound scale to be constructed first. This will allow a faster flow through of traffic during construction. The construction of a new outbound scale includes concrete ramps and curbs, washout slab, operator’s booth, barrier arm gate, guardrails and scale foundation. It also includes the installation of an electronic scoreboard and all necessary power and lighting.

• Replacement of the existing operator’s booth for the south scale, modifying the booth’s foundation and installation of all necessary power and lighting.

• Construction of a new roadway to the Class III landfill after exiting the inbound scales, as shown on the drawings.

• Contacting and coordinating with Duke Energy to relocate an existing power pole.

• Draw hydrant near outbound scales to be removed.

• Modifying and widening existing roadways near the scalehouse area to improve overall traffic movement, as shown on the plans. All new roadways will receive the installation of proper lane markings and signs.

• Stormwater improvements associated with the widening of existing roadways including construction of Florida Department of Transportation (FDOT) Type C ditch bottom inlets, 18-inch reinforced concrete pipes and FDOT cross drain mitered end sections, as shown on the plans.

Exit Road Improvements 01010 - 2

• Improvements to the scalehouse area including, construction of concrete tread and riser to the northwest corner of the scalehouse, removal of existing canopy roof, installation of new canopy roof to extend to the newly constructed outbound traffic lane, installation of new inbound operator’s booth, extension of existing concrete slab foundation at the inbound operator’s booth.

• Any millings, limerock, and soils excavated during the project shall stay onsite and be stockpiled at places indicated by the County.

The County has elected to split a portion of the work into two sperate bid alternatives in order to assess the costs upon receiving the bid and decide what Work will be included in this

Contract.

The Work of Bid Alternative 1, in general, is the construction of the area behind the Citizens

Drop-Off Area. The Work includes furnishing all labor, materials, equipment, tools, transportation, services, incidentals, and performing all work necessary to construct the area behind the Citizens Drop-Off Area consisting of:

• Construction of an additional exit lane from the Citizen’s Drop-off Area.

• Construction of roadway behind the Citizen’s Drop-off Area. All new roadways will receive the installation of proper lane markings and signs.

The Work of Bid Alternative 2, in general, is the construction of full depth shoulders on all new roadways and existing roadways to be modified. The Work includes furnishing all labor, materials, equipment, tools, transportation, services, incidentals, and performing all work necessary to construct full depth shoulders consisting of:

• Construction of full depth shoulders which includes installation of type B stabilization, limerock and Superpave asphalt concrete on all roadways.

All items shall be in place, and ready for operation and use by the County, in accordance with the Drawings and Specifications titled "Orange County Solid Waste Facility Exit Road

Improvements.”

The construction of the Orange County Landfill Entrance Road Improvements shall proceed in an orderly manner as to protect the materials placed. The Contractor shall block off the work area as to restrict it from ongoing landfill activities.

Insofar as the solid waste operations by the County are required to be ongoing during the construction period, the Contractor is required to sequence the work to eliminate interruption of the County's solid waste operations. To this end, at least two outbound lanes

(prior to the scale house) must be kept in operation at all times.

B. The Contractor shall complete all work described above and all other work incidental whether specifically mentioned or not in accordance with the Plan Drawings, Specifications, and

Contract Documents.

C. Work shall conform to the following Drawings that form a part of these Contract Documents.

Exit Road Improvements 01010 - 3

DWG. NO. TITLE

1 KEY SHEET

2 TOPOGRAPHIC SURVEY

3 OVERALL SITE LAYOUT

4-7 TYPICAL SECTIONS

8-10 ROADWAY PLAN

11-15 ROADWAY PLAN & PROFILE

16 DRAINAGE STRUCTURE CROSS SECTIONS

17-29 ROADWAY CROSS SECTIONS

30-31 TEMPORARY TRAFFIC CONTROL PLAN

32 SIGNING & MARKING PLAN

E0.0 ELECTRICAL GENERAL NOTES & SYMBOL LEGEND

E1.0 POWER AND LIGHTING PLAN

E2.0 PANEL SCHEDULE & RISER DIAGRAM

S0.1 STRUCTURAL GENERAL NOTES

S1.0 FOUNDATION PLAN

S2.0 STRUCTURAL DETAILS

S2.1 BUILDING SECTION

1.03 WORK BY COUNTY

A. County will continue to process waste through the active entrance road area. County will continue the use of the road that runs through the construction area. Therefore, the road must be kept open, and the Contractor is to furnish flagmen and/or all-weather bypass lanes when necessary.

B. If it is necessary in the course of operating the landfill for the Contractor to move its equipment and/or materials, they shall do so promptly and place that equipment and/or materials in an area that does not interfere with landfill operations.

C. Construction Quality Assurance (CQA): County will provide on-site inspection and quality assurance during construction. Quality Control procedures will involve construction observation of the material and equipment components. Some of the functions are as follows:

• Inspection of materials,

• Inspection of concrete slabs,

• Inspection of utility installation,

• Inspection of scale foundation and installation,

• Inspection operation booths foundation and installation,

• Inspection of canopy installation, and

• Inspection of electronic scoreboard installation

Contractor shall adhere to CQA procedures and work in cooperation with the County's and

Engineer’s representatives toward the successful completion of the project.

Exit Road Improvements 01010 - 4

1.04 WORK BY CONTRACTOR

A. The Contractor shall furnish all labor, materials, equipment, tools, services and incidentals to complete all of the work required as shown on the Drawings and specified.

B. The Contractor shall complete the work, in place, ready for continuous service, and shall include repairs, testing, permits, cleanup, replacements, and restoration required as a result of damages caused during construction.

C. All material, equipment, skills, tools, and labor which are reasonably and properly inferable and necessary for the proper completion of the work, in a substantial manner and in compliance with the requirements stated or implied by the Specifications or Drawings, shall be furnished and installed by the Contractor without additional compensation, whether specifically indicated in the Contract Documents or not.

D. The Contractor shall comply with all municipal, county, state, and federal laws, rules, guidelines, and codes, which are applicable to the work.

E. The Contractor will be responsible for any and all traffic control around the construction area including constructing any by-pass roads to avoid construction areas.

F. The Contractor shall maintain dust control on all roads used for access to construction and all construction areas.

CONTRACTOR USE OF SITE

A. Access to Site: Limited to public rights-of-way at the scalehouse facility. Work shall be performed so as to not block or hinder site access, except as authorized by the County.

B. Except in the event of special construction, no work shall be done between the hours of 5:00 p.m. and 7:00 a.m., Monday through Friday, weekends, and Orange County Holidays. If the proposed and efficient prosecution of the Work requires operations during the aforementioned non-working hours, the County’s permission shall be obtained 48 hours before starting such items of the work.

The Contractor is hereby informed and understands that normal working hours for the County’s

Resident Project Representative are 10 hours per day, 50 hours per week. If the Contractor plans to work more than 10 hours per day or 50 hours per week, written permission for any work beyond the normal operating hours for the Resident Project Representative is to be requested in writing 24 hours in advance. All compensation to the Resident Project Representative for working beyond the normal 50-hour weekly schedule is considered “overtime” compensation and shall be paid by the Contractor. The overtime rate for each Resident Project Representative is $150 per hour for each hour beyond 50 hours per week. The Resident Project Representative’s overtime compensation shall be processed as part of the final Change Order.

C. Construction Operations: Limited to entrance road area, Contractor’s storage and office areas, as noted on Drawings.

D. Limit Use of Landfill Property:

1. Allow use of active waste disposal areas by public and County including utilization of paved entrance roads and of waste processing areas.

2. Allow County activities for operation.

Exit Road Improvements 01010 - 5

E. Utility Outages and Shutdown: Prior approval by County and minimized in duration.

F. Safety Precautions

1. No smoking anywhere on the property.

2. Personal Protective Equipment (PPE) shall be worn at all times.

G. Observe regulations posted at the site entrance for disposal of materials and use of the facilities.

1.06 SITE CONDITIONS

A. The Contractor shall be responsible for having determined to his satisfaction, prior to the submission of his Bid, the conformation of the site, the types and quantities of materials to be encountered, the execution of the work, the general and local conditions and all other matters which can, in any way, affect the work under this Contract. No claim for extras based on existing site conditions will be allowed.

H:\S2Li Projects\Orange County\17-737-9 Additional Outbound Scales\Specifications\01010 - Summary of Work revised sbl chh 4-26-23 chh 5-11-23.doc

Exit Road Improvements 01025 - 1

SECTION 01025

MEASUREMENT AND PAYMENT

1.01 DESCRIPTION

A. The Contractor shall receive and accept the compensation provided in the Contract as full payment for furnishing all labor, equipment, and materials and for performing all construction/operations necessary to complete the Work as described in the Contract, and in full payment for all losses or damages incurred during the Work, for any discrepancies between actual and estimated quantities, or from any unanticipated difficulties which may arise during the Work until final acceptance by the County.

B. Payment for the various items on the Contractor’s Bid Form, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles and for all labor, operations, supervision, overhead, and profit, and incidentals appurtenant to the items of work being described as necessary to complete the various items of the Work all in accordance with the requirements of the Contract Documents, including all appurtenances thereto, and including all costs of compliance with the regulations of public agencies having jurisdiction, including Safety and Health Requirements of the Occupational

Safety and Health Administration (OSHA) of the U.S. Department of Labor.

C. No separate payment will be made for any item that is not specifically set forth on the Contractor’s

Bid Form and all costs, therefore, shall be included in the prices named on the Contractor’s Bid

Form for the various appurtenant items of work. Payment for complying with the safety requirements for construction on the work site shall be included in the contract unit price paid for the various items of work wherein it is required, and no separate payment will be made, therefore.

In addition, no separate payment shall be made for the following work, and all costs shall be included in appropriate payment item in the lump sum or unit price portion of the bid:

a. Construction of temporary structures during construction;

b. Cleaning stormwater inlets, culverts, and structures due to sediment or runoff from construction;

c. Hauling and disposal of construction waste material and site cleaning;

d. Traffic control activities;

e. Dust control;

f. Taxes, insurance, overhead and profit;

g. Project Schedule; and

h. All other work required and incidental to the Contract.

D. The total Bid Amount shall cover all work required by the Contract Documents. All costs in connection with the proper and successful completion of the Work, including furnishing all materials, equipment, supplies, and appurtenances; providing all construction equipment and tools; including all costs and expenses for taxes, commissions, transportation charges, and expenses, permit fees, patent fees, royalties, handling and tests; and performing all necessary labor and supervision to fully complete the Work shall be included in the bid. All work not specifically set forth as a pay item on the Contractor’s Bid Form shall be considered a subsidiary obligation of

Contractor and all costs in connection therewith shall be included in the lump sum price bid.

Exit Road Improvements 01025 - 2

E. There will be no payment for rejected or unused products. Payment will not be made for the following:

a. Loading, hauling, and disposing of rejected material;

b. Quantities of material wasted, eroded, washed away or disposed of in a manner not called for under Contract Documents;

c. Rejected loads of material, including material rejected after it has been placed by reason of the failure of Contractor to conform to provisions of Contract Documents;

d. Material not unloaded from transporting vehicle;

e. Failure to submit an updated progress schedule with pay application;

f. Defective work not accepted by the County;

g. Work performed without approved shop drawing;

h. Material remaining on hand after completion of work.

F. The Contractor shall be responsible for establishing contracts with its subcontractors, which have a measurement and payment in accordance with this Section. If the Contractor establishes a contract with its subcontractors, which conflicts with this Section, any additional cost incurred will be borne by the Contractor.

G. Partial Payment for Stored Materials and Equipment:

a. Partial Payment: No partial payments will be made for materials and equipment delivered or stored.

b. Final Payment: Will be made only for products incorporated in work and the product has been completed, tested and accepted by the County.

1.02 LUMP SUM

A. For lump-sum items, payments shall be made to the Contractor based on the Lump Sum Bid items in accordance with an accepted Schedule of Values based on actual work completed and accepted by the County at the time of partial payment request.

1.03 PAYMENT FOR INCREASED OR DECREASED QUANTITIES

A. The actual percentage of each lump sum bid item completed by the Contractor and accepted by the County at the final completion of the Project will be paid to the Contractor.

1.04 DELETED ITEMS

A. Should any items contained in the Bid Proposal be found unnecessary for the proper completion of the Work contracted, the Engineer may eliminate such items from the Contract. This action shall in no way invalidate the Contract and no financial allowance or compensating payment for anticipated profit, overhead, etc., will be made for items so eliminated in making final payment to the Contractor.

PART 2 - PRODUCTS (Not Used)

Exit Road Improvements 01025 - 3

PART 3 – EXECUTION

3.01 MEASUREMENT AND PAYMENT ITEMS

The descriptions provided in the following Paragraphs…