WPSP_Pool_Demolition_-_Scope_of_Work.pdf
PDF 139 KB Posted
- Solicitation number
- Event 32701-13628
- Issued by
- Sullivan County, Knoxville City, Tennessee
About this file
The document is a Scope of Work for a swimming pool removal project at Warriors Path State Park in Kingsport, Tennessee, issued by the Tennessee Facilities Management division. The project involves the complete demolition and removal of an existing swimming pool, including the filtration room, fencing, walkways, container walls, and associated infrastructure. The contractor will be responsible for excavating and filling the area, with specific requirements for fill material, compaction, and final grading. Work is to be completed between contract signing and June 1, 2025, during normal business hours (Monday through Friday, 8:00 a.m. to 4:30 p.m.), with potential for alternate scheduling with Facilities Management approval.
The project requires contractors to have an active Tennessee Building Contractor license (BC-B sm, BC-B, or BC-C) and submit a bid through the State of Tennessee's Edison system. Contractors must provide a Declaration of Intended Use of Subcontractor(s) form and ensure all subcontractors are properly licensed. The scope includes detailed demolition specifications, such as breaking up the concrete pool structure, removing metal components, pumping water to a retention pond, and final site restoration with topsoil and seeding. Additional requirements include maintaining site safety, protecting adjacent structures, and conducting a pre-construction conference and final inspection. The contractor must have a Certificate of Insurance and be registered with the Tennessee Department of Revenue.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SWIMMING POOL REMOVAL
WARRIORS PATH STATE PARK
490 HEMLOCK ROAD
KINGSPORT, TN 37663
This request for bids is for a contract to furnish all material, equipment, supplies, and labor necessary to remove existing swimming pool, filtration room, fencing, walkways, container walls, etc. and all excavation necessary to fill in all areas of removal.
General Conditions
1) On-Site work shall be performed between receipt of signed contract or purchase order and June 1, 2025, unless a written exception is granted by the Facilities Management
Regional Manager.
2) For this project, the Contractor and applicable subcontractors shall possess an active
BC-B sm, BC-B, or BC-C Tennessee Building Contractor license prior to submitting a bid.
Failure of the Contractor and applicable subcontractors to provide copies of their appropriate license shall result in the disqualification of the bid. All licenses shall be verified via Tennessee Commerce and Insurance database before project award.
3) The Contractor shall not assign this Contract or enter into a subcontract for this project without prior written approval of Facilities Management. The Contractor’s bid shall include a Declaration of Intended Use of Subcontractor(s) form that clearly states the intent to use a subcontractor, along with their name and license number. Facilities
Management reserves the right to reject a bid in whole or a subcontractor, based upon failure to possess an appropriate active TN builder’s license. After project award, any proposed substitution or addition of a subcontractor shall require written Facilities
Management acceptance and approval before being allowed on-site or perform any work under this contract. All subcontractors are required to have an active TN building contractor license for the applicable work to be performed before and throughout the project. Any proposed subcontractor failing to meet these requirements are not allowed to perform work on any portion of this project.
4) All work shall comply with state-approved versions of the IBC, standards, regulations, other applicable codes, manufacturer’s recommendation, and best practices. The
Contractor is responsible for all permits and associated fees.
5) All bids shall be submitted prior to the published event end date. The bids shall be submitted via the State of Tennessee’s online Edison system. Do not submit or disclose your bid to any other person.
6) Only the Facilities Management Project Manager or Facilities Management Regional
Manager can approve any alterations, modifications, and substitutions of the specifications or requirements of the project. No additional work shall be authorized unless pre-approved by either the Project Manager or Regional Manager in writing.
Park/Hospitality management and staff are not authorized to make any changes, deletions, or additions to the project or accept any portion of the work. This Contract shall be modified only by a written agreement signed by all parties. Any work performed outside of the written scope with any written change orders will be the responsibility of the Contractor or others and not Facilities Management. All questions, directives, and acceptance shall come only from either the Facilities Management
Regional Manager and/or Project Manager.
7) The Contractor shall keep the jobsite clean and safe and leave in a neat and tidy manner.
8) All color selections shall be provided to the Contractor by the Facilities Management
Project Manager.
9) All material substitutions must be pre-approved prior to bid acceptance.
10) All materials shall be installed per manufacturer’s recommendation, industry best practice, and applicable code.
11) All dimensions listed are approximate. The Contractor is solely responsible for verifying actual dimensions prior to ordering any materials or bidding. No allowances shall be made due to a bidder neglecting to visit the site and verifying dimensions and conditions.
12) All work performance under this Contract shall be under the full-time direction of the
Contractor. The Contractor shall be responsible for work and performance, and damages of any subcontractors and/or independent contractors or laborers hired in connection with the work under this Contract.
General Scope of Work
Description of Demolition and Associated Work
All debris shall be removed from the park property and disposed of in accordance with all applicable regulations, unless specifically noted.
1.The Contractor shall demo the pool structure, filtration room, any exterior tanks and designated concrete steps, walkways, concrete pads, and container walls; no pool supporting buildings shall be included and caution shall be taken to protect those structures. Any damage shall be the Contractor’s responsibility to repair.
2.The Contractor shall remove debris from state property and dispose of in an approved land fill.
3.The Contractor shall pump all water into a retention pond to allow sedimentation filtering. If necessary, the Contractor may construct on site by means of rock and sand.
4. The Contractor shall demo the pool liner by cutting into sections or using equipment to remove and load for disposal, If applicable.
5.The Contractor shall demo stainless steel skimmers, and any other metal found in pool demo site. This metal must be removed from State Park property and is up to Contractor’s disposal method.
6.The Contractor shall start in the deep end, 12-foot (twelve-foot), marked area breaking up shock crete (gunnite) floor and walls. Starting at this point the Contractor shall compact replacement fill dirt at 1-foot (one-foot) intervals with roller vibratory compacting. It shall be acceptable for the Contractor to break aggregate into pieces no more than 5-inches (five-inches) in size and add a layer of broken aggregate at 1-foot (one-foot) intervals. Each foot of fill soil shall have no more than 6-inches (six-inches) of broken aggregate added on top. There shall never be pieces of aggregate more than 5-inches (five-inches) in size added to fill and no aggregate shall be allowed that contains wire or rebar. Aggregate shall be used in the 12-foot (twelve-foot) end of the pool only. There shall be no aggregate fill within four feet of final grade.
8.The Contractor shall supply fill material of clay/sand mixture as needed to within 1-foot (one-foot) of grade. The Contractor shall supply and compact 1-foot (one-foot) of topsoil for final grade.
10.The Contractor shall demo pool deck including kiddie pool and deck 360 degrees (three hundred sixty degrees) around pool location. This includes concrete pad, foundations, anything associated with the pool that is underlying and any retaining walls, including the pool filter room under the pool deck and everything in filter room. All demoed concrete, block and brick shall be removed from park property and disposed of properly off site.
11.The Contractor shall demo the surge tank located by the 12 (twelve)-foot depth marker and water fill valve, if applicable. This shall include the concrete tank base. Tank is estimated to be 20 (twenty) feet deep (if applicable). All concrete shall be removed and disposed of offsite.
12.The Contractor shall cut and cap the water supply line by the entry point of the building or fence where it enters the pool compound.
13.The Contractor shall provide 1-foot (one-foot) of topsoil over the entire work site.
14. The Contractor shall demo the fence and fence post around pool site that have been marked for removal. Fence shall be left intact until final grading as job site security as much as possible. Any area of fence removal shall be replaced with 4 (four)-foot tall, orange, vinyl, safety fencing with post every 4 (four)-feet or less apart. Any post except for wood post shall be caped for safety.
15. The final graded surface of topsoil shall not have any dips that will hold water and shall be sloped to meet existing grades.
16. The Contractor shall Harley rake area before seeding and straw. Broadcasting shall be 25 (twenty-five) bales of straw, 20 (twenty) pounds of Kentucky 31 fescue grass seed and 20 (twenty) pounds of annual rye grass seed per acre over the entire site at completion of work.
Additional Terms and Conditions
1) All aspects of this job shall be left in a finished condition: All finish work, interior and exterior walls and trim, finish painting, caulking and final cleanup are included in this contract.
2) The Contractor shall be responsible for determining where all utilities are on the job site and care should be taken to protect the utilities from any damage caused by the demo/construction. This shall include any underground utilities around the job site area. If damage occurs, it shall be repaired within a 24-hour period from the time damage occurs.
3) The Contractor shall perform work on regular time and shall invoice work time and material not to exceed the quoted price. Any variance in quote shall be addressed only with a representative of the Facilities Management Regional Office before any additional work is undertaken or materials ordered.
4) Work shall be scheduled to avoid any interference with normal operation of the park as much as possible. During the construction period, coordinate construction schedules and operations with the park manager. Work shall be conducted during the normal business hours of Monday through Friday, 8:00 a.m. to 4:30 p.m., unless an alternate schedule is approved by Facilities Management.
5) The successful contractor shall schedule and attend a pre-construction conference where a pre-construction form shall be signed by Facilities Management, Contractor and Park Manager or park representative before work can begin. The Contractor shall also schedule and attend a final inspection where a final inspection form shall be signed by Facilities Management, Contractor and Park Manager or park representative before final invoice shall be paid.
6) The Contractor shall protect areas adjacent to his work and shall be required to repair any damage they may cause. The Contractor shall protect work of other trades. The
Contractor shall correct any painting related damage by cleaning, repairing, or replacing, and refinishing as directed by Facilities Management. The Contractor shall leave residences and other buildings in a habitable manner after hours by securing unfinished openings.
7) Workmanship shall be warrantied for not less than one year from date of final inspection. Materials shall be warrantied as per manufacturer’s warranty.
8) Unless otherwise indicated, all materials, equipment, and supplies shall be new and in good condition, UL listed when applicable, and all work accomplished in a manner acceptable to Facilities Management.
9) Clean up of the project site shall be the responsibility of the Contractor. The Contractor shall assure that job site is clean of nails, debris, etc., at end of each day to ensure safety. The Contractor shall clean up and haul away all scrap when work is completed to an approved location off state property.
10) The Contractor, employees, and sub-contractors shall be licensed, certified, or registered as required. They shall be registered in the State of Tennessee Edison purchasing system.
11) The State of Tennessee shall not be held liable for any damage, loss of property, or injury of personnel resulting from actions of the Contractor and/or his/her sub-contractors or employees.
12) At all times, the Contractor shall have a copy of project specifications, permits, and certificate of insurance on-site.
13) Facilities Management may terminate this Contract for convenience without cause and for any reason. Facilities Management shall give the Contractor at least thirty (30) days written notice before the termination date. The Contractor shall be entitled to compensation for all conforming goods delivered and accepted by the Facilities
Management or for satisfactory, authorized services completed as of the termination date. In no event shall the State be liable to the Contractor for compensation for any goods neither requested nor accepted by the Facilities Management or for any services neither requested by Facilities Management nor satisfactorily performed by the
Contractor. In no event shall the State's exercise of its right to terminate this Contract for convenience relieve the Contractor of any liability to the State for any damages or claims arising under this Contract.
14) If the Contractor fails to properly perform its obligations under this contract in a timely or proper manner, or if the Contractor materially violates any terms of this contract, the
State shall have the right to immediately terminate the Contract and withhold payments in excess of compensation for completed services or provided goods. Notwithstanding the above, the contractor shall not be relieved of liability to the State for damages sustained by virtue of any Breach Condition and the State may seek other remedies allowed at law or in equity for breach of this Contract.
15) Notwithstanding any use of the approved subcontractors, the Contractor shall be the prime Contractor and responsible for compliance with all terms and conditions. The
State reserves the right to request additional information or impose additional terms and conditions before approving an assignment of this contract in whole or in part or the use of subcontractors in fulfilling the Contractor's obligations under this Contract.
16) The Contractors and all subcontractors are not authorized to day laborers or temporary labor on this project without the express written permission of Facilities Management.
17) The Contractor shall have a Certificate of Insurance on file with Facilities Management and in compliance with state regulations. The Contractor shall have insurance as shall protect the Contractor from claims which may arise out of or result from the
Contractor’s operations under the contract and for which the Contractor may be held legally liable, whether such operations be by the Contractor or by sub-contractor or by anyone directly or indirectly employed by any of them, or anyone associated with them for whose acts they may be liable. Sub-contractors shall also be registered in the State of Tennessee Edison purchasing system, be listed on the bid application, submit copy of applicable license, and shall show proof of insurance and have workers compensation.
18) Note: Before the Contract resulting from this Invitation to Bid is signed, the apparent successful proposer shall be registered with the Department of Revenue for the collection of Tennessee sales and use tax. The State shall not approve a contract unless the proposer provides proof of such registration. The foregoing is a mandatory requirement of an award of a contract pursuant to this solicitation.
19) Invoice shall be submitted for payment not before project completion and final project acceptance but also no later than 10 days after project completion and acceptance. A copy of the invoice shall be submitted to: Deborah.g.smith@tn.gov.
20) Facilities Management Regional Contacts for this project are:
Regional Manager: Chad Young, 865-606-1551, chad.young@tn.gov
Project Manager: Doug Stephens, 865-221-2633, doug.stephens@tn.gov
Nothing follows mailto:Deborah.g.smith@tn.gov mailto:chad.young@tn.gov mailto:doug.stephens@tn.gov
File details come from the government source that posted it. Updated .