This document is a Work Restrictions section from a Construction Bid Set for an HVAC Repair project at Building 208 for the 911th Airlift Wing. The document outlines specific requirements and limitations for contractors working on-site, including work hours (0700 to 1600 Monday through Friday), prohibitions on working during federal holidays and UTA training weekends (typically first and third weekends of each month), and strict guidelines for site access and operations. Contractors must coordinate with the Contracting Officer, confine work to designated areas, keep driveways and entrances clear, and minimize interference with 911th Airlift Wing operations, noting that a portion of the building pertaining to Simulator operations will remain occupied during construction.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
911th AIRLIFT WING WORK RESTRICTIONS
01 14 00 - 1
JLSS 25-9991AMC
HVAC Repair, BLDG 208
Construction Bid Set
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES
A. Coordinate use of premises under direction of Contracting Officer. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated. Cooperate with 911th Airlift Wing personnel during construction operations to minimize conflicts and facilitate 911th Airlift Wing usage. The contractor shall assume that the building will be occupied during normal work hours and on UTA weekends.
1. Limits: Confine construction to areas indicated on construction drawings and/or as designated by the Contracting Officer. Confine storage area as designated by the Contracting Officer.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to 911th Airlift Wing employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Perform the work so as not to interfere with 911th Airlift Wing operations.
4. Building Occupancy During Construction:
a. A portion of the building pertinent to the Simulator operation will be occupied.
Maintain life safety systems and egress for occupied building areas.
b. Areas for AGE activities will not be occupied.
B. Assume full responsibility for protection and safekeeping of products under this Contract.
C. Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:
1. Normal work hours shall be between 0700 to 1600 (7:00 AM to 4:00 PM), Monday through Friday, with no work on federal holidays.
2. Any deviations from the normal working hours must be approved 3 working days in advance by the Contracting Officer.
911th AIRLIFT WING WORK RESTRICTIONS
01 14 00 - 2
JLSS 25-9991AMC
HVAC Repair, BLDG 208
Construction Bid Set
D. The Contractor shall be responsible for protecting all remaining permanent equipment.
E. Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.
F. Obtain and pay for use of additional storage or work areas needed for operations under this contract.
G. Comfort stations are not provided by 911th Airlift Wing.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
END OF SECTION