Wimbee Creek Trestle Demolition - IFB #060426
This is an Invitation for Bid (IFB) issued by Beaufort County Procurement Services for the complete demolition and removal of the Wimbee Creek train trestle fishing pier located at the Wimbee Creek Boat Landing in Dale, South Carolina. The scope of work includes demolition and disposal of seven timber pile bents, one reinforced concrete and steel pile bent, the plate girder superstructure, concrete and timber deck, pedestrian stairs, and installation of new six-foot-high chain link fencing with barbed wire across the exposed grade drop-off. Work must be completed within 120 calendar days following the Notice to Proceed, with operations limited to 7:30 a.m. to 5:00 p.m., Monday through Friday, unless advance written approval is obtained. A non-mandatory pre-bid conference will be held on May 14, 2026, at 2:00 p.m. via Microsoft Teams, with contractor questions due by 5:00 p.m. on May 21, 2026. A non-mandatory site visit is scheduled for May 20, 2026, at 10:00 a.m. at 44 Briars Creek Road, Seabrook, South Carolina. Sealed bids must be submitted electronically through the Procurement Portal by 3:00 p.m. Eastern Standard Time on June 4, 2026. The contract will be awarded to the lowest responsible and responsive bidder within ninety days of bid opening.
Bidders must submit a bid bond equal to five percent of the total bid amount, with the successful contractor required to furnish 100 percent Performance and Payment Bonds within fourteen days of receiving the Notice of Award. No specific budget or contract value is disclosed in the solicitation. Contractors must comply with OSHA standards, U.S. Army Corps of Engineers safety requirements, and environmental regulations, including development of a waste management plan within fifteen days of Notice to Proceed. The solicitation includes mandatory Small and Minority Business Enterprise (S/MBE) participation requirements with pre-award good faith efforts and post-award monthly compliance reporting. Insurance requirements include Worker's Compensation, Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Comprehensive Automobile Liability ($500,000), and Umbrella Liability ($2,000,000). Contractors must comply with Title VI of the Civil Rights Act of 1964 and are responsible for securing and paying for all necessary local, state, and federal permits and licenses; however, Beaufort County will waive its permit fees only. Liquidated damages are assessed at $600 per calendar day for schedule delays. No incumbent contractor is identified, and payment will be made on a percentage-complete basis with monthly invoices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID DOCUMENTS
WIMBEE CREEK TRESTLE DEMOLITION
IFB # 060426
Prepared By: Beaufort County Procurement Services
Dated: Thursday, April 30, 2026
Proposal Due Date: Thursday, June 4, 2026, 3:00 pm (EST)
IFB #060426 DOCUMENTS Page 2
IMPORTANT ELECTRONIC SUBMITTAL REQUIREMENTS
Response submittals for this Invitation For Bid will ONLY be received electronically and must be submitted ONLINE, through the Procurement Portal, no later than 3:00 pm on Thursday, June 4, 2026.
All responses must adhere to the following guidelines:
• Suppliers are encouraged to submit responses as soon as possible. Responses are received through our secure Procurement Portal and cannot be opened prior to the due date and time. The time and date of receipt as recorded by the server will serve as the official time of receipt. The County is not responsible for late submissions, regardless of the reason.
• All requested information and forms MUST be uploaded as indicated in the
PROPOSAL SUBMITTAL Section. If you have a problem with your submittal, you may contact Support through the Procurement Portal.
TITLE VI STATEMENT
COUNTY COUNCIL OF BEAUFORT COUNTY
Title VI Statement to Prime Contractors, Subcontractors, Architects, Engineers, and
Consultants
It is the policy of the County Council of Beaufort County, South Carolina, hereafter referred to as
“Beaufort County” or “the County”, to comply with Title VI of the 1964 Civil Rights Act (Title
VI) and its related statutes. To this end, Beaufort County assures that no person shall be excluded from participation in, denied the benefit of, or subjected to discrimination under any of its programs or activities on the basis of race, color, national origin, age, sex, disability, religion, or language regardless of whether those programs and activities are Federally funded or not. The
County is also committed to assuring every effort will be made to prevent the discrimination of low-income and minority populations as a result of any impact of its programs or activities. Beaufort County also assures that every effort will be made to prevent discrimination through the impacts of its programs, policies, and activities on minority and low-income populations. Additionally, the County will take reasonable steps to provide meaningful access to services for persons with limited English proficiency. In addition, Beaufort County will not retaliate against any person who complains of discrimination or who participates in an investigation of discrimination. Beaufort County will, where necessary and appropriate, revise, update, and incorporate nondiscrimination requirements into appropriate documents, directives, and regulations.
https://procurement.opengov.com/portal/bcgov/projects/260491/document?section=undefined
IFB #060426 DOCUMENTS Page 3
Pursuant to Title VI requirements, any entity that enters into a contract with Beaufort County including, but not limited to Prime Contractors, Subcontractors, Architects, Engineers, and
Consultants, may not discriminate on the basis of race, color, national origin, age, sex, disability, religion, or language in their selection and retention of first-tier subcontractors, and first-tier subcontractors may not discriminate in their election and retention of second-tier subcontractors, including those who supply materials and/or lease equipment. Further, Contractors may not discriminate in their employment practices in connection with highway construction projects or other projects assisted by the U.S. Department of Transportation (USDOT) and/or the Federal
Highway Administration (FHWA).
In all solicitations either by competitive bidding or negotiation made by the Contractor for work to Beaufort County to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor or supplier shall be notified by the Contractor of the Contractor's obligations under the contract and the Title VI regulations relative to nondiscrimination on the basis of race, color, national origin, age, sex, disability, religion, or language by providing such a statement in its bidding and contract documents.
Upon request, the Contractor shall provide all information and reports required by Title VI requirements issued pursuant thereto, and shall permit access to its books, records, accounts and other sources of information, and its facilities as may be determined by Beaufort County, USDOT, and/or FHWA to be pertinent to ascertain compliance with such regulations, orders, and instructions. Where any information required of a Contractor is in the exclusive possession of another who fails or refuses to furnish this information, the Contractor shall so certify to USDOT or FHWA, as appropriate and via Beaufort County, and shall set forth what efforts it has made to obtain the information. In the event of the Contractor's non-compliance with nondiscrimination provisions of this contract, USDOT may impose such contract sanctions as it or FHWA may determine to be appropriate, including, but not limited to:
• Withholding of payments to the Contractor under the contract until the Contractor complies, and/or
• Cancellation, termination, or suspension of the contract, in whole or in part.
In the event a Contractor becomes involved in, or is threatened with, litigation with a subcontractor or supplier as a result of this direction to comply with Title VI, the Contractor may request USDOT to enter into such litigation to protect the interests of USDOT and FHWA. Additionally, the
Contractor may request the United States to enter into such litigation to protect the interests of the
United States. Any person or Subcontractor who believes that they have been subjected to an unlawful discriminatory practice under Title VI has a right to file a formal complaint within one hundred eighty (180) days following the alleged discriminatory action. Any such complaint must be filed in writing or in person:
Beaufort County Government Post Office Drawer 1228 | Beaufort, SC 29901-1228
843-255-2304 Telephone | E-mail: dthomas@bcgov.net mailto:dthomas@bcgov.net
IFB #060426 DOCUMENTS Page 4
IFB #060426 DOCUMENTS Page 5
INVITATION FOR BID
Dates Advertised: April 30, 2026
This is a Formal Sealed Bid
We require Bids to be Electronically submitted through the Procurement Portal. Please go to https://procurement.opengov.com/portal/bcgov and sign up to submit your bid.
BIDS WILL BE RECEIVED UNTIL 3:00 pm LOCAL TIME ON Thursday, June 4, 2026.
Bid Title: Wimbee Creek Trestle Demolition Bid No: 060426
PREBID CONFERENCE: A Pre-Bid conference will be held on Thursday, May 14, 2026 at 2:00 pm p.m. virtually through Teams. This is a Non-Mandatory meeting; all interested bidders and subcontractors are encouraged to attend. Teams: Please email gmurray@bcgov.net for TEAMS invitation.
All questions must be submitted through the Procurement Portal no later than 5:00 pm on
Thursday, May 21, 2026.
A Bid Tabulation Will Be Posted On The Procurement Portal After Bid Opening.
BID ACCEPTANCE AND DELIVERY (Prices bid must be firm for a minimum of 90 Days). In compliance with the Invitation, and subject to all conditions thereof, the Offeror agrees, if this bid is accepted within (90) days from date of opening, to furnish any or all items quoted on at prices as set forth after the item and to make delivery within 90 Days after receipt of order with transportation cost included and prepaid. Unless otherwise stated and accepted herein, the Offeror agrees to complete this proposed contract in less than thirty (30) calendar days after issue date of purchase order.
I M P O R T A N T
IF YOU CONSIDER THESE SPECIFICATIONS AS RESTRICTIVE, SEE GENERAL
PROVISIONS, PARAGRAPH #20, DISCREPANCIES.
Bids received after the time specified for opening cannot be considered.
https://procurement.opengov.com/portal/bcgov
IFB #060426 DOCUMENTS Page 6
BID INVITATION
Wimbee Creek Trestle Demolition 060426
Sealed bids submitted through the Procurement Portal will be received electronically until 3:00 pm on Thursday, June 4, 2026 at which time responses to this request will be recorded in the presence of one or more witnesses in the Procurement Services Department. A Bid Tab will be posted on the Procurement Portal for:
Wimbee Creek Trestle Demolition
A PRE-BID conference will be held on Thursday, May 14, 2026 at 2:00 pm p.m. virtually through TEAMS This is a Non-Mandatory meeting; all interested bidders are encouraged to attend. TEAMS: Please email gmurray@bcgov.net for TEAMS invitation.
Bid documents are available through the Procurement Portal at https://procurement.opengov.com/portal/bcgov.
Beaufort County reserves the right to reject all proposals and to waive minor informalities and irregularities.
All Bids shall be accompanied by a Bid Bond drawn in favor of the Beaufort County Treasurer of Beaufort County, Beaufort, South Carolina, in the amount of at least five percent (5%) of the bid for the complete work: such Bid Bond representing that the Bidder, if awarded a contract, will promptly enter into a contract and furnish Performance Bond and Payment Bond as provided by law and approved by the attorney for Beaufort County, South Carolina. Each bond shall be equal one hundred percent (100%) of the contract amount. A copy of the Bid Bond or Certified
Check must be electronically sent with your bid documents through the Procurement Portal, as indicated in the Vendor Questionnaire Section. The original Bid Bond or Certified Check must be received by the Procurement Services Department within 10 days after the bid due date.
Failure on the bidder’s part to provide a copy of the Bid Bond or Certified Check by the Bid closing date and time will be considered as a nonresponsive bid and rejected by the County. The
Bid Bond shall be forfeited to the County Council of Beaufort County, South Carolina as liquidated damages if the Bidder fails to execute the contract and provide Performance and
Payment Bonds within fourteen (14) days after being notified that he has been awarded the
Contract.
The successful bidder shall secure and pay for necessary approvals, permits, assessments, and changes required for the construction and installation of this project as required by local, state, and federal regulations. County permits shall be required as applicable, but the fee shall be waived.
This waiver shall apply to the Beaufort County permit fee only and not to any "City or Town" permit fee and/or licenses, when applicable.
https://procurement.opengov.com/portal/bcgov
IFB #060426 DOCUMENTS Page 7
Bidders must comply with Title VI of the Civil Rights Act of 1964, the Anti-Kickback Act, the
Contract Work Hour Standard Act, and the National Occupational Safety and Health Act of
1970.
Bidders must certify that they do not and will not maintain or provide for their employees any facilities, which are segregated on the basis of race, color, creed, or national origin.
The Beaufort County Council reserves the right to reject all Bids and waive any formalities. Any claims for cost incurred by any bidders in preparation of any part of, or total package for this project will not be handled for reimbursement by Beaufort County or their representatives.
The Bidding Documents consist of the following, including all addenda issued there with and forms referenced therein, in addition to the drawings:
1. Bid Documents
2. Contract
3. General Conditions
4. Supplemental Conditions
5. General Provisions
6. Special Provisions
7. Specifications
Bid opening will be held at the Procurement Services Department. There will be no Public Bid
Opening. A Bid Tabulation will be posted on the Procurement Portal.
SCOPE OF WORK
Non-Mandatory Site visit to be held on at 10AM on 5/20/26 at 44 Briars Creek Rd Seabrook SC
29940
Work Covered by Contract Documents
The work of the Project is defined by the Contract Documents and primarily includes, but is not limited to:
1. Demolition and disposal of 7 timber pile bents
2. Demolition and disposal of 1 reinforced concrete and steel pile bent
3. Demolition of plate girder superstructure
4. Demolition of concrete and timber deck
5. Demolition of pedestrian stairs
IFB #060426 DOCUMENTS Page 8
6. Installation of new chain link fence. Fencing is to be 6’ high standard chain link fencing across the exposed grade drop off and extending 4’ to either side. Three strand standard barbed wire is to be included across the top of the entire fence.
Work Restrictions
Work Restrictions, General: Comply with restrictions on demolition operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
2. B. On-Site Work Hours: Limit work to normal business working hours of 7:30 a.m. to
5:00 p.m., Monday through Friday, unless otherwise indicated.
A. Submit request to the Owner at least 72 hours in advance for permission to work outside the normal working hours or on Saturdays, Sundays, or federal holidays.
B. Existing Utility Interruptions:
a. 1. Submit request to the Owner at least 72 hours in advance of any utility interruptions.
b. 2. Obtain Owner's written permission before proceeding with any utility interruptions. D. Take action to prevent the spread of construction dust, debris, and fumes at all times. Submit a demolition waste control plan prior to work.
c. Sanitation Facilities: The Contractor shall provide temporary toilet, wash facilities, and drinking water for use by Contractor's personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
Safety Precautions
These construction documents and the construction work hereby contemplated shall be governed at all times by applicable provisions of federal regulations, including, but not limited to, the current edition, with the latest amendments of the following:
1. William-Steiger Occupational Safety and Health Act of 1970, Public Law 91-596; Part
1926 - Occupational Safety and Health Standards, Chapter XVII of Title 29, Code of
Federal Regulations (29 CFR Part 1926).
2. B. The Contractor shall notify the local fire department at least 24 hours prior to the start of any demolition practices which may affect or impair any fire protection system or which may present a fire hazard (i.e., sanding, welding, grinding, applying hot tar, burning and utilizing of any flame producing device).
IFB #060426 DOCUMENTS Page 9
A. 1. The Contractor shall have and maintain an appropriate functioning fire extinguisher in the work area, for the type of work being done and the materials present. The
Contractor shall comply with OSHA, NFPA, and other local safety regulations.
B. C. The Contractor shall determine and employ all necessary safety precautions to protect the general public and Contractor or Subcontractor personnel during construction operations.
C. D. The Contractor shall coordinate closure of the facility with the Beaufort County
Public Work
Site Maintenance
The Contractor shall perform daily clean-up of work site, dumpsters and storage area. All dumpsters shall be covered and watertight.
B. The Contractor shall also protect existing plants, shrubs, fences, and structures within the demolition area
Construction Waste Management and Disposal
*It is known to the County that there is Creosote present. It will be the contractor's responsibility to remove of creosote and dispose of it properly. Due to the age of the structure it is assumed that any paint on the metal materials contains lead and the contractor is expected to treat it as such and dispose of properly according to SC DES standards.
1.0 SUMMARY A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous and regulated, demolition and construction waste.
3. Disposing of nonhazardous and regulated, demolition and construction waste.
B. The Contractor is responsible for complying with all Federal, State, and local environmental laws and requirements in the execution of this contract.
1.1 DEFINITIONS A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations.
Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
D. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
IFB #060426 DOCUMENTS Page 10
E. Salvage: Recovery of demolition or construction materials and deliver them to the Owner ready for reuse. F. Salvage and Reuse: Recovery of demolition or construction materials, prepare them for reuse, and subsequent incorporation into the work.
1.2 HAZARDOUS WASTE OPERATIONS
A. Contractors whose employees are exposed to hazardous waste, respond to emergencies involving hazardous materials, or participate in any cleanup or investigation of a government identified uncontrolled waste site, must follow all the requirements of 29 CFR 1910.120 which includes Site Safety and Health Plans, Emergency Contingency Plans and proper employee training. The Contractor, if required by 29 CFR 1910.120, shall submit to the Owner prior to performing the work, the Site Safety and Health Plans, Emergency Contingency Plans and proof of adequate worker training.
1.3 HAZARDOUS MATERIALS
A. The Contractor shall submit to the Engineer a copy of the Contractor's OSHA-approved hazardous communication program as required by 29 CFR 1910.1200.
B. The Contractor shall submit to the Engineer a copy of all Material Safety Data Sheets
(MSDS) for each chemical or hazardous material to be used in the execution of this contract.
C. The Owner, upon review of the Contractor's MSDS, has the right to deny the Contractor the use of chemicals or products which, in the Owner's judgment, pose an undue health risk, cause the generation or potential generation of hazardous waste, or result in the generation of other regulated wastes including wastewaters and air emissions.
D. The Contractor shall have proper secondary containment for storage of all liquid hazardous materials at the work site. This secondary containment shall be capable of containing 10% of the volume of all containers or 100% of the volume of the largest container whichever volume is the greater.
1.4 PERFORMANCE REQUIREMENTS
A. General: Practice efficient waste management in the use of materials in the course of the
Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials.
1.5 WASTE GENERATION
A. The Contractor shall be responsible for the proper management and collection of all wastes generated·. ·
B. The Contractor shall provide waste collection containers for all wastes generated that include unregulated trash, regulated wastes (construction debris, unusable excavated materials; and recyclable used oil), hazardous wastes, and wastewaters that cannot be discharged. The
Contractor shall submit to the Engineer copies of all weight tickets from the disposal of waste.
All waste shall be disposed of in permitted landfills, recycling, or treatment facilities.
IFB #060426 DOCUMENTS Page 11
C. All regulated waste generated by the Contractor shall be managed in accordance with all
State, Federal and local agencies having jurisdiction. '
D. All hazardous waste or potentially hazardous waste generated by the Contractor shall be managed in accordance with all Resource Conservation and Recovery Act (RCRA 40 CFR 260 -
266, 268 and 270), and other State and local agencies having jurisdiction. The Contractor shall be responsible for the proper collection and management of all hazardous waste.
E. The Contractor shall not discharge wastewater to any sewer, sanitary or storm, or into waterways.
1.6 SPILLS AND RELEASES
A. The Contractor shall be responsible for, and shall pay all costs for the cleanup and the disposal of wastes from any spills or releases of any hazardous materials (including all wastes) to the environment.
B. If the Contractor is performing a spill cleanup, the Contractor shall perform the cleanup in a manner that complies with applicable federal, state, and local laws and requirements.
1.7 ABATEMENT OF AIR POLLUTION
A. The Contractor shall comply with all federal, state, and local air pollution regulations.
B. The Contractor shall not release any chlorofluorocarbons (CFCs) to the environment when executing this contract.
1.8 SUBMITTALS
A Waste Management Plan: Submit plan within (15) fifteen days of date established for the
Notice to Proceed.
B. Recycling and Processing Facility Records if applicable: Indicate weight, receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them.
C. Landfill and Incinerator Disposal Records: Indicate weight, receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
D. OSHA-Approved hazardous communication program, site safety plan, emergency plans.
Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.
1.9 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
1.10 WASTE MANAGEMENT PLAN
IFB #060426 DOCUMENTS Page 12
A. General: Develop a waste management plan according to ASTM E 1609 and requirements in this Section. Plan shall consist of waste identification and waste reduction work plan.
B. Waste Identification: Indicate anticipated types and quantities of salvage, recycling, and construction waste generated by the work.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, quantity for each means of recovery, and handling and transportation procedures.
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this
Project, describe methods for preparing salvaged materials before incorporation into the
Work.
2. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept.
3. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
D. Waste Management Report: Provide a final report at the end of the project. Report shall consist of actual quantities by weight of waste salvaged, recycled, disposed of in landfill or incinerator.
PART 2- PRODUCTS (Not Used)
PART 3 - EXECUTION 3.1 PLAN IMPLEMENTATION
A. General: Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract. B.
Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, and disposal.
3.2 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements.
IFB #060426 DOCUMENTS Page 13
C. Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project site.
2.Remove recyclable waste from Owner's property and transport to recycling receiver or processor.
3.3 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Remove waste materials from Owner's property and legally dispose of or recycle them.
D. Do not discard trash or construction debris into waterways
Demolition
PART 1 GENERAL This section details the requirements for removal of the Wimbee Creek
Fishing Pier.
1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
A. U.S. ARMY CORPS OF ENGINEERS (USACE) B. EM 385-1-1 (2008; Change 1-2010;
Change 3-2010; Errata 1-2010) Safety and Health Requirements Manual
1.2 GENERAL REQUIREMENTS Do not begin demolition until authorization is received from the Engineer. Remove rubbish and debris from the project site; do not allow accumulations. The work includes demolition and removal of resulting rubbish and debris. Remove rubbish and debris from Owner's property daily, unless otherwise directed. Materials that cannot be removed daily shall be stored in areas specified by the Owner. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.
1.3 SUBMITTALS Waste Certificates, Demolition Plan
IFB #060426 DOCUMENTS Page 14
1.4 REGULATORY AND SAFETY REQUIREMENTS Comply with Federal, State, and local hauling and disposal regulations.
1.5 DUST AND DEBRIS CONTROL Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
1.6 PROTECTION
A. Traffic Control Signs Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Engineer prior to beginning such work.
B. Boat Landing Contractor shall not impede boating operations or damage existing boat landing. Boat landing closure will be at the discretion of the Public Works Director in consultation with the contractor. Public Safety is to be the primary concern.
C. Existing Work Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing work showing the condition of structures and other facilities adjacent to areas of alteration or removal. Digital photographs with a photo log submitted on a CD will be acceptable as a record of existing conditions. Include in the description the location and extent of cracks and other damage and description of surface conditions that exist prior to starting work.
D. Items to Remain in Place Take necessary precautions to avoid damage to existing items to remain in place. Repair or replace damaged items as approved by the Engineer. Coordinate the work of this section with all other work indicated. Ensure that structural elements are not overloaded.
E. Existing Construction Do not disturb existing construction beyond the extent .indicated or necessary for installation of new construction. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
F. Utility Service Maintain existing utilities to stay in service and protect against damage during demolition operations.
G. Protection of Personnel Before, during and after the demolition work the Contractor shall continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the demolition site.
1.7 BURNING The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.8 REQUIRED DATA The Demolition plan shall include procedures for careful removal and disposition of materials coordination with other work in progress, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. The demolition plan shall clearly identify the disposal facility receiving all waste.
IFB #060426 DOCUMENTS Page 15
1.9 ENVIRONMENTAL PROTECTION Comply with the Environmental Protection Agency requirements specified.
1.10 USE OF EXPLOSIVES Use of explosives will not be permitted.
PART 2 PRODUCTS Not Used.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED OR/AND SALVAGED A. Structures to be
Removed Existing structures contain treated timber that require disposal. All structures indicated for removal shall be removed as indicated in the drawings, taking care not to leave any debris on the river bed or concrete boat landing.
1. Seven Timber Pile Bents
2. One Steel Pile and Reinforced Concrete Bent
3. Plate Girder Superstructure
4. Pedestrian Stairs
Deck and Railing
B. Structures to be Salvaged
Existing Abutment
3.2 DISPOSITION OF MATERIAL
3.2.1 Title to Materials All materials and equipment designated for demolition shall become the property of the Contractor and shall be removed from Owner's property. All materials and equipment designated as salvage shall be moved to a location designated by the Owner.
3.3 CLEANUP A. Cleanup of Site Debris shall be removed and transported in a manner that prevents spillage on streets or adjacent areas. Contractor shall verify that the boat ramp is free from debris and obstructions from demolition and salvage work. Contractor shall follow all local regulations regarding hauling and disposal.
3.4 DISPOSAL OF REMOVED MATERIALS
A. Regulation of Removed Materials Dispose of debris, rubbish, scrap, and other non-salvageable materials resulting from removal operations shall comply with all applicable federal, state and local regulations as contractually specified off site. Removed materials shall not be stored on the project site. Comply with Section 017419 - CONSTRUCTION WASTE
MANAGEMENT AND DISPOSAL.
B. Removal from Owner's Property Transport waste materials removed from demolished structures from Owner's property for legal disposal.
IFB #060426 DOCUMENTS Page 16
3.5 REUSE OF SALVAGED ITEMS Replace items damaged during removal and salvage operations or restore them as directed by the Engineer prior to reuse.
3.6 DEMOLITION VERIFICATION
A. Contractor shall conduct pre and post demolition side scan sonar surveys of the site. Side scan sonar information shall extend 50 ft outside of the perimeter of the existing pier. Sonar information shall be georeferenced. Sonar information shall identify any materials that extend more than 1 ft off of the existing channel bottom. Submit side scan sonar information to engineer prior to demobilizing from project site.
SMALL AND MINORITY BUSINESS PARTICIPATION
PLEASE REVIEW THIS SECTION CAREFULLY, PAYING PARTICULAR
ATTENTION TO “PRE-AWARD DOCUMENTS” DUE WITH THE BID/PROPOSAL,
THE “GOOD FAITH EFFORTS CHECKLIST”, AND EXHIBITS 1-3.
FAILURE TO FOLLOW THE PROGRAM REQUIREMENTS AND/OR FURNISH THE
REQUESTED DOCUMENTS MAY RESULT IN THE REJECTION OF YOUR
BID/PROPOSAL.
PRE-AWARD DOCUMENTS
Item/Form SubmissionRequirements
1 Program Overview n/a
2 Self-Performance Affidavit Indicates intention to perform work and/or provide services with own current workforce.
Due with bid/proposal only if self-performing
100%.
3 Good Faith Efforts Checklist
Indicates the actions undertook to recruit and solicit small and minority businesses for this project.
Due with bid/proposal.
4 Good Faith Agencies Distribution List
Indicates agencies that should receive notice of solicitation to small and minority businesses for this project.
Copy of notice sent to good faith agencies due with bid/proposal.
5 Outreach Written Notice Example
Sample of notice to be sent to small and minority businesses soliciting their participation for this project.
Copy of notice sent to small and minority businesses due with bid/proposal.
IFB #060426 DOCUMENTS Page 17
6 Non-Discrimination Statement – Exhibit 1
Certification that this project is open to all businesses and persons and that no business or person shall be excluded from participating in the Beaufort County procurement process.
Due with bid/proposal.
7 Outreach Documentation Log – Exhibit 2
Documents solicitation efforts to obtain small and minority business participation for this project.
Due with bid/proposal.
8 Proposed Utilization Plan – Exhibit 3
Listing of the small and minority businesses that will participate on this project and their proposed contract dollar amounts.
Due with bid/proposal.
POST-AWARD DOCUMENTS
Item/Form SubmissionRequirements
9 Compliance Efforts
If the successful bidder/proposer, indicates the actions required to earnestly carry out the small and minority business utilization plan and document payments thereof.
n/a
10 Monthly Compliance Status Report – Exhibit 4
Certifies monthly usage and payments to small and minority businesses.
Due monthly after work commences throughout the life of the contract.
* NOTE: Projects involving Federal funds may have Disadvantaged Business Enterprise
(DBE) participation goals and requirements of 49 CFR Part 26, Regulations of the U.S.
Department of Transportation (USDOT), or other Federal requirements prescribed by the
U.S. Department of Agriculture (USDA) or U.S. Department of Housing and Urban
Development (HUD). Contractors submitting bids on such projects will also have to meet any outlined DBE Program requirements listed in the bid documents and submit items, including but not limited to, the following: (1) Certification of Contractor to Comply with
DBE Requirements; (2) DBE Letter of Intent and Affirmation; (3) DBE Contract Totals and
Percentage; and (4) Bidder’s List Questionnaire. For a current list of South Carolina DBE firms, please visit www.scdot.org and go to “Doing Business with SCDOT”, then see “Office of Business Development and Special Programs” and click on “DBE Directory”. Likewise, http://www.scdot.org/
IFB #060426 DOCUMENTS Page 18 any USDA and/or HUD requirements must be met in addition to Beaufort County’s requirements.
PROGRAM OVERVIEW
Introduction
Beaufort County recognizes that the South Carolina General Assembly, in South Carolina Code of
Laws Section 11-35-5210*, has declared that businesses owned and operated by minority persons have been historically restricted from full participation in our free enterprise system to a degree disproportionate to other businesses; and that it is in the state’s best interest to assist minority-owned businesses to develop fully as a part of the state’s policies and programs which are designed to promote balanced economic and community growth throughout the state. Therefore, Beaufort
County wishes to ensure that those businesses owned and operated by minorities are afforded the opportunity to fully participate in its overall procurement process for goods and services. Further, Beaufort County seeks to ensure that small businesses are likewise afforded the same participation opportunity as minority businesses. Consequently, attention of all bidders and proposers is called to contract conditions contained herein pertaining to Beaufort County’s “Small and Minority
Business Participation Program”, as prescribed in the Beaufort County Code of Ordinances
Section 2-537.2.
Definitions
Small Business means a for-profit concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on government contracts, and qualified as a small business under the criteria and size standards in the Code of Federal
Regulations, Title 13, Part 121, as amended. Beaufort County refers to these businesses as Small
Business Enterprises or “SBE”.
Minority Business means a concern at least fifty-one percent (51%) owned by a person determined to be socially and economically disadvantaged. Socially disadvantaged means those persons who have been subject to racial or ethnic prejudice or cultural bias because of their identification as members of a certain group without regard to their individual qualities. Such groups include, but are not limited to, Black Americans, Hispanic Americans, Native Americans (including American
Indians, Eskimos, Aleuts and Native Hawaiians), Asian Pacific Americans, women and other minorities to be designated by the Beaufort County Council. Economically disadvantaged means those socially disadvantaged persons whose ability to compete in the free enterprise system has been impaired due to diminished capital and credit opportunities as compared to others in the same business area that are not socially disadvantaged. Beaufort County refers to minority businesses as Minority Business Enterprises or “MBE”.
Small and Minority Business Enterprises will be abbreviated as “S/MBE”.
Provisions
The successful bidder or proposer, hereafter referred to as “Contractor”, is required to (1) make specific Pre-Award “Good Faith Efforts” to recruit S/MBE and (2) Post-Award “Compliance
IFB #060426 DOCUMENTS Page 19
Efforts” of its labors to utilize S/MBE, unless self-performing one hundred percent (100%) of the contract work. Falsification of any pre-award or post-award documents will be considered a serious breach of public trust and funds.
* SOUTH CAROLINA CODE OF LAWS, CHAPTER 35 “SOUTH CAROLINA
CONSOLIDATED PROCUREMENT CODE, SUBARTICLE 1 “ASSISTANCE TO
MINORITY BUSINESSES”
COMPLIANCE EFFORTS (POST-AWARD)
The successful Contractor is required to fulfill any Small and Minority Business Enterprise
(S/MBE) commitments made in conjunction with the “Pre-Award Good Faith Efforts”, unless good cause is demonstrated for any failure to fulfill such commitment.
If the Contractor intends to make any substitutions for any reasons, the Beaufort County
Compliance Office must be notified in writing within ten (10) business days for discussion and approval. No Contractor shall enter into an agreement with any S/MBE that would in any manner limit the S/MBE from selling or acting as a subcontractor to any other party.
Beaufort County shall have the right to inspect the Contractor’s records related to activity and expenditures to S/MBE utilized on its projects, to include related contracts/purchase orders and payment records, such as cancelled check copies. Further, designated Beaufort County personnel are permitted access to all work sites. Contractors and their staff should take measures to cooperate fully with all Beaufort County staff, including, but not limited to the Procurement Services
Director and Compliance Officer.
“Post-Award Compliance Efforts” require the Contractor to not only provide monthly reports regarding activity and expenditures to S/MBE, but also to maintain related records throughout the life of the project regarding its efforts to comply with the Small and Minority Business
Participation Program. The “Monthly Compliance Status Report” must be submitted to the
Compliance Office until the project ends, by the fifth (5th) day, reflecting the activity of the previous month.
After the County receives a monthly status report marked as “final”, the Contractor will be issued an affidavit to certify totals regarding S/MBE usage throughout the life of the project.
All questions regarding “Post-Award Compliance Efforts” should be directed to the Compliance
Office vie e-mail at dthomas@bcgov.net or (843) 255-2304.
VENDOR QUESTIONNAIRE
Certification*
I certify that this bid is made without prior understanding, agreement, or connection with any corporation, firm or any corporation, firm, or person submitting a bid for the same materials, supplies, or equipment, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this bid and certify that I am authorized by the firm to submit this bid.
IFB #060426 DOCUMENTS Page 20
☐ Please confirm
*Response required
Contact information of authorized representative?*
Please enter name, title, phone and email of the authorized representative:
*Response required
Please Provide Licenses and Certificate of Insurance*
*Response required
100% Labor and Material Payment Bond*
If awarded, you will be required to submit a 100% Labor and Material Payment Bond when requested.
Please note, this is NOT due at the time of bid submission.
☐ Please confirm
*Response required
Bidder Confirmation*
1. BIDDER has examined all Contract Documents including Addenda.
2. BIDDER understands and accepts the terms and conditions of the Invitation to Bid, Instructions to Bidders, and all other Contract Documents.
3. BIDDER having examined the plans and specifications with related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and supplies to construct the project in accordance with the contract documents, within the time set forth herein, and at the process stated below, proposed to enter into a contract with the County to provide the necessary machinery, tools, apparatus, all materials and labor, and other means of construction necessary to complete the Work. The undersigned proposes to furnish and construct the items listed in the attached Schedule of Items for the unit prices stated.
4. BIDDER agrees that the cost of any work performed, materials furnished, services provided or expenses incurred, which are not specifically delineated in the Contract
Documents, but which are incidental to the scope, intent, and completion of the Contract, shall be deemed to have been included in the prices bid for the various items scheduled.
☐ Please confirm
*Response required
Communications*
IFB #060426 DOCUMENTS Page 21
Communications concerning this Bid should be addressed to the BIDDER’s company, to the attention of:
Name:
Address:
Email:
Telephone:
*Response required
Are you submitting this bid as a local vendor?*
☐ Yes
☐ No
*Response required
When equals "Yes"
Local Vendor Preference - Participation Affidavit*
Please download the below documents, complete, and upload.
• Local_Vendor_Preference_-_P...
*Response required
Non-Collusion Affidavit of Prime Bidder*
Please download the below documents, complete, and upload.
• Non-Collusion_Affidavit_of_...
*Response required
Will you be using subcontractors?*
☐ Yes
☐ No
*Response required
When equals "Yes"
Non-Collusion Affidavit of Subcontractor*
Please download the below documents, complete, and upload.
• Non-Collusion_Affidavit_of_...
*Response required
Certification By Contractor Regarding Non-Segregated Facilities*
Please download the below documents, complete, and upload.
• Certification_By_Contractor...
https://government-project.s3.us-west-2.amazonaws.com/96409/f84b38b5-bce5-4d5d-a82e-e1fd2b3faba8_Local_Vendor_Preference_-_Participation_Affidavit.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4L4D2MPLI%2F20260520%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260520T182150Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjECoaCXVzLXdlc3QtMiJHMEUCIQDo11f6vyKBcOUdRRoiq5xHvZiPQ%2FND3RNEhBlSaaz75QIgXMHjaJrNjRYKjDSloRecLAQ2N0ueeMjzFXnvwlUbjvcqlQUI8%2F%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FARACGgw4OTIzNjQ2ODc2NzIiDOdE%2FZqtS%2BR3CSm0cSrpBHoNWdNW4K7kDMiKxWVuUx9AmBalUsgW3kYg3ru7Go0A8I6NYwJ7LTxqoZzraGLrzW5TE9WRpxTmesw3akkBJhPM9EoXbXQTdxbh4UdOBO%2FrwmcoXMEMns0U1Q9MFSvMHpEcCcXIKTLfmyxnXVU7HhnHSK%2BPHbir9wxdGYEPp8d0j3QFRgDdfhzmtg2DammraLYpiwXOsbaZp0RfMFaoOU2V4QB2ai6pefQxv9IWFiRIEIPOSuxkVlmcg2everqv9ckeRFYgdV6kNZWvIi8qU4D%2BG5u%2B4F2r8FeWoW%2BvyJEXscFqP%2Bp04So%2FfEhxroTdv8EhYepsVwzo0oEeg77qGNGJjOxdF0z3Y9MOXT8Rb2Go6syxA8XuwlvtK1Lx%2F1o6M%2FHDLgvEx%2FZ3Vm%2F3P02SJ5AcqAKRTOOq3T5gyJUsDjwCDQipRa58Xyr8cQXCf1VgBjNjlIl1Srx4Zev2LsiS6B1FskPQaF%2B2WNLboNysggw2BRcm69vZ7QoerBaESD9ldaiBMm8Q7Ipc75LshyaWNPU%2BgF3tRYcv81p5YnjEYLE8rieZkT1w91s6tl%2FdmsZuHJnr6AAQSWMSBHM%2B08Y4TpZr6QaXuFiRrknspVLgyWi1EsF%2BVrNq%2FIG%2BGalQnzE1mEnK68v7IWytIqZuTrgqHcF5HKyRibe1Sx8Bp70PkuNiSIsJl%2F9QWeU6d%2BtcGD%2BRI0nn1Odpt2jIZfWazi3Jx0NyITc%2Bl%2FU1ySoFEZ5h0mEffYLnh4KeMfK2SnvuvgFK5U6Pe5w8e2Sd2FZQzQWSlADaUpFdQi%2BYoA3rJOM9E7w6TzAnYR3un5x0MNLht9AGOpkBfTCsFCmSU64YVW9Fru8yan9Wpt%2FoBmjb12ZdXiDezksd3mJ1SdU8hVonu2gELPYlA2oj1DPisUhgrrxl0aWmewcw8LBeMyvt%2Fbl4UsYdRYzFxgmmBjZubOv47nAT4KBlpY4lBCNjl1e%2FUo7lJGMjJqqFlKHEK5Z0YjRIDBbiSGf8KtHBMTOSAyiKUSrPvzlMQkS74JmZhPF3&X-Amz-Signature=fdab0546bd5c245ff5f7f1b21d0d622562daa52c22acdf0a5dbf13281abac38a&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Local_Vendor_Preference_-_Participation_Affidavit.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/96409/2ac6bb9f-a974-4a14-a297-7d965488dba7_Non-Collusion_Affidavit_of_Prime_Bidder.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4L4D2MPLI%2F20260520%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260520T182150Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjECoaCXVzLXdlc3QtMiJHMEUCIQDo11f6vyKBcOUdRRoiq5xHvZiPQ%2FND3RNEhBlSaaz75QIgXMHjaJrNjRYKjDSloRecLAQ2N0ueeMjzFXnvwlUbjvcqlQUI8%2F%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FARACGgw4OTIzNjQ2ODc2NzIiDOdE%2FZqtS%2BR3CSm0cSrpBHoNWdNW4K7kDMiKxWVuUx9AmBalUsgW3kYg3ru7Go0A8I6NYwJ7LTxqoZzraGLrzW5TE9WRpxTmesw3akkBJhPM9EoXbXQTdxbh4UdOBO%2FrwmcoXMEMns0U1Q9MFSvMHpEcCcXIKTLfmyxnXVU7HhnHSK%2BPHbir9wxdGYEPp8d0j3QFRgDdfhzmtg2DammraLYpiwXOsbaZp0RfMFaoOU2V4QB2ai6pefQxv9IWFiRIEIPOSuxkVlmcg2everqv9ckeRFYgdV6kNZWvIi8qU4D%2BG5u%2B4F2r8FeWoW%2BvyJEXscFqP%2Bp04So%2FfEhxroTdv8EhYepsVwzo0oEeg77qGNGJjOxdF0z3Y9MOXT8Rb2Go6syxA8XuwlvtK1Lx%2F1o6M%2FHDLgvEx%2FZ3Vm%2F3P02SJ5AcqAKRTOOq3T5gyJUsDjwCDQipRa58Xyr8cQXCf1VgBjNjlIl1Srx4Zev2LsiS6B1FskPQaF%2B2WNLboNysggw2BRcm69vZ7QoerBaESD9ldaiBMm8Q7Ipc75LshyaWNPU%2BgF3tRYcv81p5YnjEYLE8rieZkT1w91s6tl%2FdmsZuHJnr6AAQSWMSBHM%2B08Y4TpZr6QaXuFiRrknspVLgyWi1EsF%2BVrNq%2FIG%2BGalQnzE1mEnK68v7IWytIqZuTrgqHcF5HKyRibe1Sx8Bp70PkuNiSIsJl%2F9QWeU6d%2BtcGD%2BRI0nn1Odpt2jIZfWazi3Jx0NyITc%2Bl%2FU1ySoFEZ5h0mEffYLnh4KeMfK2SnvuvgFK5U6Pe5w8e2Sd2FZQzQWSlADaUpFdQi%2BYoA3rJOM9E7w6TzAnYR3un5x0MNLht9AGOpkBfTCsFCmSU64YVW9Fru8yan9Wpt%2FoBmjb12ZdXiDezksd3mJ1SdU8hVonu2gELPYlA2oj1DPisUhgrrxl0aWmewcw8LBeMyvt%2Fbl4UsYdRYzFxgmmBjZubOv47nAT4KBlpY4lBCNjl1e%2FUo7lJGMjJqqFlKHEK5Z0YjRIDBbiSGf8KtHBMTOSAyiKUSrPvzlMQkS74JmZhPF3&X-Amz-Signature=9d49f76f8e85dce198c4ca19b078e4733998071024edeefe8db65adbc48fc9a3&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Non-Collusion_Affidavit_of_Prime_Bidder.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/96409/2570088f-aa3f-49d2-973c-93c896637c3d_Non-Collusion_Affidavit_of_Subcontractor.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4L4D2MPLI%2F20260520%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260520T182150Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjECoaCXVzLXdlc3QtMiJHMEUCIQDo11f6vyKBcOUdRRoiq5xHvZiPQ%2FND3RNEhBlSaaz75QIgXMHjaJrNjRYKjDSloRecLAQ2N0ueeMjzFXnvwlUbjvcqlQUI8%2F%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FARACGgw4OTIzNjQ2ODc2NzIiDOdE%2FZqtS%2BR3CSm0cSrpBHoNWdNW4K7kDMiKxWVuUx9AmBalUsgW3kYg3ru7Go0A8I6NYwJ7LTxqoZzraGLrzW5TE9WRpxTmesw3akkBJhPM9EoXbXQTdxbh4UdOBO%2FrwmcoXMEMns0U1Q9MFSvMHpEcCcXIKTLfmyxnXVU7HhnHSK%2BPHbir9wxdGYEPp8d0j3QFRgDdfhzmtg2DammraLYpiwXOsbaZp0RfMFaoOU2V4QB2ai6pefQxv9IWFiRIEIPOSuxkVlmcg2everqv9ckeRFYgdV6kNZWvIi8qU4D%2BG5u%2B4F2r8FeWoW%2BvyJEXscFqP%2Bp04So%2FfEhxroTdv8EhYepsVwzo0oEeg77qGNGJjOxdF0z3Y9MOXT8Rb2Go6syxA8XuwlvtK1Lx%2F1o6M%2FHDLgvEx%2FZ3Vm%2F3P02SJ5AcqAKRTOOq3T5gyJUsDjwCDQipRa58Xyr8cQXCf1VgBjNjlIl1Srx4Zev2LsiS6B1FskPQaF%2B2WNLboNysggw2BRcm69vZ7QoerBaESD9ldaiBMm8Q7Ipc75LshyaWNPU%2BgF3tRYcv81p5YnjEYLE8rieZkT1w91s6tl%2FdmsZuHJnr6AAQSWMSBHM%2B08Y4TpZr6QaXuFiRrknspVLgyWi1EsF%2BVrNq%2FIG%2BGalQnzE1mEnK68v7IWytIqZuTrgqHcF5HKyRibe1Sx8Bp70PkuNiSIsJl%2F9QWeU6d%2BtcGD%2BRI0nn1Odpt2jIZfWazi3Jx0NyITc%2Bl%2FU1ySoFEZ5h0mEffYLnh4KeMfK2SnvuvgFK5U6Pe5w8e2Sd2FZQzQWSlADaUpFdQi%2BYoA3rJOM9E7w6TzAnYR3un5x0MNLht9AGOpkBfTCsFCmSU64YVW9Fru8yan9Wpt%2FoBmjb12ZdXiDezksd3mJ1SdU8hVonu2gELPYlA2oj1DPisUhgrrxl0aWmewcw8LBeMyvt%2Fbl4UsYdRYzFxgmmBjZubOv47nAT4KBlpY4lBCNjl1e%2FUo7lJGMjJqqFlKHEK5Z0YjRIDBbiSGf8KtHBMTOSAyiKUSrPvzlMQkS74JmZhPF3&X-Amz-Signature=e5908fd3052079cb411ae3e48447be0661be2c8dd5eb86a40f55c2f9f7fe86f0&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Non-Collusion_Affidavit_of_Subcontractor.pdf%22&x-id=GetObject…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .